MONTHYEARIR 05000324/20253012024-10-17017 October 2024 Notification of Licensed Operator Initial Examination 05000325/2025301 and 05000324/2025301 IR 05000324/20244012024-10-15015 October 2024 Security Baseline Inspection Report 05000324/2024401 and 05000325/2024401 ML24297A6262024-10-11011 October 2024 PCA Letter to NRC Brunswick Potential Tropical Storm Eight IR 05000324/20240102024-09-10010 September 2024 Focused Engineering Inspection Commercial Grade Dedication Report 05000324-2024010 and 05000325-2024010 ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000324/20240052024-08-23023 August 2024 Updated Inspection Plan for Brunswick Steam Electric Plant, Units 1 and 2 (Report 05000324/2024005 and 05000325/2024005) IR 05000324/20240022024-08-0505 August 2024 Integrated Inspection Report 05000324/2024002 and 05000325/2024002 and 07200006/2024001 ML24206A1062024-07-30030 July 2024 2024 Brunswick Requal Inspection Corporate Notification Letter ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000324/20244202024-07-0202 July 2024 – Security Baseline Inspection Report 05000324/2024420 and 05000325/2024420 ML24108A0702024-06-0505 June 2024 – Issuance of License Amendments to Revise the 10 CFR 50.69 Categorization Process to Reflect an Alternative Seismic Approach IR 05000324/20244022024-05-17017 May 2024 Plan Material Control and Accounting Program Inspection Report 05000324/2024402 and 05000325/2024402 - Cover Letter IR 05000324/20240012024-05-0909 May 2024 Integrated Inspection Report 05000324/2024001 and 05000325/2024001 05000325/LER-2024-002, Re Automatic Start of Emergency Diesel Generator Due to Emergency Bus De-energization2024-04-10010 April 2024 Re Automatic Start of Emergency Diesel Generator Due to Emergency Bus De-energization 05000325/LER-2024-001, Primary Containment Penetration Local Leak Rate Testing Failure2024-04-10010 April 2024 Primary Containment Penetration Local Leak Rate Testing Failure ML24066A0132024-03-0505 March 2024 Bru 2024-002 Radiation Safety Baseline Inspection Information Request ML24026A0982024-03-0101 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0057 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000324/20230062024-02-28028 February 2024 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 – NRC Inspection Reports 05000324/2023006 and 05000325/2023006 IR 05000324/20244032024-02-14014 February 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perm Inspection 05000325/2024403; 05000324/2024403 ML24032A1392024-02-12012 February 2024 Correction of Errors within Authorized Alternative Request RA-22-0308 IR 05000324/20230042024-02-0606 February 2024 Integrated Inspection Report 05000324/2023004 and 05000325/2023004 IR 05000324/20230112023-12-26026 December 2023 NRC Fire Protection Team Inspection - FPTI Report 05000324/2023011 and 05000325/2023011 IR 05000324/20234022023-12-14014 December 2023 Security Baseline Inspection Report 05000324-2023402 and 05000325-2023402 ML23297A0262023-11-27027 November 2023 – Proposed Alternatives to ASME Code Section XI Subsection IWE Requirements for Torus Metallic Liner Inspections ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000324/20230032023-11-0101 November 2023 Integrated Inspection Report 05000324/2023003 and 05000325/2023003 IR 05000324/20230102023-10-17017 October 2023 Biennial Problem Identification and Resolution Inspection Report 05000324/2023010 and 05000325/2023010 IR 05000325/20234012023-10-16016 October 2023 Security Baseline Inspection Report 05000324 and 05000325 2023401 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000324/20230052023-08-23023 August 2023 Updated Inspection Plan for Brunswick Steam Electric Plant, Units 1 and 2 (Report 05000324/2023005 and 05000325/2023005) IR 05000324/20230022023-08-0404 August 2023 Integrated Inspection Report 05000324/2023002 and 05000325/2023002 ML23201A2042023-07-28028 July 2023 Summary of Regulatory Audit in Support of Alternative Request RA-22-0308 for Inservice Inspection of the Torus Metallic Liner IR 05000324/20243012023-07-25025 July 2023 – Notification of Licensed Operator Initial Examination 05000325/2024301 and 05000324/2024301 ML23212A9502023-05-24024 May 2023 Engine Systems, Inc., Part 21 Report Re Woodward EGB-35P Governor/Actuator with Foreign Material ML23146A0012023-05-24024 May 2023 EN 56538 - Engine Systems Inc and Brunswick ML23130A3902023-05-12012 May 2023 Regulatory Audit Plan in Support of Alternative Request RA 22-0308 for Inservice Inspection of the Torus Metallic Liner IR 05000324/20230012023-05-10010 May 2023 Integrated Inspection Report 05000324 2023001 and 05000325 2023001 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI IR 05000324/20220042023-04-0404 April 2023 Reissue - Brunswick Steam Electric Plant - Integrated Inspection Report 05000324/2022004 and 05000325/022004 ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000324/20220062023-03-0101 March 2023 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 NRC Inspection Reports 05000324/2022006 and 05000325/2022006 ML23033A5252023-02-0808 February 2023 Integrated Inspection Report 05000324/2022004 and 05000325/2022004 IR 05000324/20223012023-02-0303 February 2023 NRC Operator License Examination Report 05000325/2022301 and 05000324/2022301 IR 05000324/20224022022-11-23023 November 2022 Security Baseline Inspection Report 05000324 2022402 and 05000325 2022402 ML22332A0132022-11-23023 November 2022 Operator Licensing Written Examination Approval 05000325/2022301 and 05000324/2022301 ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 IR 05000324/20224032022-11-10010 November 2022 Cyber Security Inspection Report 05000324/2022403 and 05000325/2022403 2024-09-04
