UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406.1415 July 26, 2010 Mr. George H. Gellrich, Site Vice President Constellation Energy Nuclear Group, LLC Calvert Cliffs Nuclear Power Plant, LLC 1650 Calvert Cliffs Parkway Lusby, Maryland 20657-4702
SUBJECT:
OPERATOR LICENSING EXAMINATION APPROVAL CALVERT CLIFFS NUCLEAR POWER PLANT
Dear Mr. Gellrich:
The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing examinations at Calvert Cliffs.
The NRC has completed its review of the operator license applications submitted in connection with this examination and separately provided a list of approved applicants to Mr. Marl< Draxton, Manager, Nuclear Training Department. Note that any examination waivers and application denials hi3ve been addressed in separate correspondence.
The NRC has approved the subject examinations and hereby authorizes you to administer the written examinations in accordance with NUREG-1021, "Operator Licensing Examinations Standards for Power Reactors," Revision 9, Supplement 1, on August 11, 2010. The NRC staff will administer the operating tests during the weeks of August 2 and 9, 2010.
This examination has undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this review I have concluded that the examination meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG-1021 guidelines, and is appropriate for measuring the qualifications of licensed operator applicants at your facility. If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at (610) 337-5046.
Please contact your Chief Examiner, Peter Presby, at 610-337-5392, if you have any questions or identify any errors or changes in the license level (RO or SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant.
Sincerely, Samuel L. Hansell, Chief Operations Branch Division of Reactor Safety Docket No. 050-317/318 cc: Distribution via ListServ
Mr. George H. Gellrich. Site Vice President Constellation Energy Nuclear Group, LLC Calvert Cliffs Nuclear Power Plant, LLC 1650 Calvert Cliffs Parkway Lusby, Maryland 20657-4702
SUBJECT:
OPERATOR LICENSING EXAMINATION APPROVAL CALVERT CLIFFS NUCLEAR POWER PLANT
Dear Mr. Gellrich:
The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing examinations at Calvert Cliffs.
The NRC has completed its review of the operator license applications submitted in connection with this examination and separately provided a list of approved applicants to Mr. Mark Draxton, Manager, Nuclear Training Department. Note that any examination waivers and application denials have been addressed in separate correspondence.
The NRC has approved the subject examinations and hereby authorizes you to administer the written examinations in accordance with NUREG-1021, "Operator Licensing Examinations Standards for Power Reactors," Revision 9, Supplement 1, on August 11,2010. The NRC staff will administer the operating tests during the weeks of August 2 and 9, 2010.
This examination has undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this review I have concluded that the examination meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG-1021 guidelines, and is appropriate for measuring the qualifications of licensed operator applicants at your facility. If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at (610) 337-5046.
Please contact your Chief Examiner, Peter Presby, at 610-337-5392, if you have any questions or identify any errors or changes in the license level (RO or SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant.
Sincerely, IRA!
Samuel L. Hansell, Chief Operations Branch Division of Reactor Safety Docket No. 50-317/50-318 cc: Distribution via ListServ Distribution w/encl:
M. Oapas, Acting RA D. Lew. Acting DRA J. Clifford, DRP D.Collins, DRP O. Roberts. DRS P. Wilson. OHS L. Trocine. RI OEDO SUNSI Review Complete:
SLH ADAMS PKG: ML100560028 G. Dentel, DRP N. Perry, ORP J. Hawkins. ORP S. Sloan, DRP S. Kennedy, ORP, SRI M. Osborn. DRP. RI C. Newgent. ORP, OA D. Bearde. DRS (Reviewer'S Initials)
ADAMS ACC #ML102070208 RidsNrrPMCalvertCliffs Resource RidsNrrDorlLpl1-1 Resource ROPreportsResourca@nrc,gov P. Presby, DRS, Chief Examiner C. Bixler. DRS S. Hansell, DRS DOCUMENT NAME: G:\\ORS\\Operations Branch\\PRESBy\\Exam FY10-CC Aug 10(U01770)\\ExamApprovaILtr.doc After declaring this document "An OffiCial Agency Record" it will be released to the Public.
To receive a copy of this document, indicate in the box: "c n = Copy without attachment/enclosure "ER = Copy-with attachment/enclosure "N" = No copy OFFICE RlfDRS/OB I
RI/DRS/OB I
RIIDRS/OB I
I I
NAME CJBixler/CJB PAPresby/PAP SLHanseli/SLH DATE 07/23/10 07/23/10 07/23/10 OFFICIAL RECORD COpy