ML101310049
| ML101310049 | |
| Person / Time | |
|---|---|
| Site: | Vermont Yankee File:NorthStar Vermont Yankee icon.png |
| Issue date: | 05/20/2010 |
| From: | Borchardt R NRC/EDO |
| To: | Hodes P US HR (House of Representatives) |
| Boska J, NRR, 301-415-2901 | |
| Shared Package | |
| ML101310044 | List: |
| References | |
| G20100235, LTR-10-0175, SECY-2010-0210 | |
| Download: ML101310049 (70) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 20, 2010 The Honorable Paul W. Hodes United States House of Representatives Washington, DC 20515-2902
Dear Congressman Hodes:
On behalf of the U.S. Nuclear Regulatory Commission (NRC), I am responding to your letter dated April 19, 2010, about tritium leaks at the Vermont Yankee Nuclear Power Station (Vermont Yankee). Your letter is available from the NRC's Agencywide Documents Access and Management System (ADAMS) in the public Electronic Reading Room on the NRC Web site at http://www.nrc.gov/reading-rm/adams.htmlunderADAMSAccessionNo.ML101120663. With your agreement, the NRC has processed your letter as a petition for enforcement action under Title 10 of the Code of Federal Regulations (10 CFR), Section 2.206, "Requests for Action under this Subpart."
Your petition requested that the NRC not allow Vermont Yankee, operated by Entergy Nuclear Operations, Inc. (Entergy or the licensee), to restart after its scheduled refueling outage until all environmental remediation work and relevant reports on leaking tritium at the plant have been completed. Specifically, your petition requested that Vermont Yankee be prevented from resuming power production until the following work has been completed to the Commission's satisfaction: (1) the tritiated groundwater remediation process; (2) the soil remediation process scheduled to take place during the refueling outage, to remove soil containing not only tritium, but also radioactive isotopes of cesium, manganese, zinc, and cobalt; (3) Entergy's ongoing Root Cause Analysis; and (4) the Commission's review of the documents presented by Entergy in response to the Commission's demand for information, which was issued on March 1, 2010.
This petition was assigned to the NRC's Office of Nuclear Reactor Regulation (NRR). NRR's Petition Review Board (PRB) met on May 3,2010, and made an initial recommendation to accept this petition for review. Your staff was informed of this decision. On May 14, 2010, you submitted supplemental information (ADAMS Accession No. ML101370031) by letter to the PRB. Any supplemental information which is pertinent to the petition will be considered by the PRB during the development of the Director's Decision on the petition. The PRB's final recommendation is to accept the petition for review, but deny your immediate action request to prohibit restart of Vermont Yankee based upon our determination that the licensee has identified the source of the leak, stopped the leak, and taken actions to prevent recurrence of contamination from this source. We have determined that the licensee has the equipment, facilities, people. and procedures in place to continue to safely operate the plant. The status of our reviews and conclusions to address your concerns and our basis for reasonable assurance of safety are explained in detail below.
NRC inspectors have been closely reviewing Entergy's actions to terminate and remediate the leakage of radioactive material from the plant. On February 27, 2010, following excavation and leak testing of the Advanced Off Gas (AOG) system pipe tunnel, it was reported that leakage had been identified into the surrounding soil and groundwater from an unsealed joint in the concrete tunnel wall. The AOG pipe tunnel is located about 15 feet underground. Entergy determined that piping inside the tunnel was leaking, and the drain inside the tunnel was
P. Hodes
- 2 clogged. Soil samples in the vicinity showed traces of radioactive isotopes that are associated with reactor water. Entergy reported to the NRC that the leakage from the plant had been stopped by isolating piping and containing the water leaking from the AOG pipe tunnel. NRC inspectors independently reviewed groundwater sample results which support the licensee's conclusion that this was the source of the leakage. The inspectors will continue to review the licensee's monitoring and remediation activities associated with this leak.
On March 23, 2010, Entergy installed an extraction well (GZ-EW1). On April 7, 2010, Entergy placed in service a second extraction well (GZ-EW1A), with a higher flow capacity. About 55,000 gallons of groundwater has been pumped out of these wells in order to reduce the amount of tritiated water in the groundwater. The water is being stored in above-ground containers until it can be filtered, processed, and either reused in the plant or disposed of properly. This pumping operation has resulted in significant decreases in the tritium measured in monitoring wells located near the source of the leak. There is a plume of tritiated groundwater extending from the source of the leak to the Connecticut River. The NRC inspections indicate that no NRC regulatory limits have been or are likely to be exceeded, and there are no health or safety concerns for members of the public or plant workers.
The soil in the vicinity of the leak was also contaminated with small amounts of radioactive nuclides associated with nuclear plant operations, including manganese-54, cobalt-50, zinc-55, and cesium-137. Sampling indicated very little migration away from the immediate area, which is typical for these radionuclides. Approximately 128 cubic feet of contaminated soil has been removed, and is being packaged for disposal at a licensed disposal facility. Although some minor amounts of contaminated soil may remain, NRC inspections indicate that it poses no threat to public health and safety. Areas of minor contamination are typically remediated during plant decommissioning. The NRC experience with decommissioning nuclear plants such as Maine Yankee, Haddam Neck, and Yankee Rowe indicate that these areas can be successfully remediated during plant decommissioning. Again, there are no health or safety concerns for members of the public or plant workers.
As part of Entergy's corrective action program, Entergy is performing a root cause analysis (RCA) of the leakage event. Upon Entergy's completion of the RCA, the NRC will assess the comprehensiveness of the RCA and document our assessment in a separate NRC inspection report. In the meantime, NRC inspectors have independently assessed Entergy's activities associated with determining the root cause of the occurrence. In addition, the network of over 20 monitoring wells installed at Vermont Yankee are capable of detecting any additional leakage.
On March 1, 2010, the NRC issued to Entergy a Demand for Information (DFI) (ADAMS Accession No. ML100570237), requiring Entergy to confirm that communications over the past 5 years to the NRC by certain Entergy employees, that were material to NRC-regulated activities, were complete and accurate. The NRC issued the DFI after Entergy verbally informed the NRC, on February 24, 2010, that some employees at Vermont Yankee had been removed from their site positions and placed on administrative leave as a result of Entergy's independent internal investigation into alleged contradictory or misleading information provided to the State of Vermont that was not corrected. Entergy provided its response to the NRC on March 31, 2010 (ADAMS Accession No. ML100910420). The NRC staff continues to review the DFI response, and the results of the review will be made public.
P. Hodes
- 3 After reviewing the information from the extensive NRC actions to date, the NRR Director, in consultation with the Region I Regional Administrator, has concluded that there are no issues that would lead the NRC to prohibit Entergy from restarting Vermont Yankee from its current outage. The NRC has reasonable assurance that the health and safety of the public, as well as the environment, are being protected and there are no immediate safety concerns. NRR management will review the NRC staff's evaluation of the issues identified in your petition to ensure that Entergy is taking appropriate action in response to the abnormal plant leakage.
NRC inspectors continue to closely observe and review Entergy's actions. The Director of NRR will issue the final Director's Decision on your petition. We will continue to communicate with you and your staff concerning developments at Vermont Yankee, and we will ensure that you receive NRC inspection documents related to the topics in your petition as they are completed.
As required by 10 CFR 2.206, the NRC will take action on your petition within a reasonable time. John Boska has been assigned as the petition manager for your petition. He can be reached at 301-415-2901. I have enclosed for your information a copy of the notice that the NRC is filing with the Office of the Federal Register for publication. I have also enclosed for your information a copy of Management Directive 8.11, "Review Process for 10 CFR 2.206 Petitions," and the associated brochure NUREG/BR-0200, "Public Petition Process," prepared by the NRC Office of Public Affairs.
Sincerely,
~"-~t R. W. Borchardt Executive Director for Operations Docket No. 50-271
Enclosures:
- 1. Federal Register Notice
- 3. NUREG/BR-0200 cc: Listserv
7590-01-P U.S. NUCLEAR REGULATORY COMMISSION ENTERGY NUCLEAR OPERATIONS, INC.
ENTERGY NUCLEAR VERMONT YANKEE, LLC VERMONT YANKEE NUCLEAR POWER STATION DOCKET NO. 50-271 LICENSE NO. DPR-28 RECEIPT OF REQUEST FOR ACTION UNDER 10 CFR 2.206 Notice is hereby given that by petition dated April 19, 2010, Congressman Paul W.
Hodes (the Petitioner) has requested that pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Section 2.206, "Requests for Action under this Subpart," the U.S.
Nuclear Regulatory Commission (NRC) take action with regard to the Vermont Yankee Nuclear Power Station (Vermont Yankee). The Petitioner requested that the NRC not allow Vermont Yankee, operated by Entergy Nuclear Operations, Inc. (Entergy or the licensee), to restart after its scheduled refueling outage until all environmental remediation work and relevant reports on leaking tritium at the plant have been completed. Specifically, the Petitioner requested that Vermont Yankee be prevented from resuming power production until the following work has been completed to the Commission's satisfaction: (1) the tritiated groundwater remediation process; (2) the soil remediation process scheduled to take place during the refueling outage, to remove soil containing not only tritium, but also radioactive isotopes of cesium, manganese, zinc, and cobalt; (3) Entergy's ongoing Root Cause Analysis; and (4) the Commission's review of the documents presented by Entergy in response to the Commission's demand for information, which was issued on March 1, 2010.
- 2 The NRC is treating the request under 10 CFR 2.206 of the Commission's regulations.
The request has been referred to the Director of the Office of Nuclear Reactor Regulation (NRR). By letter dated May 20, 2010, the Director denied the Petitioner's request to maintain Vermont Yankee shut down. As provided by 10 CFR 2.206, the NRC will take appropriate action on this petition within a reasonable time.