[Table view] |
Text
MichaelJ.I.Annacone Progress Energy Vice President Brunswick Nuclear Plant JUL 2 9-2010 SERIAL: BSEP 10-0093 10 CFR 50.90 TSC-2010-01
& TSC-2010-02 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Subject:
Brunswick Steam Electric Plant, Unit Nos. 1 and 2 Renewed Facility Operating License Nos. DPR-71 and DPR-62 Docket Nos. 50-325 and 50-324 Brunswick Unit 2 Cycle 20 Thermal-Hydraulic Design Report
References:
- 1. Letter from Michael J. Annacone to the U.S. Nuclear Regulatory Commission (Serial: BSEP 10-0052), "Request for License Amendment
-Addition of Analytical Methodology Topical Report to Technical Specification 5.6.5, "Core Operating Limits Report (COLR)," dated April 29, 2010 (ADAMS Accession Number ML 101310388)
- 2. Letter from Michael J. Annacone to the U.S. Nuclear Regulatory Commission (Serial: BSEP 10-0057), "Request for License Amendment
-Addition of Analytical Methodology Topical Report to Technical Specification 5.6.5, "Core Operating Limits Report (COLR)," dated April 29, 2010 (ADAMS Accession Number ML 101310389)
Ladies and Gentlemen:-
By letters dated April 29, 2010 (i.e., References 1 and 2), Carolina Power & Light Company (CP&L), now doing business as Progress Energy Carolinas, Inc., requested license amendments to revise the Technical Specifications (TS) for the Brunswick Steam Electric Plant (BSEP), Unit Nos. 1 and 2. The proposed license amendments revise Technical Specification 5.6.5.b by adding: (1) AREVA Topical Report ANP-10298PA, ACE/ATRIUM 1OXM Critical Power Correlation, Revision 0, March 2010, and (2) AREVA Topical Report BAW- 1 0247PA, Realistic Thermal-Mechanical Fuel Rod Methodology for Boiling Water Reactors, Revision 0, April 2008, to the list of analytical methods that have been reviewed and approved by the NRC for determining core operating limits.In these requests, CP&L stated that the Unit 2 Cycle 20 Thermal-Hydraulic Design Report would be provided to the NRC, for information, in August 2010. The thermal-hydraulic design report (i.e., ANP-2936(P), Revision 0, Brunswick Unit 2 Thermal-Hydraulic Design Progress Energy Carolinas, Inc.P0. Box 10429 Southport, NC 28461 T > 910.457.3698 Document Control Desk BSEP 10-0093 / Page 2 Report for ATRIUM T M 1 OXM Fuel Assemblies, dated July 2010) has been completed and is provided in Enclosure
- 1. ANP-2936(P), Revision 0, contains information that AREVA considers to be proprietary as defined by 10 CFR 2.390. AREVA, as the owner of the proprietary information, has executed the affidavit provided in Enclosure 2, which identifies that the enclosed proprietary information has been handled and classified as proprietary, is customarily held in confidence, and has been withheld from public disclosure.
AREVA requests that the enclosed proprietary information be withheld from public disclosure in accordance with the provisions of 10 CFR 2.390. A non-proprietary version of ANP-2936(P), Revision 0, is provided in Enclosure 3.No regulatory commitments are contained in this submittal.
Please refer any questions regarding this submittal to Ms. Annette Pope, Supervisor
-Licensing/Regulatory Programs, at (910) 457-2184.I declare, under penalty of perjury, that the foregoing is true and correct. Executed on July 29, 2010.Sincerely, Mi ael J. Annacone WRM/wrm
Enclosures:
- 1. AREVA Report ANP-2936(P), Revision 0, Brunswick Unit 2 Thermal-Hydraulic Design Report for ATRIUMTM 1 OXM Fuel Assemblies, dated July 2010 (Proprietary Information
-Withhold from Public Disclosure in Accordance With 10 CFR 2.390)2. AREVA Affidavit Regarding Withholding ANP-2936(P), Revision 0, from Public Disclosure
- 3. AREVA Report ANP-2936(NP), Revision 0, Brunswick Unit 2 Thermal-Hydraulic Design Report for ATRIUMTM ]OXM Fuel Assemblies, dated July 2010 Document Control Desk BSEP 10-0093 / Page 3 cc (with Enclosures 1, 2, and 3): U. S. Nuclear Regulatory Commission, Region II ATTN: Mr. Luis A. Reyes, Regional Administrator 245 Peachtree Center Avenue, NE, Suite 1200 Atlanta, GA 30303-1257 U. S. Nuclear Regulatory Commission ATTN: Mr. Philip B. O'Bryan, NRC Senior Resident Inspector 8470 River Road Southport, NC 28461-8869 U. S. Nuclear Regulatory Commission (Electronic Copy Only)ATTN: Mrs. Farideh E. Saba (Mail Stop OWFN 8G9A)11555 Rockville Pike Rockville, MD 20852-2738 cc (with Enclosures 2 and 3): Chair -North Carolina Utilities Commission P.O. Box 29510 Raleigh, NC 27626-0510 Mr. W..Lee Cox, III, Section Chief Radiation Protection Section North Carolina Department of Environment and Natural Resources 1645 Mail Service Center Raleigh, NC 27699-1645