liT' Kuntz, Robert From:
Sent:
To:
Subject:
Attachments:
Saba, Farideh I*.Z*
Tuesday, December 15, 2009 9:44 AM Kuntz, Robert; Bernardo, Robert FYI: CR3 Root Cause Information 2009 Dec 11 - Root Cause Update for NRC.pptx I --
Farideh E. Saba, P.E.
Senior Project Manager N RC/ADRO/N RR/DORL 301-415-1447 Mail Stop O-8G9A Farideh.Saba@NRC.GOV From: McCabe, Brian [mailto: Brian.McCabe@pgnmail.com]
Sent: Monday, December 14, 2009 7:29 AM To: Sykes, Marvin; Franke, Mark; Wert, Leonard; Kennedy, Kriss; Saba, Farideh; Orf, Tracy
Subject:
CR3 Root Cause Information As we discussed lastThursday, the root cause investigative work (not the report) is scheduled to be completed by 12/28.
Brian
/