Letter Sequence Approval |
---|
|
|
MONTHYEARML1020005942010-02-24024 February 2010 Email Draft RAI for Temporary Exemption from 50.46 and App. K Project stage: Draft RAI ML1020005812010-02-24024 February 2010 Email Draft RAI for Temporary Exemption from 50.46 and App. K Project stage: Draft RAI ML1014102622010-05-12012 May 2010 Response to Request for Additional Information Regarding the Request for Temporary Exemption from the Provisions of 10 CFR 50.46 and 10 CFR 50, Appendix K for Lead Fuel Assemblies Project stage: Response to RAI ML1019002802010-08-17017 August 2010 Cover Letter, Environmental Assessment and Finding of No Significant Impact Exemption from the Provisions of 10 CFR 50.46 and 10 CFR 50, Appendix K for Lead Fuel Assemblies Project stage: Approval ML1019002872010-08-17017 August 2010 Environmental Assessment and Finding of No Significant Impact Exemption from the Provisions of 10 CFR 50.46 and 10 CFR 50, Appendix K for Lead Fuel Assemblies Project stage: Approval ML1019002542010-08-26026 August 2010 Cover Letter, Exemption from the Provisions of 10 CFR 50.46 and 10 CFR 50, Appendix K for Lead Fuel Assemblies Project stage: Approval ML1019002962010-08-26026 August 2010 Exemption from the Provisions of 10 CFR 50.46 and 10 CFR 50, Appendix K for Lead Fuel Assemblies Project stage: Approval NRC-2010-0281, Exemption from the Provisions of 10 CFR 50.46 and 10 CFR 50, Appendix K for Lead Fuel Assemblies2010-08-26026 August 2010 Exemption from the Provisions of 10 CFR 50.46 and 10 CFR 50, Appendix K for Lead Fuel Assemblies Project stage: Approval 2010-05-12
[Table View] |
|
---|
Category:Environmental Assessment
MONTHYEARML19205A2732019-08-19019 August 2019 Environmental Assessment for the Exemption Request for Arizona Public Service Company'S Palo Verde Nuclear Generating Installation in Wintersburg, Arizona ML19120A1982019-04-26026 April 2019 Enclosufinal Environmental Assessment (Memo to File Environmental Assessment and Finding of No Significant Impact for Arizona Public Service Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 73.30(b) ...) ML1019002802010-08-17017 August 2010 Cover Letter, Environmental Assessment and Finding of No Significant Impact Exemption from the Provisions of 10 CFR 50.46 and 10 CFR 50, Appendix K for Lead Fuel Assemblies ML1019002872010-08-17017 August 2010 Environmental Assessment and Finding of No Significant Impact Exemption from the Provisions of 10 CFR 50.46 and 10 CFR 50, Appendix K for Lead Fuel Assemblies ML0825404722008-09-26026 September 2008 Environmental Assessment and Finding of No Significant Impact, Request for Temporary Exemption from 10 CFR 50.46 and Part 50 Appendix K for Lead Fuel Assemblies 2019-08-19
[Table view] Category:Federal Register Notice
MONTHYEARML24130A0012024-05-16016 May 2024 April 2024, Issuance of Multiple Exemptions Regarding Security Notifications, Reports, and Recording Keeping ML24114A3102024-05-0303 May 2024 Monthly (28-Day) Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 14, 2024 ML23166B0852023-07-0606 July 2023 FRN: for Issuance of Exemption ML23045A3112023-03-15015 March 2023 Order Extending the Effectiveness of the Approval of the Indirect Transfer of the Co-Owner Licenses from Public Service Company of New Mexico to Avangrid, Inc. (EPID L-2022-LLO-0000) (FRN) ML22146A1872022-06-0101 June 2022 FRN for Issuance of Exemption ML22101A2572022-05-11011 May 2022 Order Extending the Effectiveness of the Approval of the Indirect Transfer of the Co-Owner Licenses from Public Service Company of New Mexico to Avangrid, Inc. (EPID L-2022-LLO-0000) (FRN) ML22054A0072022-03-24024 March 2022 Exemption from the Requirements of 10 CFR 50.62 to Delete Diverse Auxiliary Feedwater Actuation System Using Risk-Informed Process for Evaluations (EPID L 2022 Lle 0004) FRN ML22034A9832022-02-15015 February 2022 FRN - Notice of Issuance of COVID-19 Exemptions Issued in January 2022 ML22003A1042022-01-26026 January 2022 The Independent Spent Fuel Storage Installation - Order Approving Indirect Transfer of Control of Licenses (EPID L 2021 LLM 0002) (FRN) ML21307A1332021-11-17017 