MONTHYEARML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24155A0882024-05-30030 May 2024 Email Summary of Verbal Authorization 1RR06 ML24150A3342024-05-29029 May 2024 Official RCIs for Susquehanna Proposed Alternative 1RR06 ML24087A0672024-04-22022 April 2024 Email to Melisa Krick Regarding Exemption Decision for Susquehanna ML24087A0682024-04-17017 April 2024 Email to Melisa Krick Regarding Availability of Environmental Assessment for the Susquehanna Exemption ML24106A0672024-04-12012 April 2024 State of Pennsylvania Input Review of Draft EA for Exemption Request for Susquehanna, Units 1 and 2 ML24103A0012024-04-11011 April 2024 – Summary of Verbal Authorization of 4RR-11 ML24102A1252024-04-10010 April 2024 Request for Additional Information for Susquehanna, Unit 1 Alternative Request 4RR-11 ML24106A0662024-04-10010 April 2024 Request for State Review of Draft EA for an Exemption Request for Susquehanna, Units 1 and 2 ML24082A0922024-03-21021 March 2024 Confirmation Email 3-21-2024 Regarding Exemption Request for Future Loading Only at Susquehanna ML24047A1232024-02-14014 February 2024 NRC Consultation with Commonwealth of PA Proposed NSHC for Susquehanna LAR TSTF-568 and TSF-563 Email ML24029A2732024-01-29029 January 2024 NRC Consultation with Commonwealth of Pennsylvania Re Proposed NSHC for Susquehanna License Amendment Request ML23352A2542023-12-18018 December 2023 NRC LIC-109 Acceptance Review Results for Susquehanna Steam Electric Station, License Amendment Request to Revise Technical Specifications (TS) to Adopt TSTF-568 ML23345A0542023-12-0808 December 2023 Email - NRC LIC-109 Acceptance Review Results for Susquehanna License Amendment Request to Revise Technical Specifications to Adopt TSTF-563 ML23334A1682023-11-30030 November 2023 NRC Request for Additional Information Re. Susquehanna Relief Request RR-01 ML23334A1502023-11-30030 November 2023 NRC Request for Additional Information Re. Susquehanna Relief Request RR-02 ML23242A2832023-08-30030 August 2023 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Susquehanna Steam Electric Station, Proposed Alternatives RR01 and RR02 (EPIDs L-2023-LLR-0043 and -0044) ML23230A0712023-08-18018 August 2023 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Susquehanna Steam Electric Station, Proposed Alternative for Valve 251130 ML23188A0802023-07-0707 July 2023 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Susquehanna Steam Electric Station, License Amendment Request to Revise Control Rod Technical Specifications ML23171A4312023-06-20020 June 2023 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Susquehanna Steam Electric Station, Proposed Alternative 5RR-02 ML23103A4702023-04-12012 April 2023 NRR E-mail Capture - Susquehanna Unit 2 - Verbal Authorization of Relief Request 4RR-10 ML23094A1242023-03-31031 March 2023 EN 56387 Update - Paragon Energy Solutions Final Notification of Defect of Automatic Transfer Switch ML23075A0492023-03-16016 March 2023 NRR E-mail Capture - Notification to the State of Pennsylvania Re. Susquehanna Steam Electric Station, Units 1 and 2 - Indirect License Transfer and Draft Conforming Amendments ML23073A1202023-03-14014 March 2023 NRR E-mail Capture - Evacuation Time Estimate Review ML23013A2082023-01-13013 January 2023 Request for Additional Information ML23012A0012023-01-11011 January 2023 NRC Notification to the State of Pennsylvania Re. Emergency Amendment Control Rod Technical Specifications ML22293A0882022-10-20020 October 2022 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Susquehanna License Transfer ML22257A1942022-09-14014 September 2022 NRR E-mail Capture - NRC Notification to the State of Pennsylvania Re. Susquehanna Steam Electric Station, Units 1 and 2 Amendment - Relocating Staff Qualification Requirements ML22213A2612022-08-0101 August 2022 NRR E-mail Capture - NRC Notification to the State of Pennsylvania Re. Susquehanna Steam Electric Station, Units 1 and 2 Amendment - Instrumentation and Control Technical Specifications ML22179A2902022-06-28028 June 2022 NRR E-mail Capture - NRC