A copy of the petition is available to the public from the NRC's Agencywide Documents Access and Management System (ADAMS) in the public Electronic Reading Room on the NRC Web site at http://www.nrc.gov/reading-rm/adams.htmlunder ADAMS Accession No. ML101120663, and is available for inspection at the Commission's Public Document Room, located at One White Flint North, 11555 Rockville Pike (first floor), Rockville, Maryland.
Dated at Rockville, Maryland this 20th day of May, 2010.
FOR THE NUCLEAR REGULATORY COMMISSION E~L~
Office of Nuclear Reactor Regulation Management Directive 8.11 Review Process for 10 CFR 2.206 Petitions ADAMS Accession No. ML041770328
u.s. NUCLEAR REGULATORY COMMISSION
.r To:
Subject*
Purpose:
Office and Division of Origin:
Contact:
Date Approved:
Volume:
Directive:
Availability:
TN: DT-00-20 NRC Management Directives Custodians Transmittal of Directive 8.11, "Review Process for 10 CFR 2.206 Petitions" Directive and Handbook 8.11 are being revised to address stakeholder feedback and to improve clarity.and make the' handbook easier to use. There are three major changes to the handbook: (1) the addition ofan opportunityfor petitioners to address the Petition Review Board after it discusses the petition; (2) the deletion of criteria for technical meetings with the petitioners; and (3) the additionof arequirement to request comments from the petitioner(s) and affected licensee(s) on the proposed director's decision, with associated steps to resolve, and document the resolution of, those comments.
Office of Nuclear Reactor Regulation Andrew J. Kugler, (301) 415-2828 or Donna Skay, (301) 415-1322 July 1, 1999 (Revised: October 25,2000) 8 Licensee Oversight Programs 8.11 Review Process for 10 CFR 2.206 Petitions Rules and Directives Branch Office ofAdministration.
David L Meyer, (301) 415-7162 or Doris Mendiola, (301) 415-6297 OFFICE OF ADMINISTRATION
TN: DT-00-20 Significant Changes to the Management Directive 8.11 Review Process for 10 CFR 2.206 Petitions The entire document has been revised to improve clarity and make it easier to use. In particular, the handbook is now written with actions in chronological order. In addition to those general changes, the following significant changes have been made:
- Addition of an opportunity for the petitioner to address the Petition Review Board (pRB) after the PRB has developed its recommendations on the petition. This meeting orteleconference issimilarto those alreadyofferedto petitionersbeforethe PRBmeets.
- Removal of specific restrictions on the amount of time allowed for petitioners to address the PRB and also*allow petitioners to be assisted by a reasonable number of representatives.
V
- Deletion of the criteria for meetings between the petitioner and the staff. The staffwill hold these meetings whenever the staff feels it will be beneficial to its review.
- Addition of a process by which the staff requests and resolves comments from the petitioner and the licensee on the proposed director's decision (i.e., before it issigned).
The comments and the staff's resolution become part of the director's decision.
'. Revision of the timeliness goal to 120 days from the date of the acknowledgment letter until the date the proposeddirector'sdecisionissent out for comment. Add anew goal of 45 days from the end of the comment period until the director's decision is signed.
- Addition of a process flow chart and a petition manager's checklist to assist staff persons involved with petitions.
2
.'J Review Process for 10 CFR 2.206 Petitions Directive 8.11
Volume 8, Licensee Oversight Programs ReviewProcess for 10 CFR 2.206 Petitions
'Directive 8.11 Contents Policy. ~........................................................ 1 Objectives 1
Organizational Responsibilities and Delegations ofAuthority 2
Executive Director for Operations (EDO) 2 General Counsel (GC)..................................................
2 Office Directors
"............... 2 Regional Administrators 3
2.206 PRB Chairperson
~............................
3 Associate Directors - Office of Nuclear Reactor Regulation (NRR) 4 Division Directors......................................................
4 Director, Division of Licensing Project Management (DLPM),
Office of Nuclear Reactor Regulation (NRR) 4 V
Applicability
".............................. 4 Handbook 4
Definitions 4
References...................................................... 5 Approved: July 1, 1999 (Revised: October 2~; 2000) iii
- u. S. Nuclear Regulatory Commission
..Volume: 8 Licensee Oversight Programs NRR Review Process for 10 *CFR 2.206 Petitions Directive 8.11 Policy (8.11-01)
It is the policy ofthe U.S. Nuclear Regulatory Commission to provide members of the public with the means to request that the Commission take enforcement-related action (i.e., to modify, suspend, or revoke a license, or for other. appropriate. enforcement-related action, as distinguishedfrom actions such as licensing or rulemaking). This policy iscodified at Section 2.206ofTitle 10of the CodeofFederalRegulations (10 CFR 2.206). The Commission may grant a request for action, in whole or in part, take other action that satisfies the concerns raised by the requester, or deny the request. Requests that raisehealth andsafety and other concernswithout requestingenforcement-related actionwill be reviewed by means other than the 10 CfR 2.206 process.
Objectives (8.11-02)
- "Io ensure the public he~lth and safety, through the prompt and thorough evaluation of' any potential problem addressed by a petition filed under 10 CPR 2.206. (021)
- !'O provide for appropriate participation by a petitioner in, and observation by the public of,; NRC's. decisionmaking activities related to a 10 CFR 2.206 petition. (022) 1 4
~'
- To ensure effective, communication with the petitioner and other stakeholders on the' status of the petition, including providing relevant documents and notification of interactions between the NRC staff and a licensee or certificate holder relevant to the petition. (023),.
Approved: July 1, 1999 (Revised: October 25, 2000) 1
______________________________---Jl.
IL Volume 8, Licensee Oversight Programs ReviewProcess for 10 CFR 2.206 Petitions Directive 8.11 Organizational Responsibilities and Delegations ofAuthority (8.11-03)
Executive Director for Operations (EDO)
(031)
Receives and assigns action for all petitions filed under 10 CFR 2206.
General Counsel (GC)
(032)
- Conducts legal reviews and provides advice on 10 CFR 2.206 petitions and, uponspecificrequestfrom the staffin special cases or where the petition raises legal issues, reviews drafts of director's decisions. (a)
- Provides legal advice to the Commission, EDO, office directors, and staff on other matters related to the 10 CFR 2.206 process. (b)
\\...J Office Directors (033)
- Have overall responsibility for assigned petitions. Because 10 CFR 2.206 petitions request enforcement-related action, petitions are assigned to the Office ofNuclear Reactor Regulation, the Office of Nuclear Material Safety and Safeguards, the Office' of Enforcement, or the Office of the General Counsel. Therefore, most of the actions described in this directive and the associated handbook apply only to those.offices. (a)
- Approve or deny a petitioner's request for immediate action. (b)
- Sign acknowledgment letters,FederalRegister notices and director's decisions. (c)
- Provide up-to-date information for the monthly status report on all assigned petitions. (d)
- Appoint a petition review board (PRB) chairperson. (e)
- . Designate a petition manager for each petition. (f)
Approved: July 1,1999.
2 (Revised: October 25, 2000)
Volume,8, Licensee Oversight Programs
,ReviewProcess for 10 CFR 2.206 Petitions Directive 8.11' Office Directors (033) (continued)
- Promptlynotify (1) the Office ofInvestigations ofany allegation of wrongdoing by a licensee or certificate holder, applicant for a license or certificate, their Contractors, or their vendors or (2) the Office ofthe Inspector General of any allegation ofwrongdoing by an NRC staff person or NRC contractor, that is contained in a petition they may receive. (g)
- Provide a draft of, each director's decisions to the Office of Enforcement for review. (h)
- Designate an office coordinatorfor 2.206 petitions, if applicable. (i)
Regional Administrators (034)
- As needed, provide support and informationfor the preparation of an acknowledgment letter and/or a director's decision on a 2.206 petition. (a)
- Make the petitionmanageraware ofinformation that is received or that is the subject of any correspondence relating to a pending petition. (b)
- Participate, as necessary, in meetingswith the petitionerandpublic, in technical review ofpetitions and in deliberations ofthe PRB. (c) 2.206 PRB Chairperson (035)
Each office that is assigned a petition will appoint a PRB chairperson, generally a Senior Executive Service manager, who will-
- Convene PRB meetlngs.ja) '.
~.
- Ensure appropriate review of all.new petitions in a timely manner. (b)
- Ensure appropriate documentation ofPRB meetings. (c)
- Convene periodic PRB meetings with the petition managers to discuss the status of open petitions and to provide guidance for timely resolution. (d)
Approved: July 1, 1999 (Revised: October 25, 2000) 3
Volume 8, Licensee Oversight Programs ReviewProcess for 10 eFR 2.206 Petitions Direettve 8.11 Associate Directors Office of Nuclear Reactor Regulation (NRR)
(036)
Concur in each extension request from petition managers in their organization and forward the extension request to the Office of the EDO for approval.
Division Directors (037)
Concur in each extension request from petition managers in their organization and forward the extension request to the Office of the EDO (Associate Director for NRR) for approval.
Director, Division of Licensing Project Management (DLPM),
Office of Nuclear Reactor Regulation (NRR)
(038)
Appoints the Agency 2.206 Petition Coordinator, normally a DLPM staff person.
"--.J Applicability (8.11-04)
The policy and guidance in this directive and handbook apply to all NRC employees.
Handbook (8.11-05)
Handbook 8.11details the procedures for staff review and disposition of petitions submitted under Section 2.206.
Definltlons (8.11-06)
A 10 CFR2.206Petition. A written request filed by anyperson that the Commission modify, suspend, or revoke a license, or take any other enforcement-relatedaction thatmaybe proper. The request mustmeet the criteria for review under 10 CFR 2.206 '(see Part III of Handbook 8.11).
Licensee. Throughout the handbook, any references to a licensee shall be interpreted to include certificate holders; applicants for licenses or certificates, or other affected parties.'