November 2021 The Independent Spent Fuel Storage Installation - Order Approving Transfers of Control of Licenses for Minority Interests Subject to Expiring Leases (Superseding Order of October 21, 2021) (FRN) ML21307A1312021-11-17017 November 2021 The Independent Spent Fuel Storage Installation - Order Approving Transfers of Control of Licenses for Minority Interests Subject to Expiring Leases (EPID L-2021-LLM-0003) (Letter) ML21245A0662021-10-21021 October 2021 The Independent Spent Fuel Storage Installation - Order Approving Transfers of Control of Licenses for Minority Interests Subject to Expiring Leases (EPID L-2021-LLM-0003) (FRN) ML21245A0642021-10-21021 October 2021 The Independent Spent Fuel Storage Installation - Order Approving Transfers of Control of Licenses for Minority Interests Subject to Expiring Leases (EPID L-2021-LLM-0003) (Letter) ML21245A0652021-10-21021 October 2021 The Independent Spent Fuel Storage Installation - Order Approving Transfers of Control of Licenses for Minority Interests Subject to Expiring Leases (EPID L-2021-LLM-0003) (Order) ML21165A0542021-06-23023 June 2021 Letter, Notice of Consideration of Approval of Application Proposed Transfer of Control of Licenses and Opportunity to Request a Hearing ML21165A0562021-06-23023 June 2021 FRN - Notice of Consideration of Approval of Application Proposed Transfer of Control of Licenses and Opportunity to Request a Hearing ML21118B0292021-05-25025 May 2021 Order Approving Indirect Transfer of Licenses for Units 1, 2, and 3, and the Independent Spent Fuel Storage Installation (EPID L-2020-LLM-0002) (Order) ML21118B0312021-05-25025 May 2021 FRN - Order Approving Indirect Transfer of Licenses for Units 1, 2, and 3, and the Independent Spent Fuel Storage Installation ML21106A1502021-04-28028 April 2021 ISFSI - FRN - Notice of Consideration of Approval of Application Regarding Proposed Indirect License Transfer and Opportunity to Request a Hearing ML21106A1482021-04-28028 April 2021 ISFSI - Letter - Notice of Consideration of Approval of Application Regarding Proposed Indirect License Transfer and Opportunity to Request a Hearing ML21028A0122021-02-18018 February 2021 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for January 2021 ML21011A2492021-01-21021 January 2021 ISFSI, Letter - Notice of Consideration of Approval of Application Regarding Proposed Indirect License Transfer and Opportunity for a Hearing ML21011A2592021-01-21021 January 2021 ISFSI, FRN - Notice of Consideration of Approval of Application Regarding Proposed Indirect License Transfer and Opportunity for a Hearing ML20335A0902020-12-21021 December 2020 Federal Register Notice - November 2020 COVID-19 Exemptions ML20119A5242020-05-0707 May 2020 FRN: Notice of Issuance of Multiple Exemptions Regarding 10 CFR Part 26 (COVID-19) ML20035C4082020-02-18018 February 2020 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 02/25/2020 ML19213A0342019-08-23023 August 2019 Federal Register Notice: Palo Verde Nuclear Generating Station Independent Spent Fuel Storage Installation - Issuance of Exemption ML19205A2742019-08-19019 August 2019 Federal Register Notice: Palo Verde Nuclear Generating Station ISFSI - Environmental Assessment and Finding of No Significant Impact; Issuance ML19122A2102019-05-15015 May 2019 Federal Register Notice: Palo Verde Independent Spent Fuel Storage Installation - Environmental Assessment and Finding of No Significant Impact; Issuance NRC-2018-0277, Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Consideration and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Publication Date: January2018-12-13013 December 2018 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Consideration and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Publication Date: January 8, 2 ML18334A2202018-12-13013 December 2018 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Consideration and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Publication Date: January 8, 2 ML18295A7442018-10-25025 October 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 11/06/18 NRC-2017-0175, Biweekly