Email from Franke, Mark to Cauffman, Christopher; Subject: Crystal River SIT (Containment)
ML102090390
Person / Time
Site: Crystal River Duke energy icon.png
Issue date: 01/12/2010
From: Mark Franke
NRC/RGN-II/DRS/EB3
To: Cauffmann C
NRC/NRR/DIRS/IRIB
References
FOIA/PA-2010-0116
Download: ML102090390 (1)


Text

Franke, Mark From: Franke, Mark Sent: Tuesday, January 12, 2010 3:58 PM To: Cauffman, Christopher Cc: Haskell, Russell

Subject:

RE: Crystal River SIT (Containment)

Hi Chris, We do not have an exit date set.

Two SIT Charter items depend on a licensee root cause analysis and a corrective action.

5. Assess the licensee's activities related to the problem investigation (e.g., root cause analysis, extent of condition, etc).
6. Assess the licensee's corrective action/"fix" in addressing the containment delamination issue.

The licensee hopes to have a root cause by end of January and hopes to have a repair (corrective action) plan sometime in February.

Based on the current schedule, the SIT public exit would most likely be in March.

From: Cauffman, Christopher 1"'*

Sent: Tuesday, January 12, 2010 3:36 PM To: Franke, Mark Cc: Haskell, Russell

Subject:

Crystal River SIT (Containment)

Franke, With regards to the Crystal River SIT:

What date did we do the exit meeting or what date do we plan on exiting, if known?

Respectfully, Chris C. Cauffman U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Division of Inspection & Regional Support NRR/ADRO/DIRS/IRIB Office: O-07E09 Mail Stop: 0-07C2A 301-415-8416 (Voice) 301-415-3061 (Fax) christopher.cauffman@nrc.gov 75