..'-...J Approved: July 1, 1999 (Revised: October 25, 2000),
4
Volume 8, Licensee Oversight Programs ReviewProcess for 10 CFR 2.206'Petitions Directive 8.11 References (8.11-07)
Code ofFederal Regulations 10 CFR 2.206, "Requests for Action Under This Subpart."
10 CFR 2.790, "Public Inspections, Exemptions, Requests for Withholding."
10 CFR 2.1205, "Request for a hearing; petition for leave to intervene."
Management Directives 3.5, "PublicAttendance at Certain Meetings Involving the NRC Staff."
8.8, "Management of Allegations."
12.6, "NRC Sensitive Unclassified Information Security Program."
Memorandum of Understanding Between the NRC and the Department of Justice, December 12, 1988.
"Nuclear Regulatory Commission Issuances.vpublished quarterly as NUREG-0750.
Approved: July 1, 1999 (Revised: October 25, 2000) 5
Review Process for 10 CFR 2.206 Petitions Handbook 8.11
\\..J I
I
Volume 8, Licensee Oversight Programs Review Process for 10 CFR 2.206 Petitions.
Handbook 8.11 Parts I -IV Contents Part I Introduction 1
Title 10 of the Code ofFederal Regulations, Section 2.206 (10 CFR 2.206) (A)
~.......
1 General Cautions (B)..................................................
1 Part II.
Initial StaffActions 3
NRCts Receipt ofa Petition (A)......................................*..
3 Process Summary (1).........
3 Assignment of Staff Action (2).......................................
3 Office Action (B) 4 Petition Manager Action (C) 4 Part III Petition ReviewBoard (PRB) 7 General (A)..........................................................
7
.Schedule (1).........................*...................*........
7 Board Composition (2)
~
~......
7 Preparation for the PRB Meeting (B)
~....
8 Criteria for Petition Evaluation (C),
~................................
11 Criteria for ReviewingPetitions Under 10,<;:FR 2.206 (1) 11 Criteria for Rejecting Petitions Under 10 CFR 2.206 (2).*...............
11 Criteria for Consolidating Petitions (3)................................
12
, PRB Meeting (D)
~ ~ ~ '
~
~ ~
~
~ <
~..
13 Informing the Petitioner of the Results (E)
~
~ *.............
14
, Meeting With the Petitiorier (F)
~
~
~
~
- .'.. ~
~
~
. 14 Response to the Petitioner (G)
~ '~'..-.'. ~
15 Requests That Do Not Meet the Criteria (1)
~.'.',. ~
~.....
15 Requests That Meet the Criteria (2). ~..., ~
~.;
'. '.'~....
16 Sending Documents to the Petitioner (H) '
~
.. :. : ~ ~ :..
16 Supplements to the Petition (1)
~.. ~
~
~.....
17 Approved: July 1, 1999 (Revised: October 25, 2000) iii
~
Volume 8, Licensee Oversight Programs Review Process for 10 CFR 2.206 Petitions Handbook 8.11 Parts I -'IV.
Contents (continued)
Part IV Petition Review Activities 19' 0
0 0
0 0
0 0
0 0 ********
0 0
0 ***
0*0 0
0 0
0 0
0 0
0 **
0 0
Reviewing the Petition (A). 0 19
.0 **
0 **
0 0 ****
0 0
0 0 ***
0 0
0 0
0 **
0 0
0 0
0 ***
0 0
0 Interoffice Coordination (1) 19 o **
0 ***
0 ****
0 0
0 ****
0 0 *****
0 0
0 0
0 0
0 0 ***
Request for Licensee Input (2) 0 20 0
0 0
0 0
0 0
0 0
0 0 ***
0 0
0 ****
0 0
0 0
0 Technical Review Meeting With the Petitioner (3). 0 20 0
0 0
0 0 ***
0 ***
0 0
0 Additional Petition Review Board (PRB) Meetings (4).. 00 20 0
0 0
0 0
O' 0
0 0
Schedule (B).
0 0
- 0 0
0 0
- ~
0 0
0 0
0 *******
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 **
20 Keeping the Petitioner Informed (C) 22 0
0 ** 0 0 ***** 0 0 ***** 0
- 0 **** 0 Updates to Management and the Public (D) 22 0
0
- 0 0 **** 00' ***** 0 0
0 0
0 ****
Part V The Director's Decision 24 Content and Format (A). 0 0
0
- 0
- 0
- 0 0
0 0
0 0
~
24 0
0 0
0 0
0 0
0 Final Versus Partial Director's Decisions (B)..
2S 0
0 0
0 0
0 ***
0 0
0 0
0 0
0 0
0 0
Granting the Petition (C). 0 2S 0
0 0
0 0 *********************
0 0
0 ** 0 0
0 0 **
0 0
0 Denying the Petition (D).. 0 26 0
0
- 0 *** 0 0
0 ** 0 *******
0 0
0 0 **** 0 ***
0 0
0 0
0 0
Issuing the Proposed Director's Decision for Comment (E)...
26 0
- 0
- 0 0 ** 0 0
0 Comment Disposition (F) 0 0
0
- 0 0
0 0
- 0 0
~
0 0
0 0
27 0
0 0
0 0
0 0
0 0
Issuing the Director's Decision (G). 0 0
- 0 0
- 0 o *** 0 0
- 0 27 0
0 0
0 0
0
.000 Administrative Issues (H) 28 Commission Actions (I) 0
~
0 0
0 0
0 0
0 0
0 0
30 0
0 0
0 0
0 0
0 0
0 0
0 Exhibits 1
Simplified 2.206 Process Flow Chart 31 0 ***
0 0
0 0
0 0
0 0
0 0
0 0
0 ***
0 **
0 0
2 Petition Manager Checklist 0
0 0
0 0
0
~
0 0
0 0
0 33 0
0 0
0 0
0 0
0 0
0
,3 Sample Closure Letter for Requests That Are Not 2.206 Petitions. 0 36 0
0
- 0 4
Sample Acknowledgment Letter 37 0 ******
0 0
0 0
0 0
0 0
0 0
0 0
0 5
Sample Federal Register Notice 38 0 ***
0 0
0 ******
0 0...
0 0
0 0
0 0
0 0
0 0
0 0
,6. Sample Director's Decision and Cover Letter 39 0 ****** 0 ********** 0 **** 0
- 7.
Sample Federal. Register. Notice for Director's Decision 0 43 0 ******
0 0
0 ***
0 8
Sample Letters Requesting Comments on the Proposed Director's Decision 0 ************ 0 ************ 0 **** 0 **** 0 ********* 0 45 Approved:.July1, 1999 iv.
(Revised: October 25, 2000)
Volume 8, Licensee Oversight Programs Review Process for 10 CFR 2.206 Petitions Handbook8.11** Part I Introduction Title 10 ofthe Code ofFederal Regulations, Section 2.206 (10 CFR 2.206) (A)
This section of the regulations has been a part of the Commission's regulatory framework since the 'Commissionwas established in 1975.
Section 2.206 permits any person to file a petition to request that the Commission take enforcement-related action., i.e., to modify, suspend, or revoke a license or to take other appropriate action. (1)
Section 2.206 requires that the petition be submitted in writing and provide the groundsfor taking the proposed action. The NRCstaffwill not treat general oppositionto nuclearpowerora general assertion ofa safety problem, without supporting facts, as a formal petition under 10 CFR 2.206. The staff will treat general requests as allegations or routine correspondence. Petitioners are encouraged to provide a telephone number or e-mail address throughwhich the staffmaymake contact. (2)
General Cautions (B)
Management Directive (MD) 8.8, "Management of Allegations,"
provides NRC policy with regard to notifying the Office of Investigations (01) and the Office of the Inspector General (OIG) of wrongdoing matters, as well as initiating, prioritizing, and terminating investigations. Each petition manager should become familiar with the currentversion ofMD8.11 and this handbook andfollow the policy and procedures included in them when dealing with issues requiring 01 or OIG investigations. (1)
Any mention outside NRC ofan ongoing 01 or 01G investigation, for example, as an explanationfor schedule changes, requires the approval of the Director, 01, or the IG, respectively. (2)
Approved: July 1,1999 (Revised: October ~S, 2000) 1
Volume 8, Licensee Oversight Programs ReviewProcess for 10 CFR 2.206 Petitions Handbook 8.11 Part I General Cautions (B) (continued)
Ifthe petition contains Information on alleged wrongdoing on the part of a licensee or certificate holder, an applicant for a license or certificate, their contractors, or their vendors, treat the petition, or the relevant part ofthe petition, as an allegation and promptly notify OI.1f the petition contains information on alleged wrongdoing involving an NRC employee, NRC contractors, or NRC vendors, promptly notify OIG. (3)
"-..J"
" Approved: July 1, 1999 (Revised: October 25, 2000) 2
. Volume 8,: Licensee Oversight Programs ReviewProcess for 10 CFR 2.206 Petitions
' Handbook 8.11 Part II Part'II InltialStaffActions NRC's Receipt of a Petition (A)
Process Summary (1), "
After NRC receives a petition, the Executive Director for Operations (EDO) assigns it to the directorofthe appropriate office for evaluation and response. The original incoming petidoI?- is sent to the office and a copyofthe petitionissentto the Office ofthe General Counsel (OGC).
The officialresponse isthe office director'swritten decision addressing the issues raised in the petition. The office directorcan grant, partially grant, or deny the petition. The Commission may, on its own initiative, review the director's decisionwithin 25 days of the date of the decision, although it will not entertain a request for review of the director's decision.'