Sholly Report - Federal Register Notice Fr Publication Date: August 15, 20172017-08-0404 August 2017 Biweekly Sholly Report - Federal Register Notice Fr Publication Date: August 15, 2017 ML17213A1842017-08-0404 August 2017 Biweekly Sholly Report - Federal Register Notice Fr Publication Date: August 15, 2017 NRC-2016-0202, Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 27, 20162016-09-19019 September 2016 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 27, 2016 ML16257A5172016-09-19019 September 2016 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 27, 2016 NRC-2016-0161, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 16, 20162016-08-0303 August 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 16, 2016 ML16215A2272016-08-0303 August 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 16, 2016 NRC-2016-0100, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 24, 20162016-05-13013 May 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 24, 2016 ML16131A7952016-05-13013 May 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 24, 2016 ML16061A3012016-03-0202 March 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: March 15, 2016 NRC-2015-0269, Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: December 8, 20152015-11-27027 November 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: December 8, 2015 ML15328A5502015-11-27027 November 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: December 8, 2015 ML15252A1102015-09-11011 September 2015 Letter, Newspaper Notice, Exigent License Amendment Request to Amend Technical Specification Surveillance Requirement 3.1.5.3 for Control Element Assembly 88 for the Remainder of Cycle 19 ML13018A2392015-04-0808 April 2015 G20110171 - Letter to Petitioner Saporito on Proposed Director'S Decision Regarding 2.206 Petition Dated: March 12, 2011 ML14177A6452014-06-27027 June 2014 Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations ML14059A1812014-03-0707 March 2014 FRN - Withdrawal of License Amendment Request to Revise Technical Specifications; Eliminate Use of the Term Core Alteration Consistent w/TSTF-471 and NUREG-1432, Rev 3 ML13225A5572013-08-12012 August 2013 Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit ML13228A3992013-08-12012 August 2013 Letter to Holders of Independent Spent Fuel Storage Installation (ISFSI) Licenses Re Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit - Rin 3150-AI64 (NRC-2009-0163) EA-02-109 NRC-2012-0067, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status2012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status 2024-05-03
[Table view] Category:Finding of No Significant Impact
MONTHYEARML1019002802010-08-17017 August 2010 Cover Letter, Environmental Assessment and Finding of No Significant Impact Exemption from the Provisions of 10 CFR 50.46 and 10 CFR 50, Appendix K for Lead Fuel Assemblies ML1019002872010-08-17017 August 2010 Environmental Assessment and Finding of No Significant Impact Exemption from the Provisions of 10 CFR 50.46 and 10 CFR 50, Appendix K for Lead Fuel Assemblies 2010-08-17
[Table view] Category:Letter
MONTHYEARML24295A0362024-10-23023 October 2024 Regulatory Audit Plan in Support of Relief Request No. 71; Resubmittal of Relief Request-30 IR 05000528/20244022024-10-22022 October 2024 Security Baseline Inspection Report 05000528/2024402 and 05000529/2024402 and 05000530/2024402 ML24296B2142024-10-22022 October 2024 Transmittal of Valve Relief Request (VRR) - 02: Alternative Request Allowing Normally Closed Valves with a Safety Function to Close to Be Exercise Tested Once Per Refueling Cycle ML24296B2152024-10-22022 October 2024 Transmittal of Valve Relief Request (VRR) - 03: Alternative Request Allowing Removal of the Lower Acceptance Criteria Threshold from Solenoid-Operated Valves ML24296B2172024-10-18018 October 2024 Submittal of Unit 1 Core Operating Limits Report, Revision 34, Unit 2 Core Operating Limits Report, Revision 26, and Unit 3 Core Operating Limits Report, Revision 3 ML24292A2192024-10-18018 October 2024 Core Operating Limits Report Revision 34, 26 and 33 ML24292A0322024-10-17017 October 2024 Th Refueling Outage Steam Generator Tube Inspection Report ML24285A2562024-10-11011 October 2024 License Renewal - Alloy 600 Management Program Plan Response to Request for Additional Information IR 07200044/20244012024-10-0808 October 2024 Independent Spent Fuel Storage Installation Security Inspection Report 07200044/2024401 ML24269A1542024-09-27027 September 2024 Summary of Presubmittal Meeting with Arizona Public Service Company to Discuss Proposed Life-of-Plant Alternatives for a Pressurizer Thermowell Nozzle Repair at Palo Verde Nuclear Generating Station, Unit 1 ML24262A0972024-09-23023 September 2024 Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000529/2024011) ML24241A2542024-08-28028 August 2024 Inservice Inspection Request for Information ML24241A2782024-08-28028 August 2024 License Amendment Request to Revise the Technical Specifications 3.5.1 and 3.5.2 Safety Injection Tank Pressure Bands, and to Use GOTHIC Code ML24240A2682024-08-27027 August 2024 Transmittal of Technical Specification Bases Revision 79 IR 05000528/20240052024-08-22022 August 2024 Updated Inspection Plan for Palo Verde Nuclear Generating Station - Units 1, 2, and 3 (Report 05000528/2024005, 05000529/2024005, 05000530/2024005) 05000530/LER-2024-001-01, Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation2024-08-21021 August 2024 Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation ML24208A0612024-08-20020 August 2024 Issuance of Amendment Nos. 224, 224, and 224 Regarding Revision to Technical Specifications 3.5.1, 3.5.2 and 3.6.5 IR 05000528/20244042024-08-0808 August 2024 Cybersecurity Inspection Report 05000528/2024404, 05000529/2024404 and 05000530/2024404 ML24213A3232024-07-31031 July 2024 Transmittal of Relief Request (RR) No. 71: Re-Submittal of RR-30 ML24213A3292024-07-31031 July 2024 Transmittal of Relief Request (RR) No. 72: Re-Submittal of RR-39 IR 05000528/20240022024-07-29029 July 2024 Integrated Inspection Report 05000528/2024002 and 05000529/2024002 and 05000530/2024002 ML24173A3302024-07-24024 July 2024 Pressurizer Surge Line Inspection Program ML24159A4702024-07-17017 July 2024 Issuance of Amendment Nos. 223, 223, and 223 Revision to Technical Specifications 3.5.1 and 3.5.2 Using Risk Informed Process for Evaluations ML24198A0662024-07-16016 July 2024 Program Review - Simulator Testing Methodology ML24193A3442024-07-11011 July 2024 Fourth 10-Year Interval, Second Period Owner’S Activity Report Number 3R24 ML24129A0522024-07-0303 July 2024 Review of the Spring 2023 Steam Generator Tube Inspection Report IR 05000528/20240042024-06-25025 June 2024 Notification of Inspection (NRC Inspection Report 05000528/2024004, 05000529/2024004, 05000530/2024004) 05000530/LER-2024-002, Invalid Specified System Actuation of Train B Emergency Diesel Generator2024-06-25025 June 2024 Invalid Specified System Actuation of Train B Emergency Diesel Generator ML24177A3212024-06-25025 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Transportable Storage Canisters Identification Numbers AMZDFX180, AMZDFX181, AMZDFX182 Vertical Concrete Cask Identification Nu ML24177A3222024-06-25025 June 2024 Invalid Specified System Actuation of Train B Emergency Diesel Generator ML24170A9962024-06-18018 June 2024 Response to Second Request for Additional Information to Revise Technical Specifications (TS) 3.5.1, Safety Injection Tanks (Sits) – Operating, TS 3.5.2, Safety Injection Tanks (Sits) – Shutdown a ML24129A2062024-06-14014 June 2024 Issuance of Amendment Nos. 222, 222, and 222 Revision to Technical Specifications to Adopt TSTF-266-A 05000530/LER-2024-001, Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation2024-06-0505 June 2024 Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation ML24159A0262024-06-0303 June 2024 Annual Report of Guarantee of Payment of Deferred Premium 05000529/LER-2024-001, Valid Specified System Actuations of Unit 2 Train B Emergency Diesel Generator and Train B Auxiliary Feedwater2024-05-23023 May 2024 Valid Specified System Actuations of Unit 2 Train B Emergency Diesel Generator and Train B Auxiliary Feedwater