ES-301 Administrative Topics Outline Form ES-301-1 Facility: WATERFORD 3 Date of Examination: March 16, 2010 Examination Level: RO Operating Test Number: NRC Exam Administrative Topic Type Describe activity to be performed (see Note) Code*

2.1.18, Ability to make accurate, clear, and concise A1 S, N logs, records, status boards, and reports.

Conduct of Operations Complete OP-903-001, Technical Specification Surveillance Logs, Attachment 11.9, Adjustment of FC1.

K/A Importance:

3.6 A2 S/R, M 2.1.23 Ability to perform specific system and Conduct of Operations integrated plant procedures during all modes of plant operation.

K/A Importance: Complete Attachment 11.1, Manual CEA Subgroup 4.3 Selection of OP-004-15, Reactor Power Cutback System.

A3 R, M 2.2.41, Ability to obtain and interpret station electrical Equipment Control and mechanical drawings.

Identify system effects and boundaries for electrical K/A Importance: component isolation.

3.5 A4 S/R, M 2.3.11 Ability to control radiation releases.

Radiation Control Determine if meteorological conditions permit release of a Gas Decay Tank.

K/A Importance:

3.8 Emergency Plan Not selected NOTE: All items (5 total are required for SROs. RO applicants require only 4 items unless they are retaking only the administrative topics, when 5 are required.

  • Type Codes & Criteria: (C)ontrol room, (S)imulator, or Class(R)oom (D)irect from bank ( 3 for ROs;  4 for SROs & RO retakes)

(N)ew or (M)odified from bank ( 1)

(P)revious 2 exams ( 1; randomly selected)

Revision 12

ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: WATERFORD 3 Date of Examination: March 16, 2010 Exam Level (circle one): RO Operating Test No.: NRC Control Room Systems@ (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)

System / JPM Title Type Code* Safety Function S1 004 Chemical and Volume Control System A, M, E, L, S 1 Perform Emergency Boration with 2 stuck CEAs in accordance with OP-901-103, Emergency Boration.

Fault: Gravity Feed Valve BM-113 A will fail to open, requiring Boration with the Boric Acid Makeup Pumps.

S2 006 Emergency Core Cooling System D L, S 2 Evaluate the need and establish simultaneous hot and cold leg injection in accordance with OP-902-002, Loss of Coolant Accident Recovery.

S3 010 Pressurizer Pressure Control System A, N, S 3 Perform OP-903-118, section 7.10 to cycle Pressurizer Spray valves.

Fault: During manipulation of the second spray valve, a Pressurizer pressure instrument will fail high, requiring action to remove it from service.

S4 045 Main Turbine Generator System N, L, S 4-S Break Main Condenser Vacuum on Turbine Trip due to high vibration in accordance with OP-901-210, Turbine Trip S5 028 Hydrogen Recombiner and Purge Control System D, L, S 5 Start Hydrogen Recombiner A in accordance with OP-008-006.

S6 035 Steam Generator System A, M, L, S 4-P Stabilize RCS Temperature with an Excess Steam Demand Event in accordance with OP-902-004, Excess Steam Demand Recovery.

Fault: Emergency Feedwater controller will fail to control, requiring operator to use the alternate controller.

S7. 012 Reactor Protection System D, L, S 7 Reset CSAS in accordance with OP-902-009, Standard Appendices, Section 5 - E S8 008 Component Cooling Water System N, L, S 8 Start CCW Pump AB in accordance with OP-901-311, Loss of Train B Safety Bus with 3AB Bus aligned to the faulted train.

1 Revision 4

ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 In-Plant Systems@ (3 for RO; 3 for SRO-I; 3 or 2 for SRO-U)

P1 041 Steam Dump System and Turbine Bypass Control A, D, L 4-S Operate Atmospheric Dump Valve B locally in accordance with OP-005-004, Main Steam.

Fault: The local pneumatic control station will not function, requiring use of the local handwheel.

P2 062 A.C. Electrical Distribution N 6 Transfer SUPS MD from Alternate to Normal AC Power in accordance with OP-006-005, Inverters and Distribution.

P3 004 Chemical and Volume Control System M, E, L, R 1 Perform the BOP Operator Time Critical Actions of OP-901-502, Evacuation of Control Room and Subsequent Plant Shutdown, steps 4 and 5 to start Emergency Diesel Generator B and align Boric Acid Gravity Feed.

@ All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.

  • Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room (D)irect from bank 9/8/4 (E)mergency or abnormal in-plant 1/1/1 (EN)gineered safety feature - / - / 1 (control room system)

(L)ow-Power / Shutdown 1/1/1 (N)ew or (M)odified from bank including 1(A) 2/2/1 (P)revious 2 exams 3 / 3 / 2 (randomly selected)

(R)CA 1/1/1 (S)imulator 2 Revision 4