Assignment of StaffAction (2)
Petitions maybe in the form ofrequestsfor NRCaction thatmay ormay not cite 10 CFR 2.206 and may initially be directed to staff other than the EDO'. I~, any of these cases, the staff person who receives the document should make an initial evaluation as to whether the document meetsthe criteriaforreview tinder 10.CFR2~206providedin Part III of this handbook. Staffpersons who are uncertain whether or not the document meets the criteria should consult their management or office coordinators for further guidance..If a petition meets the criteria but does not 'specifically cite' 10' CFR 2.206, the staff will attempt to contactthe petitionerbytelephone to determine ifhe orshe
, wants the request processed pursuant to 10 CPR 2.206. The staffmay
. determine that a request.forwarded for staffaction is not a petitionfor
.enforcement-related action but, rather/a petition for rulemaking, for
,example. Ifthere is any uncertaintyaboutwhether or not a request is a petition under 10 CPR 2.206, it should be treated as one so that a petition review 'board (pRB).can make' its recommendations, as described in Part III of this handbook. (a)
Approved: July 1, 1999 (Revised: October 25, 2000),
3
_______________________________....L..-______JU...
Volume 8, Licensee Oversight Programs ReviewProcess for 10 CFR 2.206 Petitions Handbook 8.11 Part II*.
NRC's Receipt of a Petition (A) (continued)
Assignment of StafTAction (2) (continued)
Ifthe staffreceives a request that it believes is a 10 CFR2.206 petition,.
it will forward the request to the Office of the EDO (OEDO) for assignment of action. Petitions also may be forwarded to the OEDO from the AtomicSafety and Licensing Board Panel or from a Presiding Officer in accordance with 10 CFR 2.1205(1)(2). The EDO will assign each petition to the appropriate office for action. Ifthe document does not cite 10 CFR 2.206 and does not meet the criteria for review under that section, the staffwill respond to it under some other process (e.g.,
routine correspondence, allegations). (b)
Petitions that cite 10 CFR 2.206 and are addressed to the EDO will be added to the Agencywide DocumentsAccess and ManagementSystem (ADAMS). by OEDO. OEDO will not declare these petitions official agency records nor will it make them publicly available. Those steps will be carried out by the assigned office as described below. (c)
Office Action (B)
Upon receipt, office management will assign the petition to a petition manager. (1)
The Agency 2.206 Petition Coordinator (appointed by the Director, Division ofLicensing Project Management, Office of Nuclear Reactor Regulation (NRR>>, receives copies ofall 2.206 petitions from OEDO
. and will add them to the 2.206 database. (2)
Petition Manager Action (q The petition manager will promptly review the petition and determine whetherornot it contains allegations orsensitive information. The timing ofthis step is particularly importantfor petitions that are not addressed to the EDO. Normally, these documents have been entered into ADAMS through the Document Control Desk (DCO) and are released to the public after a specified period of time. The delay allows the staff time to review the petition for allegations or other sensitive information. If the
.petition manager determines that a document contains allegations or other sensitive information, he or she should immediately contact the ADAMS Help Desk (301-415-1234) to prevent releasing the document to the public. (1)
Approved: July 1, 1999 (Revised:' October 25~ 2000) 4
Volume 8, Licensee Oversight Programs Review Process for 10 CFR'2.206 Petitlons
. Handbook 8.11.Part II Petition Manager Action (C) (continued)
Before the petition is released to the public, before the PRB meeting, and in anyevent within 1week ofreceipt of the petitionby the assigned office, the petition manager will inform the petitioner by telephone that the 2.206 petition process is a public process in which the petition and all the information in it will be made public. If the petitioner requests anonymity and that the petition not. be made public, the.
petition manager will-advise the petitioner that, because of its public nature, the 2.206 process cannot provide protection of the petitioner's identity. In. these cases, the petition manager must obtain the agreementofthe petitioner asto howthe matterwillbe handled (i.e., as an allegation or not) and document the petitioner's agreement in writing, usuallyinthe form of a memorandumto file. Incaseswhere the staff identifies certain issues in a petition that it believes are more appropriately addressed using the allegation process, the petition manager will obtain the agreement of the petitioner as to how these issues will be handled (i.e., as an allegation or not) and document the petitioner's agreement in writing. Ifall or part of the petition is treated as an allegation, this fact will be documented in the allegation acknowledgment letter.(see Management Directive (MD) 8.8, "Management of Allegations"). (2)
Ifthe request clearly does not meet the criteria for review as a 10CFR 2.206 petition, the petition manager will also discuss this issue with the petitioner. The petitioner may be able to help the petition manager better understand the basis for the petition or the petitioner may realize that a 10 CFR 2.206 petition is not the correct forum for the issues raised in the request. Finally, the petition managerwill offer the petitioner an opportunity to have one or more representatives give a presentation to the PRB and cognizant supporting staff either by telephone (or videoconference, if available) or in person. This is an opportunity for the petitioner to provide any relevant additional explanation and support for the request. This type of meeting is described in more detail in Part II.r of this handbook. (3)
After the initial contact with the petitioner, the petition manager will promptly advise the licensee(s) of the petition, send the appropriate licensee(s) a copy of the petition for information, and ensure that the petition and all subsequentrelated correspondence are made available to the public. (Note that if the petitioner wishes to have the request handled as an allegation, the request isno longer a 2.206 petition.)Any information related to allegations or other sensitive information that Approved: July 1, 1999 (Revised: October 25, 2000) 5
____________________________1..--_____......
Volume 8, Licensee Oversight Programs
\\ ReviewProcess for 10 CFR 2.206 Petitions Handbook 8.11 Part II Petition Manager Action (C) (continued) make rip a part of the petition will be redacted from copies sent to the
. licensee or made available to the public. For allegations, the petition manager should refer to MD 8.8. As discussed in MD 8.8, allegations must be forwarded to the associated Office Allegations Coordinator expeditiously. MD 8.8 also addresses the referral ofwrongdoing issues to the Office of Investigations and the Office of the Inspector General. (4)
See Exhibit 1, Simplified 2.206 Process Flow Chart, and Exhibit 2, Petition Manager Checklist, for further information on petition manager actions. (5)
Approved: July 1, 1999 (Revised: October 25, 2000) 6
,-Volume 8, Licensee Oversight Programs Review Process for 10 CFR 2.206 Petitions
,Handbook 8.11' Part III Part III
~.
Petition ReviewBoard (PRB)
General (A)
Schedule (1)
The assigned office holds ~ PRB meeting to review the 2.206 petition.
The PRBineeting is normally held within 2 weeks of receipt of the petition. The PRB meeting may be held much,sooner ifstaffdecisions are required on short-term, immediate actions (e.g., a request to shut down an operating facility orprevent restart ofa facility that is readyto restart). In unusual.situations, it may not be possible to hold the meeting in time to address any immediate action requests. In these cases, the staffwilldecide how any immediate actions requested willbe addressed and obtain appropriate management concurrence as soon as possible. If the staff plans to take an action'that is contrary to an immediate action requested in, the petition before issuing the acknowledgmentletter(such as permittingrestartof afacility when the petitioner has requestedthat restart notbe permitted), the petition manager must promptly notify the petitioner by telephone of the pending staff action. '
Board. Compositio~'(2)
The PRB~ consists 6f~a)
- A PRB chairperson (generally a Senio~ Executive Service manager) (i)
A petition manager (ii),
, ~ '. co~ttri;ma~em~~t and staff, ~necessaIY (iii)
'. A representative' from the Office'of Investigations (OI), as needed (iv)
- rr, :~;
- A representative from.the Office of *Enforcement (OE) 'and, for petitions-assigned to-the Office of Nuclear Reactor Regulation (NRR), the NRR Senior Enforcement Coordinator, as needed (v)
Approved:.July 1, 1999 (Revised: October 25, 2000) 7
Volume 8, Licensee Oversight Programs ReviewProcess for 10 CFR 2.206 Petitions Handbook 8.11 Part III.
General (A) (continued)
Board Composition (2) (continued)
In addition, a representative from the Office of the General Counsel (OGC) will normally participate. (b)
Preparation for the PRB Meeting (B)
The petition manager will provide copies of the petition to PRB and assist in scheduling the review board meeting. The petition manager also will arrange for cognizant technical staff members to attend the meeting, asnecessary, and prepare a presentationfor the review board.
In assigning technical staff members to the petition, management will consider ~ny potential conflictfrom assigning any staff person who was previously involved with the issue that gave rise to the petition. (1)
The petition manager's presentation to PRB should include-(2)
A recomniendation as to whether or not the petition meets the criteria for review under 10 CFR 2.206 (a)
A discussion of the safety significance of the issues raised (b)
- Recommendations for anyimmediate action (whether requested or not) (c)
- Recommendations on whether or not assistance from 01, OE, or OGe is necessary (d)'
- A request for confirmation concerning referral to 01 or the Office of the Inspector General (OIG), as appropriate (e)
- The proposed schedule, including the review schedule for the affected technical branches (f)
The petition manager also will offer a meeting or teleconference between the petitioner and the PRB before the board reviews the petition. This meeting or teleconference, if held, is an opportunity for the 'petitioner to provide any relevant additional explanation and support for the request in advance of the PRB's evaluation. The staff will hold this type of meeting ifthe petitioner desires it. Ifa decision.is required' on a petitioner's request for immediate action before the petitioner's presentation can be scheduled; that decision will not be delayed. (3)
Approved: July i,1999 (Revised:' October 25, 2000) 8
Volume 8, Licensee Oversight Programs Review Process for 10 CFR 2.206 Petitions Handbook 8.11 Part III Preparation for the PRB Meeting,(B) (continued)
,The petition manager also Will invite'the licensee to participate in the meeting or teleconference to' erisure that it'understands the concerns aboutits facilityor'activities. The PRB members may ask any questions needed 'toclarify the petitioner's request. The'licensee may also ask questions to clarifythe issues raised by the petitioner. Any member of
- the public may attend (orlisten inbytelephone for a teleconference) as an observer. 'Meetings between PRB and the petitioner normally will be held at NRC headquarters in Rockville, Maryland, with provisions for participationbytelephone orvideoconference. This publicmeeting
- or teleconference 'is separate from the (closed) PRB meeting during which the PRB members develop theirrecommendations with respect to the petition. (4), '.,
The petitionmanagerwillensure that allstaffpersons at the meetingor
,teleconference are aware of the need to protect sensitive information from disclosure. Sensitive information includes safeguards or facility security information", proprietary or confidential commercial
, information, orinforriiation relating to' an ongoing investigation of
'wrongdoing. (5)
If the petitioner' chooses to.address PRB by telephone, it is not considered a meeting and no,public notice is necessary. The petition managerwill establish a mutually agreeable time and date and arrange to conduct the teleconference on a recorded line through the NRC Headquarters OperationsCenter (301-816-5100). The tape recording
, from the Operations Center is converted to a printed transcript that is
,.treated as a supplement to the petition and is sent to the petitioner and the same distribution as the original petition. Thepetitionmanagerwill make arrangements for.transcription :service,by submitting an NRC Form 587.to the AtomicSafetyand LicensingBoardPanel orbysending
- an..e-mail to, "Court Reporter," giving the same information as requested on theForm 587. (6).,
l Ifthe petitionerchooses to attendinperson, the meetingwill take place at NRC headquarters atamutually agreeable 'time. For the meeting,
- the petition manager will.follow the prior public notice period and
'other 'provisions' 'of, Management: Directive (MD) 3.5, "Public Attendance at Certain Meetings Involving the NRC Staff." However, time constraints associated with this type of meeting will often dictate that the 10-day public notice 'period described in MD 3.5 will not be Approved: July 1, 1999 (Revised. ' October 25, 2000) 9'
a.L..
Volume 8, Licensee Oversight Programs Review Process for 10 CFR 2.206 Petitions Handbook 8.11 Part In:
Preparation for the PRB Meeting {B) (continued) met. MD 3.5 allows for less than 10 days' public notice, if necessary, with appropriate management concurrence. The meeting should be noticed as a meeting between the ~~ staff, the petitioner, and the license-e (unless the licensee chooses notto participate). The licensee is invited to participate, as in the teleconference described above, and members of the public may attend as observers. The meeting is transcribed and the transcript is treated in the same manner as in the case of a telephone briefing, (7).
The petitioner may request that a reasonable number of associates be permitted.to assist him or her in addressing PRB concerning the petition. The petition manager will (1) discuss this request with the petitioner, (2) determine the number of speakers, and (3) allot a reasonable amount of time for the presentation so that the staff can acquire' the information needed for its review in an efficient manner. (8)
At the meeting or teleconference, the chairperson will provide a brief summary of the 2.206 process, the petition, and the purpose of the discussion that willfollow. The NRC staffand the licensee will have an opportunityto ask the petitionerquestions for purposesofclarification.
PRB may meet in closed session before and/or after the meeting with the petitioner to conduct its normal business. (9)
The requirements for scheduling" and holding the petitioner presentation may impact the established time goals for holding the regular' PRB meeting and issuing the acknowledgment letter. Any impacts should be kept to' a minimum. (10)
The petition manager will review the transcript and, where necessary, edit it to ensure it accurately reflectswhat was said in the meeting or teleconference. Corrections are onlynecessaryforerrors thataffectthe meaning of the text of the transcript. The petition manager is not exp~cted to correct inconsequential errors. (11)
_After editing, the petition manager will ensure that the transcript gets
- the-same distribution (petitioner, licensee, publicly available, etc.) as the original petition. Formeetings, this step shouldbe accomplished by attaching' the transcript to.a brief.- meeting summary. For
,:teleconferences; the petition manager may attach the transcript to a memorandum to file. (12)
"-.J'
, Approved: July 1, 1999 10, (Revised; October 25, 2000)
Volume8, Licensee Oversight Programs ReviewProcessfor 10 CFR 2.206 Petitions '
Handbook 8.11.' Part III Criteria for Petition Evaluation (C)
The staff will use the criteria discussed in this section to determine whetherornota petitionshould be considered under 10CFR2.206 and whether or not similar petitions should be consolidated.
Criteria for RevieWing Petitions Under 10 CFR 2.206 (1)
.The staffwillreview a petitionunder the requirements of10 CFR2.206 if the request meets all of the.following criteria-(a)
- The petition contains a request forenforcement-related action such as issuing an order modifying, suspending, or revoking a license, issuing a notice ofviolation, with orwithouta proposedcivil penalty, etc. (i)
- The facts that constitute the bases for taking the particular action are specified. The petitionermustprovide some element ofsupport beyond the bare assertion: The supporting facts must be credible and sufficient to warrant :further inquiry. (ii).
- There is no NRC proceeding available in which the petitioner is or could be a party and through which the petitioner's concerns could be addressed.If there is a proceeding available, for example, if a petitioner raises an issue that he or she has raised or could raise in an ongoinglicensing proceeding, the staffwillinform the petitioner of the ongoing proceeding and will not treat the request under 10 CFR 2.206. (iii),
An exception to the first two criteria is any petition to intervene and request for hearing in a licensing proceeding that is referred to the 10 CFR 2.206 process inaccordancewith 10 CFR 2.1205(1)(2). These referrals may be made when the petition does not satisfy the legal requirements for a hearing or intervention and the Atomic Safety and LicensingBoardPanel orthe PresidingOfficerdetermines thatreferral to the 10 CFR 2.206 process is appropriate. For these referrals, the
.substantive issues in' the request for a: hearing 'or intervention will be read as' an implicit -request foreriforcement-related action, thus
._' satisfying the criteria 'for treatnient under the 10 CFR 2.206 review process. (b)
Criteria for Rejecting Petitions Under 10 CFR 2.206 (2)
The, staff will not review a petition under 10 CPR 2.206, whether specifically cited or not, under the following circumstances Approved: July 1,1999 (Revised:' October 25, 2000) 11
Volume 8, Licensee Oversight Programs ReviewProcess for 10 CFR 2.206 Petitions Handbook 8.11 Part III Criteria for Petition Evaluation (C) (continued)
Criteria for Rejecting Petitions Under 10 CFR 2.206 (2) (continued)
- The incoming correspondence does not ask for an enforcement-related action or fails to' provide sufficient facts to support the petition but simply alleges wrongdoing, violations of NRC regulations, or existence of safety concerns. The request cannot be simply a general statement of opposition to nuclear power or a general assertion without supporting facts (e.g., the quality assura~ce at the facilityisinadequate). These assertionswill be treated as routine correspondence or as allegations that will be referred for appropriate action in accordance with MD 8.8, "Management of Allegations." (a)
." The 'petitioner raises issues that have already been the subject of NRC staff review and'evaluation either on that facility, other similar facilities, or on a generic basis, for which a resolution has been achieved, the issues have been resolved, and the resolution is applicable to the facility in question. This would include requests to
"-..J reconsider or reopen a previous enforcement action (including a decision not to initiate an enforcement action) or a director's decision. These requests will not be treated as a 2.206 petition unless they present significant new information. (b)
- The request is to deny a license application or amendment. This type of request should initially be addressed in the context of the relevant licensing action, not under 10 CFR 2.206. (c)
- The request addresses deficiencies within existing NRC rules. This type ~f requestshould be addressed as a petitionfor rulemaking. (d)
Criteria for Consolidating Petitions (3),
Generally, all requests submitted by different individuals will be treated and evaluated separately. When two or more petitions request action against the same licensee, specify essentially the same bases, provide adequate supporting information, and are submitted at about the same time, PRB will consider the benefits of consolidating the petitions against the potential of diluting the importanceofanypetition and recommend whether or not consolidation is appropriate. The assigned office director will determine whether or not to consolidate the petitions.
Approved: July 1,1999 (Revised: October 25, 2000) 12
Volume 8, Licensee Oversight Programs Review Process-for 10 'CFR 2.206 Petitions Handbook 8.11 Part ill '
PRB Meeting (D)
PRB ensures that an appropriate petition review process is followed.
The purposes of the PRE processare to-(1),
- Determine whether or not the' petitioner's request meets the criteria for review as a 10CFR2.206petition (see PartIII(C) ofthis handbook)'(a)
- Determine whether or not the petitioner should be offered or informed of an alternative process (e.g., consideration of issues as allegations, considerationofissuesin a pendinglicense proceeding,.
or rulemaking) (b)
- Determine whether' there is a need for any immediate actions (whether requested ornot) (c).
- . Establish 'a schedule for responding to the petitioner so that a commitment ismade bymanagement arid the technical reviewstaff to respond to the petition iIi-a timely maimer (see Part IV of this handbook for guidance regarding schedules) (d)
,. Address the possibility.of issuing a partial director's decision (e)
- Determinewhether or'notthe petition shouldbe consolidatedwith another petition (t)
'('.
- Determine whether or not referral to 01 or OIG is appropriate (g)
'~.'. -'.'.. '
- Determine whether or not there is a need for aGe to participate in the review (h)
- Determine whether tii 'n6t ~~ ti~ensee ~hould be requested to respond to ~e petition ~i). '.
- Determine whether or riot the petition',is sufficiently complex that additional.review board.meetings should be scheduled to ensure that suitable progressis being made(j) :'. :
,..The PRB meeting is a closedmeeting, separate from any meetingwith the, petitioner: and the licensee, 'during' which the PRE members develop their recommendations with respect to the petition. At the
".meeting, the petition manager briefs PRE on the petitioner's
. request(s), any background Information, the need for an independent technical review, and a proposed plan for resolution, including target completion dates. The petition manager, with the assistance of the Approved: JulyI, 1999 (Revised: October 25, 2000) 13
Volume 8, Licensee.Oversight Programs ReviewProcess' for 10 CFR 2.206 Petitions Handbook 8.11.Part III.*
PRB Meeting (D) (continued)
Agency 2.206 Petition Coordinator, ensures appropriate documentation of all PRB recommendations in the summary of the PRB meeting. (2)
The OGC representative provides legal review and advice on 10 CFR 2.206 petitions. OGC may be assigned as the responsible office for the
. review, if appropriate. (3)
.Informing the Petitioner of the Results (E)
After PRB meets, and before issuing the acknowledgment letter, the petition manager will ensure that appropriate levels of management (as determined by the assigned office) are informed of the board's recommendations and that theyconcur. The petitionmanagerwill then inform the petitioner by telephone as to whether or not the petition
. meets the criteria for review under 10 CFR 2206, of the disposition of any requestsfor immediate action, ofhow the reviewwill proceed, and thatan acknowledgment letter is forthcoming. Ifthe staffplans to take"-.-J an action that is contrary to an immediate action requested in the petition before issuing the acknowledgment letter, the petition manager must notify the petitioner promptly by telephone of the pendingstaff action. An example ofa contrary action would be ifNRC permitted restart of a facility when the. petitioner had requested that restart not be permitted. The petitioner will not be advised of any wrongdoing investigation being conducted by 01 or OIG.