Notification to the State of Pennsylvania Re. Susquehanna Steam Electric Station, Units 1 and 2 Amendment - TSTF-505, Risk Informed Completion Times ML22146A0742022-05-25025 May 2022 NRR E-mail Capture - NRC Request for Additional Information - Susquehanna License Amendment Request ML22123A1112022-05-0303 May 2022 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Susquehanna Steam Electric Station, License Amendment Request to Relocate Staff Qualifications ML22111A3132022-04-21021 April 2022 NRR E-mail Capture - NRC Request for Additional Information - Susquehanna License Amendment Request ML22084A0222022-03-25025 March 2022 NRR E-mail Capture - Susquehanna Atrium-11 LAR Audit Report ML22038A1062022-02-0404 February 2022 NRR E-mail Capture - Susquehanna Steam Electric Station, Units 1 and 2 - Acceptance of Requested Licensing Action Application to Revise Technical Specifications to Adopt TSTF-564, Safety Limit MCPR ML22005A0712021-12-21021 December 2021 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Susquehanna 1 & 2 ECCS TS LAR ML21190A1702021-06-11011 June 2021 NRR E-mail Capture - NRC Notification to the State of Pennsylvania Regarding a Susquehanna Steam Electric Station, Unit 2 Amendment - Unit 1 Transformer Replacement ML21124A2022021-05-0404 May 2021 NRR E-mail Capture - Acceptance Review for Susquehanna TSTF-505 ML20343A3712020-12-0808 December 2020 NRR E-mail Capture - Corrected - Acceptance Review of Susquehanna RR 4RR-02 ML20343A3702020-12-0808 December 2020 NRR E-mail Capture - Acceptance Review of Susquehanna RR 4RR-02 ML20335A5732020-11-30030 November 2020 NRR E-mail Capture - Susquehanna -Acceptance Review Replacement of Unit 1 Transformers ML20283A7722020-10-0909 October 2020 Submittal of Pennsylvania Letter Requesting Exemption from Biennial Exercise Requirements for Pennsylvania Nuclear Power Plants in Calendar Year 2020 ML20261H4272020-09-17017 September 2020 NRR E-mail Capture - Corrected Acceptance Review for Susquehanna - Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements ML20261H4212020-09-16016 September 2020 NRR E-mail Capture - Corrected Acceptance Review for Susquehanna - Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements ML20195B1282020-07-13013 July 2020 NRR E-mail Capture - Acceptance Review for Susquehanna- Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules (EPID L-2020-Lla-0139) ML20178A6502020-06-26026 June 2020 Acceptance Review for Susquehanna - Revise Technical Specification 3.8.1 to Create a New Condition for an Inoperable Manual Synchronization Circuit ML20028F6352020-01-28028 January 2020 NRR E-mail Capture - Acceptance Review of LAR to Revise the Dose Consequence Analysis for a Loss of Coolant Accident ML19319A0092019-11-14014 November 2019 NRR E-mail Capture - Draft RAI for SSES Units 1 and 2 LAR to Replace ESW Piping ML19319B1922019-11-14014 November 2019 NRR E-mail Capture - RAI for Susquehanna, 1 and 2 License Amendment Request - Replace the Emergency Service Water System and Residual Heat Removal Service Water System ML19234A0342019-08-19019 August 2019 Acceptance Review: Susquehanna Units 1 and 2 License Amendment Request for Advanced Framatome Methodologies for Atrium 11 2024-09-04
[Table view] |
Text
From: Vaidya, Bhalchandra Sent: Monday, August 30, 2010 3:25 PM To: 'Coddington, Cornelius T'; 'Rochester, Margaret'; 'Crowthers, Michael H' Cc: Feliu, Luis; Wolfgang, Robert; McMurtray, Anthony; Salgado, Nancy
Subject:
ME 4068 & ME4069 - Draft Request for Additional Information, RR02 Revision 1 - MSRV Test Frequency Grace Period for 3rd 10-year IST
SUBJECT:
PPL Susquehanna, Units 1 and 2- DRAFT Request for Additional Information (RAI) RE: Relief Request RR-02, Extension of Testing Interval for MS SRVs (TAC NO. ME4068 & ME4069)
By letter dated June 1, 2010, you submitted relief requests RR-02, for the NRC approval to allow for the grace period of 6 months for the test frequency (in addition to the 6-year test frequency which was previously approved) for Main Steam Relief Valves PSV141F013A through H, J through N, P, R, and S (RR-02).