ML24135A2482024-05-14014 May 2024 Response to Second Request for Additional Information to Proposed Method to Manage Environmentally Assisted Fatigue for the Pressurizer Surge Line ML24164A2582024-05-0909 May 2024 10-PV-2024-04 Post-Exam Comments ML24129A1482024-05-0707 May 2024 And Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Casks with Applied Changes ML24128A2702024-05-0707 May 2024 Docket Nos. Stn 50-528/529/530 - Response to NRC Regulatory Issue Summary (RIS) 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000528/20240012024-05-0202 May 2024 Independent Spent Fuel Storage Installation, Integrated Inspection Report 05000528/2024001, 05000529/2024001, 05000530/2024001, 07200044/2024001, and Exercise of Enforcement Discretion ML24119A0022024-04-26026 April 2024 2023 Annual Environmental Operating Report ML24116A2082024-04-24024 April 2024 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report 2023 ML24109A0712024-04-22022 April 2024 NRC Initial Operator Licensing Examination Approval 05000528/2024301, 05000529/2024301, and 05000530/2024301 IR 05000528/20244012024-04-22022 April 2024 Security Baseline Inspection Report 05000528/2024401 and 05000529/2024401 and 05000530/2024401 (Cover Letter) ML24112A0012024-04-19019 April 2024 Core Operating Limits Report, Revision 32 ML24108A1982024-04-16016 April 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Casks with Applied Changes Authorized by an Amended Certificate of Compliance ML24103A2482024-04-12012 April 2024 Emergency Core Cooling System Performance Evaluation Models, 10 CFR 50.46(a)(3)(ii) Annual Report for 2023 ML24131A0972024-04-10010 April 2024 Annual Radiological Environmental Operating Report 2023 ML24096A2202024-04-0505 April 2024 Transmittal of Technical Specification Bases Revision 78 ML24032A1542024-04-0303 April 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) 2024-09-27
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 17, 2010 Mr. Randall K. Edillgton Executive Vice President Nuclear/
Chief Nuclear Officer Mail Station 7602 Arizona Public Service Company P.O. Box 52034 Phoenix, AZ 85072-2034
SUBJECT:
PALO VERDE NUCLEAR GENERATING STATION, UNIT 3 ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT (TAC NO. ME2590)
Dear Mr. Edington:
Enclosed is a copy of the Environmental Assessment and Finding of No Significant Impact related to your application for temporary exemption dated November 2, 2009, as supplemented by letter dated May 12, 2010 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML093160596 and ML101410262, respectively). The proposed temporary exemption would allow up to eight lead fuel assemblies with Optimized ZIRLOTM to be inserted into the Unit 3 core during the fall 2010 refueling outage. The temporary exemption would allow the lead fuel assemblies to be used for up to three operating cycles (Cycles 16, 17, and 18).
The assessment is being forwarded to the Office of the Federal Register for publication.
Sincerely, James R. Hall, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. STN 50-530
Enclosure:
Environmental Assessment cc w/encl: Distribution via Listserv
[7590-01-P]
NUCLEAR REGULATORY COMMISSION
[NRC-2010-XXXX]
Arizona Public Service Company Docket No. STN 50-530 Palo Verde Nuclear Generating Station, Unit 3 Environmental Assessment and Finding of No Significant Impact The U.S. Nuclear Regulatory Commission (NRC) is considering issuance of a temporary exemption from the requirements of Title 10 of the Code of Federal Regulations, Part 50 (10 CFR 50), Section 50.46, "Acceptance criteria for emergency core cooling systems for light-water nuclear power reactors," and 10 CFR 50, Appendix K, "ECCS Evaluation Models," for Facility Operating License No. NPF-74, issued to Arizona Public Service Company (APS, the licensee),
for operation of Palo Verde Nuclear Generating Station (PVNGS), Unit 3, located in Maricopa County, Arizona. Therefore, as required by 10 CFR 51.21, the NRC has performed an environmental assessment. Based on the results of the environmental assessment, the NRC is issuing a finding of no significant impact.
ENVIRONMENTAL ASSESSMENT Identification of the Proposed Action:
The proposed action would permit the use of fuel rods with Optimized ZIRLOTM cladding to be inserted into PVNGS, Unit 3's core for Operating Cycles 16, 17, and 18. Since the requirements in 10 CFR 50.46, specifically, and 10 CFR 50, Appendix K, implicitly, refer to the use of zircaloy or ZIRLO cladding, a temporary exemption is required to allow the use of fuel
-2 rods clad with an advanced zirconium-based alloy that is neither zircaloy nor ZIRLO. The temporary exemption would allow up to eight lead fuel assemblies (LFAs) manufactured by Westinghouse with fuel rods clad with Optimized ZIRLOTM to be inserted into the PVNGS, Unit 3 core during the fall 2010 refueling outage. The temporary exemption would allow the LFAs to be used for up to three operating cycles (Cycles 16, 17, and 18).
The proposed action is in accordance with the licensee's application dated November 2, 2009 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML093160596), as supplemented by letter dated May 12, 2010 (ADAMS Accession No. ML101410262).
The Need for the Proposed Action:
The proposed temporary exemption is needed by APS, as explained in its application dated November 2, 2009, in order lito evaluate cladding for future fuel assemblies that may need to be of a more robust design than current fuel assemblies to allow for possible higher duty and/or extended burnup." The regulations specify standards and acceptance criteria only for fuel rods clad with zircaloy or ZIRLO. Consistent with 10 CFR 50.46, a temporary exemption is required to use fuel rods clad with an advanced alloy that is not zircaloy or ZIRLO. Therefore, the licensee needs a temporary exemption to insert up to eight LFAs containing Optimized ZIRLOTM cladding material into the PVNGS Unit 3 core for up to three cycles of operation.
Environmental Impacts of the Proposed Action:
The NRC has completed its evaluation of the proposed action and concludes that the proposed exemption will not present any undue risk to the public health and safety. The NRC approved Westinghouse Electric Company LLC (Westinghouse) topical reports, WCAP-16500 P-A Revision 0, liCE [Combustion Engineering] 16x16 Next Generation Fuel Core Reference Report" (Proprietary), dated August 2007, and WCAP-12610-P-A and CENPD-404-P-A,
- 3 "Optimized ZIRLOTM" (Proprietary), dated July 2006, have demonstrated that predicted chemical, mechanical, and material performance characteristics of the Optimized ZIRLOTM alloy cladding are bounded by those approved for zircaloy under anticipated operational occurrences (AOOs) and postulated accidents. The LFAs shall be placed in non-limiting core regions as required by PVNGS, Unit 3 Technical Specification 4.2.1, "Fuel Assemblies." Also, APS and Westinghouse utilize NRC approved methods for the reload design process for the PVNGS reload cores containing Optimized ZIRLOTM fuel rod cladding. Therefore, the environmental impact, due to the unlikely event of an LFA clad failure, would be minimal and would be bounded by the environmental impacts associated with previous accident analyses.
The details of the NRC staff's safety evaluation will be provided in the exemption that will be issued as part of the letter to the licensee approving the exemption to the regulation.
The proposed action will not significantly increase the probability or consequences of accidents. No changes are being made in the types of effluents that may be released offsite.
There is no significant increase in the amount of any effluent released offsite. There is no significant increase in occupational or public radiation exposure. Therefore, there are no significant radiological environmental impacts associated with the proposed action.
Based on the nature of the exemption, the proposed action does not result in changes to land use or water use, or result in changes to the quality or quantity of non-radiological effluents. No changes to the National Pollution Discharge Elimination System permit are needed. No effects on the aquatic or terrestrial habitat in the vicinity or the plant, or to threatened, endangered, or protected species under the Endangered Species Act, or impacts to essential fish habitat covered by the Magnuson-Stevens Act are expected. There are no impacts to the air or ambient air quality. There are no impacts to historic and cultural resources. There would be no noticeable effect on socioeconomic conditions in the region.