Meeting With the Petitioner (F)
After informingthe petitionerofthe pertinent PRBrecommendations,
.the petition manager will offer the petitioner an opportunity to comment on the recommendations..This opportunity will be in the form of a meeting or teleconference between the petitioner and the PRB. If the petitioner accepts this offer, the petition manager will establish a mutually agreeable date for the meeting or teleconference with the petitioner. The petitionmanager also will invite the licensee to participate' and will. coordinate the.schedules and dates with the licensee. The meeting or teleconference should be scheduled so as not to adversely affect the established petition review schedule. (1)
. Approved: July 1,1999 (ReVised:.October 25, 2000) 14
Volume 8, Licensee OversightPrograms ReviewProcess for to CFR 2.206 Petitions Handbook 8.11 PartIlI Meeting With the Petitioner (F) (continued)
This meeting or teleconference, if held, is an opportunity for the petitioner to provide any relevant additional explanation and support for the request in light ofPRB's recommendations. The PRB members may ask questions to clarify the petitioner's request. Ifstaff decisions on any of the petitioner's immediate action' requests are required before the petitioner's presentation can be scheduled, those decisions will not be delayed. The format of the meeting.or teleconference, application ofMD 3.5~ transcription, etc., and the requirements to edit
.and distribute the transcript. are the same as for a meeting or teleconference held prior to the PRB's review of the petition. (2)
After this discussion, PRB will consider the need to modify any of its recommendations. The final recommendations will be included in the acknowledgment letter. The acknowledgment letter will address any
',comments the petitioner made conceniing' the initial PRB recommendations and the staff's response. 'The petitioner will be notified promptly of staff decisions on any immediate action requests.
Ifthe petitioner presents significant new information to the staff, PRB u
maydeterminethat this new informationconstitutes a new petitionthat will be treated separately from the initial petition. (3)
The requirements for scheduling and holdingthe petitionerpresentation may impact the established time goals for issuing the acknowledgment letter. These impacts should be kept to a minimum. (4)
Responseto the Petitioner <<;7)
After PRB finalizes its recommendations.. the petition manager prepares a written response to the petitioner.
Requests ~at Do Not ~eet the Criteria (1)
IfPRB, with office-level managementconcurrence, determines that the petition does not meet the Criteria for review'asa 10 CFR 2206petition, the petition manager then prepares a letter that (1) explains whythe request is not being reviewed under 10 CFR 2206; (2) responds, to the extent possible at that time, to the issuesin the petitioners request; and (3) explains what further' actions/if any, the staff intends to take in response to the request (e.g., 'treat it as an allegation or routine correspondence). See Exhibit 3 for an example. (a)
The petition manager will attach, the original petition and any
, enclosure(s) to the Reading File copy of the letter. (b)
Approved: July 1,1999 (Revised: October 25, 2000) 15
Volume 8, Licensee Oversight Programs Review Process. for 10 CFR 2.206 Petitions Handbook 8.11 Part III Response to the Petitioner (G) (continued)
, Requests That Meet the Criteria (2)
If the PRB finds that the petition meets the criteria for review as a 10 CFR 2.206 petition, the petition manager prepares an acknowledgment letter and associated Federal Register notice (see Exhibits 4 and 5). The letter should acknowledge the petitioner's efforts inbringing issues to the staff's attention. If the petition contains a request for immediate action by the.NRC, such as a request for immediate suspension offacility operation until final action is taken on the request, the acknowledgment letter must explain the staff's respons~ to the immediate action requested and the basis for that respons~. (a)
The petition manager ensuresthat a copyof this management directive and of the pamphlet "Public Petition Process," prepared by the Office of Public Affairs, are included with the acknowledgment letter. The acknowledgment letter also should include the name and telephone number. of the petition manager, identify the technical staff organizational units that will participate in the review, and provide the planned schedule for the staff's review. A copy of the acknowledgment letter must be sent to the appropriate licensee and the docket service list(s). (b)
The petition manager will attach the original 2.206 petition and any enclosure(s) to the ReadingFile copyofthe acknowledgmentletter. (c)
In rare cases the staff may be prepared to respond to the merits of the petition immediately. In this case, the staff can combine the functions of the acknowledgment letter and the director's decision into one document. A similar approach. would be taken in combining the associ~ted Federal Register notices. (d)
Sending Documents.to the Petitioner (H)
If the PRB determines that the request is a 2.206 petition, then the petition manager will-(l)
- Add the petitioner to the service list(s) for the topic (if one exists).
Add the petitioner to the headquarters and regional service listsfor the licensee(s) that is(are) the subject of the petition. (a)
Approved: July 1,1999:
(Revised: October 25, 2000) 16
, Volume 8; Licensee Oversight Programs ReviewProcessfor 10 CFR 2.206 Petitions Handbook 8.11' Part III
.Sending Documents to the Petitioner.(H) (continued)
- . Request the licensee to send copies of any future correspondence related to the petition' to the petitioner," with due regard for proprietary, safeguards,' and other sensitive information. (b)
- To the extent that the petition manager is aware of these documents, ensure that the petitioner is placed on distribution for other NRC '
correspondence relating to the issuesraised in the petition, including relevant generic letters 'or bulletins that are issued during the pendency of the NRC's consideration of the petition. TIlls does not include NRC correspondence or documentation related to an 01 or OIG investigation, which will not be released outside NRC without the approval of the Director, 01, or the IG, respectively. (c)
These three actions will remain in effect until 90 days after the director's decision is issued ifthe petitioner desires it. (2)
Supplements to the Petition (I)
A petitionerwill sometimes submit a supplement to his or her petition.
The petition manager,will review the supplement promptly and determine whether, or" not _it contains allegations or sensitive
,information. If the supplement appears to contain information of this nature,the petition manager must obtain the agreement of the petitioner asto howthese issueswillbe handled(i.e., as an allegationor not) and document the petitioner's agreement in writing, usually in the form of a memorandum to file. Ifallor partofthe supplement istreated as an allegation, this fact will be documented in the allegation acknowledgment letter (see MD 8.8, "Management of Allegations").
See Part II(C) ofthis handbook for more detailed information. (1)
The petition manager Will 'also ensure the supplement receives 'the same distributionasthe petition' and will forward a copy of the supplement to the PRB members.'The PRB members will review the supplement and determine whether they'need to meet formally to discuss it and, ifso.whetheror not to offer the petitioneran opportunity to discuss the supplement with the PRB members before the board reviews the supplement (see Part III(B) of this handbook). In deciding whether a'formal.PRB,meeting is needed, 'the PRB members will
- 'consider the safetysignificance and complexity of the information in the supplementClarifications of previous information will generally not require a new PRBmeeting. Ifa newPRB meetingisnot convened, the petition manager will include the supplement in the ongoing petition review and no further action is necessary. (2)
Approved: July 1,1999 (Revised: October 25, 2000)
Volume 8, Licensee Oversight Programs Review Process for 10 CFR 2.206 Petitions Handbook 8.11.Part III.
Supplements to the Petition (I) (continued).
If a new PRB meeting is convened, the PRB members will determine whether or not-(3)
- There is a need for any immediate actions (whether requested or not) (a)
- The supplement should be consolidated with the existing petition (b)
- To issue a partial director's decision (c)
- Referral to 01 or OIG is appropriate (d)
- To revise the review schedule for the petition based on the supplement (see Part IV of this handbook for guidance regarding schedules) (e)
- To send an acknowledgment letter for the supplement. (An acknowledgment letter should be sent if the supplement provides significant new information, causes the staff to reconsider a previous determination, or requires a schedule change beyond the original 120-day goal. See Part III(G) of this handbook for information on acknowledgment letters.) (f)
- To offer the petitioner a meeting or teleconference with PRB to discuss its recommendations with respect to the supplement. (See Part III(F) ofthis handbookfor information on this type ofmeeting or teleconference.) (g)
If the staff determines that the schedule for the petition must be extended beyond the original 120-day goal as a result of the supplement, the assigned office should send ari'acknowledgment letter
.to' the petitioner, reset the 120-day clock to the date of the new acknowledgment letter, and inform the Office of the Executive Director for Operations (OEDO). (4)
If PRBdetermines thatthe supplementwill betreated as a new petition (i.e., not consolidated with the existing petition), the assigned office
,must contact OEDO andobtain a new tracking number in the Work Item Tracking System. (5)
Approved: July 1, 1999 (Revised: October 25, 2000) 18
Volume 8, Licensee Oversight Programs Review Process for 10 CFR 2.206 Petitions" "Handbook 8.11 Part IV Part*IV
'Petition Review Activities Reviewing the Petltion (A)
Interoffice Coordination (1)
The petition manager coordinates "all information required for the petition review." The petition manager also advises his or her management of the need for review and advice from the Office of the General Counsel (OGe) regarding a petition in special cases. When
\\": appropriate, an Associate Director in the Office of Nuclear Reactor Regulation, a Division Director in the Office of Nuclear Material
- . Safety and Safeguards,or the'Director of the Office. of Enforcement
- requests OGC involvement through the OG~ special counsel assigned to 2.206 matters, (a) "
All information related to a Wrongdoing investigation by the Office of "Investigations (01) or the Office of the Inspector General (OIG), or
- even the fact that-an investigation is being conducted, will receive limited distribution within NRC and will not be released outside NRC without the approval of the Director, 01, or the IG, respectively (see Management "Directive (MD) :8.8). :Within NRC, access to this information is limited to those having a need-to-know. Regarding a
" 2.206petition, the assigned office"director, or his designee, maintains
" copies, of any documents: required and ensures that no copies of documents related to 'an 01 or 'OIG investigation are placed in the docket file or the Agencywide Documents 'Access and Management System(ADAMS)without the approval ofthe Director, 01, or the IG, "
respectively. (b)
\\
~.'