That staff of the Nuclear Reactor Regulation (NRR), Division of Component Integrity (DCI), Component Performance and Testing Branch (CPTB) has determined that additional information is needed to complete its review. The DRAFT RAI is provided below:
===========================================
RAI-RR-02-01 By letter dated June 1, 2010 (Accession No. ML101610805), the licensee requested NRC approval for Relief Request RR-02 Revision 1, to allow for a grace period of 6 months for the test frequency (in addition to the 6-year testing frequency which was previously approved) for MSRVs. The licensee stated that RR-02 Revision 1 is consistent with the grace period allowed by ASME Code Case OMN-17 (the six months grace period is not part of the previously approved Relief Request RR-02). ASME OM Code Case OMN-17 requires, in part, that disassembly and inspection of each valve after as-found set-pressure testing be performed to verify that parts are free of defects resulting from time-related degradation or service-induced wear. Also, ASME OM Code Case OMN-17 requires, in part, that each valve be disassembled and inspected in accordance with OMN-17 subparagraph (d) prior to the start of the 72-mo test interval.
The licensees request does not explain how these requirements are met.
Please provide your explanation as to how you meet the requirements in Code Case OMN-17 subparagraphs 1(b)(1), 1(b)(2), 1(d), and 1(e).
====================================
Please contact me ASAP to schedule a telephone conference between PPL Susquehanna and the NRC Staff to ensure that you clearly understand the NRC Staff request and to obtain the firm commitment for the supplemental submission with response to this request.
Bhalchandra K. Vaidya Licensing Project Manager NRC/NRR/DORL/LPL1-1 (301)-415-3308 (O) bhalchandra.vaidya@nrc.gov
E-mail Properties Mail Envelope Properties ()
Subject:
ME 4068 & ME4069 - Draft Request for Additional Information, RR02 Revision 1 - MSRV Test Frequency Grace Period for 3rd 10-year IST Sent Date: 08/30/2010 2:54:11 PM Received Date: 08/30/2010 3:24:00 PM From: Vaidya, Bhalchandra Created By: Bhalchandra.Vaidya@nrc.gov Recipients:
ctcoddington@pplweb.com ('Coddington, Cornelius T')
Tracking Status: None mrochester@pplweb.com ('Rochester, Margaret')
Tracking Status: None mhcrowthers@pplweb.com ('Crowthers, Michael H')
Tracking Status: None Luis.Feliu@nrc.gov (Feliu, Luis)
Tracking Status: None Robert.Wolfgang@nrc.gov (Wolfgang, Robert)
Tracking Status: None Anthony.McMurtray@nrc.gov (McMurtray, Anthony)
Tracking Status: None Nancy.Salgado@nrc.gov (Salgado, Nancy)
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 18665 08/30/2010 Options Expiration Date:
Priority: olImportanceNormal ReplyRequested: False Return Notification: False Sensitivity: olNormal Recipients received: