Reyes, Rogerio From:
Morrissey, ThomasV' Sent:
Sunday, October 11, 2009 10:26 PM To:
Chou, Rich Cc:
Sykes, Marvin; Reyes, Rogerio
Subject:
20 shift/1 0 day delay added to outage
- Rich, Just a heads up. Due to the redesign of the OTSB lift system, the licensee is expecting a 10 day delay for the design/fabrication/installation of the lift system and therefor any SG moves. We will have more details on Tuesday.
Tom Thomas Morrissey Nuclear Regulatory Commission Senior Resident Inspector Crystal River Nuclear Plant Offi rpL1127q' 7A7 Cell' (.b*)(6)L Page-r(352.621.845 T9