I
'11
.,t.
Approved: JUlyi, 1999 :",
19' (Revised: October 25, 2000)
IL Volume8, Licensee Oversight Programs ReviewProcess for 10 CFR 2.206 Petitions Handbook 8.11 Part IV Reviewing the Petition (A) (continued)
Request for Licensee Input (2)
If appropriate, the petition manager will request the licensee to provide a voluntary response to the NRC on the issues specified in the petition, usually within 30 days. This staffrequest will usually be made in writing. The petition manager will advise the licensee that the NRC will make the licensee's response publicly available and remind the licensee to provide a copy of the response to the petitioner. The licensee may voluntarily submit information relative to the petition, even if the NRC staffhas not requested any such information. (a)
Unless necessary for NRC's proper evaluation of the petition, the' licensee should avoid, using proprietary. or personal privacy information that requires protection from public disclosure. If such information is necessary to respond to the petition completely, the petition manager ensures the information is protected in accordance with 10 CFR 2.790. (b)
Technical Review Meeting With the Petitioner (3),
A technical review meeting with the' petitioner will be held whenever the staff believes that such a meeting (whether requested by the petitioner, the licensee, or the,staff) would be beneficial to the staff's review of the petition. Meeting guidance is provided in MD 3.5. The petitionmanagerwill ensure thatthe meetingdoes notcompromisethe protection of sensitive information. A meeting will not be held simply
'because the petitioner claims to have additional information and will not present it in any other forum.
Additional Petition ReviewBoard (PRB) Meetings (4)
Additional.PRB meetings may be scheduled for complex issues.
Additional meetings also may be appropriate if the petition manager finds that significant changes must be made to the original plan for the resolution of the petition.
Schedule (B)
The first goal is to issue the proposed director's decision for comment within 120 days after issuing the acknowledgment letter. The proposed director's decision for uncomplicated petitionsshould be issued in less than 120 days. The second goal is to issue the director's decisionwithin 45 days of the.end of the comment period for the proposed
~
Approved: July 1,1999 (Revised: October 25, 2000) 20
Volume 8; Licensee Oversight Programs ReviewProcess for 10 CFR 2.206 Petitions
'Handbook 8~11 Part IV Schedule (B) (continued) director's decision. The actual schedule should be shorter if the
.. number arid complexity of Pte comments allow. The Office of the Executive Directorfor Operations (OEDO) tracks the first target date, and any change ofthe date requires approvalby the EDO. The petition manager monitors the progress of any.01 investigation and related enforcement actions. Enforcement actions that are prerequisites to a
.director's decision should be.expedited and completed in time to meet the 120-day goal.' Investigations by 01 and OIG associated with petitions should be expedited to the extentpracticable, However, the goal ofissuingthe proposed director's decision for commentwithin 120 days after issuing the acknowledgment letter applies only to petitions whose review schedules are within the staff's control. If issues in a petition are the subjectof an investigationby 01 orOIG, orareferral to the Department of Justice (DOJ), or if NRC decides to await a DepartmentofLabordecision, the clockfor the 120-daygoalisstopped for the portion of' the' petition awaiting disposition by those organizations. The clock will start again when the staff receives the results ofthe investigation. Ifthe staffcan respond to some portions of the petition without the results of the investigation, then a proposed partial, director's decision should be issued for comment within the original 120. days.,When' the.staff receives the results of the investigation, it will promptly develop and issue a proposed final director's decision for comment..See Part V of this handbook for a discussion of partial director's decisions. (1)
)f the proposed director's decision cannot be issued in 120 days for
'other reasons (e.g., very complex issues), the appropriate level of management in -the assigned, office. determines the need for an extension ofthe schedule and requests the extensionfrom the EDO. In
'. addition, the petition manager will contact the petitioner promptly to explain the reason(s) for the delay and will maintain a record of the contact. (2)
After the comment period closes on a proposed director's decision, the
.'assigned officewill.review the comments received and provide the schedule to 'issue'the director's decision to the Agency 2.206 Petition
,. 'COordinator for Inclusion in the ne~ status' report. (3)
Approved: July 1,'i999 (Revised:.October 25, 2000) 21
I.
Volume 8, Licensee Oversight Programs ReviewProcess for 10 CFR 2.206 Petitions Handbook 8.11, Part IV Keeping the Petitioner Informed (C)
The petition manager ensures that the petitioner is notified at least every '60 days of the status of the petition, or more frequently if a signlficant action occurs. If a significant action will be reported in the monthly.status report prepared by' the Agency 2.206 Petition Coordinator, the petitionmanagerwillinform the petitionerbefore the status report is issued. The petition manager makes the status reports to thepetitioner by telephone. The petition manager should speak directlyto the petitioner Ifreasonablypossible. The petition manager keeps up-to-date on the status of the petition so that reasonable detail can be provided with the status reports, However, the status report to the petitioner will not indicate
- An ongoing 01 or OIG investigation, unless. approved by the Director, 01, or the IG (1)
- The referral of the matter to DOJ (~)
- Enforcement action under consideration (3)
Updates to Management and the Public (D)
On a monthlybasis,the Agency2.206 Petition Coordinatorwill contact all petition managers reminding them to prepare a status report regarding 2.206 petitionsin theiroffices. The petition managers should e-mail the status report for each open petition; with the exception of sensitive information as described below, to "Petition." The Agency 2.206 Petition Coordinator combines all the status reports, including staffperformance metrics for petitions processed under 10 CFR 2.206 for the currentyear, in a monthlyreport to the EDO from the Associate Director, Project licensing and Technical Analysis. The Agency 2.206 Petition Coordinator also ensures the document is added to ADAMS and made publicly available and e-mails acopy to "NRCWEB" for placement on the NRC's Web site. (1).
Ifthe statusofthe petitionincludessensitive informationthat may need to be protectedfrom disclosure, the petitionmanagerwill so indicate in the e-mail and in the status report itself. Sensitive informationincludes
. safeguards or facility security information, proprietary or confidential
.commercial information, information' relating to an ongoing investigation of wrongdoing or enforcement actions under development, or information about referral ofmatters to the DO] and should be handled in accordance with MD 12.6, "NRC Sensitive Unclassified Information Security Program." The Agency 2.206.
. - Approved: July 1, 1999 (Revised:.October 25, 2000)
I '.
22
Volume 8, Licensee Oversight Programs ReviewProcess for 10 CFR 2.206 Petitions.
. Handbook 8.11 Part IV Updates to Management and the Public (D) (continued)
Petition Coordinator will protect this.inforrnaticn from disclosure by placing the affected status report(s) in a separate enclosure to the status report, clearly marking the status report to the EDO, and redactingthe sensitiveinformationfrom the versionofthe report thatis made public. (2)
The NRC's Web site provides the up-to-date status of pending 2.206 petitions, director's' decisions issued, and other related information, The NRC external Web site (http://www.nrc.gov) is accessible via the World Wide Web, and documents related to petitions may be found on the Public Involvement" page under the section on Petitions.