-4 Therefore, no changes or different types of non-radiological environmental impacts are expected as a result of the proposed action. Accordingly, the NRC concludes that there are no significant environmental impacts associated with the proposed action.
Environmental Impacts of the Alternatives to the Proposed Action:
As an alternative to the proposed action, the staff considered denial of the proposed action (Le., the "no-action" alternative). Denial of the application would result in no change in current environmental impacts. The environmental impacts of the proposed action and the alternative action are similar.
Alternative Use of Resources:
The action does not involve the use of any different resources than those previously considered in the Final Environmental Statement for the Palo Verde Nuclear Generating Station, NUREG-0841, dated February 1982.
Agencies and Persons Consulted:
In accordance with its stated policy, on July 8, 2010, the NRC staff consulted with the Arizona State official, Aubrey Godwin of the Arizona Radiation Regulatory Authority regarding the environmental impact of the proposed action. The State official had no comments.
FINDING OF NO SIGNIFICANT IMPACT On the basis of the environmental assessment, the NRC concludes that the proposed action will not have a significant effect on the quality of the human environment. Accordingly, the NRC has determined not to prepare an environmental impact statement for the proposed action.
For further details with respect to the proposed action, see the licensee's letter dated November 2, 2009, as supplemented by letter dated May 12, 2010. Documents may be
-5 examined, and/or copied for a fee, at the NRC's Public Document Room (PDR), located at One White Flint North, Public File Area 01 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records will be accessible electronically from the Agencywide Documents Access and Management System (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, http://www.nrc.gov/reading-rm/adams.html. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS should contact the NRC PDR Reference staff by telephone at 1-800-397-4209 or 301-415-4737, or send an e-mail to pdr.resource@nrc.gov.
h Dated at Rockville, Maryland, this 1i day of August 2010.
FOR THE NUCLEAR REGULATORY COMMISSION k~ *
- Nageswaran Kalyanam, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Allgust 17, 2010 Mr. Randall K. Edington Executive Vice President Nuclearl Chief Nuclear Officer Mail Station 7602 Arizona Public Service Company P.O. Box 52034 Phoenix, AZ 85072-2034
SUBJECT:
PALO VERDE NUCLEAR GENERATING STATION, UNIT 3 ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT (TAC NO. ME2590)
Dear Mr. Edington:
Enclosed is a copy of the Environmental Assessment and Finding of No Significant Impact related to your application for temporary exemption dated November 2, 2009, as supplemented by letter dated May 12, 2010 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML093160596 and ML101410262, respectively). The proposed temporary exemption would allow up to eight lead fuel assemblies with Optimized ZIRLOTM to be inserted into the Unit 3 core during the fall 2010 refueling outage. The temporary exemption would allow the lead fuel assemblies to be used for up to three operating cycles (Cycles 16, 17, and 18).
The assessment is being forwarded to the Office of the Federal Register for publication.
Sincerely, IRA by N. Kalyanam fori James R. Hall, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. STN 50-530
Enclosure:
Environmental Assessment cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsNrrPMPaloVerde Resource LPLIV rlf RidsNrrLA~IBurkhardt Resource RidsAcrsAcnw_MailCTR Resource RidsOgcRp Resource RidsNrrDlrRerb Resource RidsRgn4MailCenter Resource RidsNrrDorlLpl4 Resource ADAMS Accession Nos. Letter ML101900280, EA FRN ML101900287 OFFICE DORLlLPL4/PM DORL/LPL4/PM DORLlLPL4/LA NRRIDLR/RERB/BC OGC DORLlLPL4/BC DORULPL4/PM MMarkley JRHall NAME LKGibson JRHali JBurkhardt Almboden LSubin CFLyon for NKalyanam for DATE 7/14/2010 7/20/2010 7/14/10 8/5/10 8/9/10 8/17/10 8/17/10 OFFICIAL RECORD COpy