Director's decisions.are also' published.in NRC Issuances (NUREG-0750). (3)
Approved: July 1,1999 (Revised: October 25, 2000) 23
Volume 8, Licensee Oversight Programs ReviewProcess for 10 CFR 2.206 Petitions Handbook 8.11 Part V Part V The. Director's Decision Content and Format (A)
The petition manager prepares the proposed director's decision on the petition and the associated Federal Register notice for the office director's consideration, including coordination with the appropriate staffsupporting the review.See Exhibits6 and 7for a sample director's decision with cover letter and the associated Federal Register notice"
)
respectively. The petition manager will also prepare letters to the petitioner and the licensee that will enclose the proposed director's decision and request comments on it (see Exhibit 8). These letters will be routed with the director's decision for concurrence. (1)
The director's decision will clearly describe the issues raised by the petitioner, provide a discussion of the safety significance of the issues, and clearly explain the staff's disposition for each issue. The petition manager will bear in mind the broader audience (i.e., the public) when preparing the explanation of technical issues. Refer to the NRC Plain Language Action Plan, available on the internal Web site, for further guidance. In addition, the petition manager will ensure that any documents referenced in the decision are available to the public. Ifa partial director's decision was issued previously, the final director's decision will refer to, but does not have to repeat the content of, the partial director's decision. Mer management's review, the petition manager incorporates any proposed revisions in the decision. (2)
Ifappropriate, the decision and the transmittal letter for the director's decision or partial director's decision should. acknowledge that the petitioner identified valid issues and should specify the corrective actions that have been or will be taken to address these issues, notwithstanding thatsome or all ofthe petitioner'sspecificrequests for action have not been granted. (3)
~
Approved: July 1,1999 (Revised: October 25, 2000) 24
Volume 8, Licensee OversightPrograms ReviewProcess' for 10 CFR 2.206 Petitions Handbook 8.11 Part V Content and Format (A) (continued),
Ifthe Office of Investigations (01) has completed its investigation ofa
, potential wrongdoing issue'and the matter lias been referred to the DepartmentofJustice (DOJ)~ thepetitionmanagerwillcontact 01 and the Office of Enforcement (OE) to coordinate NRC's actions. For petitions assigned to the Office ofNuclear ReactorRegulation (NRR),
the petition manager also will contact the'NRR Senior Enforcement Coordinator. The staff may need to withhold action on the petition in keeping with the Memorandum of Understanding with DOJ. (4)
If the results of a wrongdoing investigation by 01 in relation to the petition are available, thestaffwill considerthese results in completing the, action on' the.petition.,01 must concur in the accuracy and characterizationofthe 01 findings and conclusions that are used in the decision. (5)
The petitionmanagerwill obtain OE'sreview ofthe director's decision for potential enforcement implications.Forpetitions assigned to NRR, the petition manager also will provide a copy ofthe director's decision to the NRR Senior Enforcement Coordinator. (6)
Final Versus,,~artial Director's Decisions (Bj,
The staff will consider preparing a partial director's decision when some of the issues associated with the 2.206 petition are resolved in advance of other issues and' if significant schedule delays are anticipated before resolution of the entire petition. (1) :
The format, content, and method of processing a partial director's decision are the same,'a~, that_of a' director's, decision (as described above) and an accompanying Federal Register notice would still be prepared (see.Exhibit,7).. However, the partial director's decision should clearly indicate those portions ofthe petition that remain open, explainthe reasonsforthe delayto the extentpractical, and provide the staff'sschedule for the final director's decision. Ifall ofthe issues in the petition can be resolved together, then the director's decision will
,address all of the issues. (2)
Granting the Petition (C)..,.. '<, '
"Oncethe staffh~sdetermined thatthe petitionWillbegranted, inwhole or in part" the petition manager will prepare a "Director's Decision
, Under 10 CFR 2.206" for the office director's signature. The decision will explain the bases upon which the petition has been granted and identify the actions that NRCstaffhas taken or will take to grant all or that portion of the petition.'The decision 'also should describe any
, Approved: July 1, 1999 (Revised: October 25, 2000) 25
Volume 8,Lic~nsee Oversight Programs Review Process for 10 CFR 2.206 Petitions Handbook 8.11 PartV Granting the Petition (C) (continued) actions the, licensee took voluntarily that address aspects of the petition. The Commission may granta requestfor enforcement-related action, in whole or in part, and also may take other action to satisfy the concerns raised by the petition. A petition is characterized as being granted. in part when the NRC grants only some of the actions requested and/or takes actions other than those requested to address the underlying problem. Ifthe petition is granted in full, the director's decision will explain the bases for granting the petition and state that the Commission's action resulting from the director's decision is outlined in the Commission's' order. or other appropriate communication. Ifthe petition isgrantedin part,the director'sdecision will clearly indicate the portions of the petition that are being denied and the staff's bases for the denial.
Denying the Petltlon (D)
Once the staff has determined that the petition will be denied, the petition manager will prepare a "Director's Decision Under 10 CFR 2.206" for the office director's signature. The decision will explain the bases for the denial and discuss all matters raised by the petitioner in support of the request.
Issuing the Proposed Director's Decision for Comment (E)
After the assigned office director has concurred in the proposed director's decision, the petition'manager will issue the letters to' the petitioner and the licensee enclosing the proposed director's decision and requesting comments on it. The letters, with the enclosure, will be made available to the public through the Agencywide Documents Access and Management System (ADAMS). (1)
The intent of this step is to give the petitioner and the licensee an opportunity to identify errors in the decision, The letters will request a response within a set period oftime, nominally2weeks. Theamountof
- time allowed for the response may be adjusted depending on circumstances, Forexample, forvery complextechnical issues it maybe appropriate to allow more time for the petitioner and licensee to develop their comments: The letters, including the proposed director's decision, should be transmitted to the recipients electronically or by fax, if possible. (2)
Approved: July 1,1999 (Revised: October 25, 2000) 26
v Volume 8, Licensee"Oversight Programs Review Process for 10 CFR 2.206 Petitions Handbook 8.11 PartV Comment Disposition (F)
After the comment period closes on the proposed director's decision, the assigned office will review the comments received and provide the schedule to issue the director's decision to the Agency 2.206 Petition Coordinator for Inclusion in. the next status report. The petition manager will then evaluate any comments received on the proposed decision, obtaining the assistance of the technical staff, as appropriate.
Although the staff requested comments from only the petitioner and the licensee,' commentsfrom other sources'(e.g., othermembers ofthe public) may be received. 'These additional comments should be addressedin the same manrierasthe commentsfrom the petitionerand licensee. A copy of the comments received and the associated staff responses will be included in the director's decision. An attachment to the decision will generally be used for this purpose. (1),
If no comments are received on the proposed decision, the petition managerwill include in the director's decision a reference to the letters that requested comments.and a statement that no comments were received. (2)
If the comments from the petitioner include new information, the petition review boardwillbe reconvened to determinewhetherto treat the new information as part of the current petition or as a new petition. (3)'
Issuing the Director's Decision (G)
A decision under 10 CFR 2.206 consists of a letter to the petitioner, the director's decision" and' the' Federal Register notice. The petition manager will obtain.a director's decision number (i.e., DD-YY-XX) from the Office ofthe Secretary(SECY). A director's decisionnumber is assigned to'each director'sdecision in numerical sequence. This number is included on the letter to the petitioner, the director's decision, and the 'Federal. Re'gister notice. Note that the director's decision itselfis not published in the FederalRegister, only the notice of its availability, containinga summary ofthe substance ofthe decision, is published(seeExhibits 6 and 7). (1)
The petition manager ~i11 pr~pare a letter to transmit the director's decision to the petitioner and will also prepare the associated Federal Register notice. Ifthe staff'sresponse to the petition involvesissuingan order, the petitionmanagerwillprepare a letterto transmitthe orderto the licensee. The petitionmanager also will include a copyof the order ApprovediTuly 1;1999 (Revised: October 25, 2000) 27
Volume 8, Licensee Oversight Programs Review Process for 10 CFR 2.206 Petitions Handbook 8.11 Part V Issuing the Director's Decision (0) (continued) in the letter to the petitioner. When the director's decision has been signed, the petition manager will promptlysend a copy of the decision, electronically or by fax if possible, to the petitioner. Copies of the director's decision and Federal Register notice that are sent to the licensee and individuals on the service list(s) are dispatched simultaneously with the petitioner's copy. Before dispatching the director's decision (or partial decision), the petition manager will infonn the petitioner ofthe imminent Issuance of the decision and the substance of the decision, The petition manager will also ask.the petitioner whether he or she wishes to continue receiving documents related to the petition. (2)
The assigned office director will sign the cover letter, the director's decision, and the Federal Register notice. After the notice is signed, the staff forwards it to the Rules.and Directives Branch, Office of Administration (ADMIDASIRDB), for transmittal to the Office ofthe Federal Register for publication. The staff shall NOT include a copy of the director's decision in the package that is sent to RDB. RDB only"-..J forwards the Federal Register notice to be published. (3)
Administrative Issues (H)
The administrative staff of the assigned office will review the 10 CFR
.. 2206 package before it is dispatched and determine appropriate distribution. The administrative staffalso will immediately (same day) hand -carrythe Iistedrnaterial to the following offices (in the case ofthe petitioner, promptly dispatch the copies.)-(l)
Rulemakings and Adjudications staff, SECY (a)
- Five copies of the director's decision (i)
- Twocourtesycopies ofthe entire decision package including the distribution and service lists (ii)
- Twocopies of the incomingpetition and any supplement(s) (iii)
- Petitioner (b)
- Signed original letter (i)
- Signed director's decision (ii)
- A copy of the Federal Register notice (iii)
.Approved: July 1, 1999
(~e~sed: Octo~er 25,2000) 28
v Volume 8, Licensee Oversight Programs Review Process for 10 CFR 2.206 Petitions Handbook 8.11 Part V Administrative Issues (H) (continued)
Chief, Rules and Directives Branch (c)
- Original signed Federal Register notice only (do not include the director's decision) (i)
- " Five paper copies of the notice (ii)
- A disk with a WordPeifect file that contains the Federal Register notice (iii)
The staff must fulfill these requirements promptly because the Commission has 25 calendar days from the date of the decision to determine whether or not the director's decision should be reviewed. (2)
The staff will use the following guidelines when distributing copies intemally and extemally-(3)
- When action on a 2.206petition iscompleted, the petitionmanager willensure thatallpubliclyreleasable documentationisavailable to the public in ADAMS. (a) _
- The assigned office will determine the appropriate individuals and offices to include on the' distribution lis~. (b)
The administrative staff of the assigned office will complete the following actions within 2 working days of issuance of the director's decision: (4)
- Provide one paper copy of the director's decision to the special counsel in the Office of the General Counsel assigned to 2.206 matters. (a)
- E-inail the final version of the director's decision to the NRC Issuances(NRCI) Project Officer,PublishingServicesBranch (PSB),
Officeofthe ChiefInformation Officer (OCIO).lfotherinformation (opinions, partial information (such as errata), or footnotes) is includedin the e-mail, clearlyidentifythe director's decision number at the beginning of each file to avoid administrative delays and" improve the technical production schedule for proofreading, editing; and composingthe documents. In addition, send two paper copies of the signed director's decision to the NRCI Project Officer, (b)
Approved: July 1, 1999
. (Revised: October 25, 2000) 29
Volume 8, Licensee Oversight Programs Review Process for 10 CFR 2.206 Petitions Handbook 8.11 Part V Administrative Issues (H) (continued)
- E-mail a signed, dated, and numbered copy of the director's decision to "NRCWEB" for posting on the NRC's Web site. (c).
The petition manager will prepare headnotes, which are a summary of the petition, consisting of no more than a few paragraphs describing what the petition requested and how the director's decision resolved or closed outthe petition. The petition managerwille-mail the headnotes to the NRCI Project Officer, PSB, aCID, for monthly publication in the NRC Issuances, NUREG-0750. The headnotes should reach PSB*
before the 5th dayof the month followingthe issuance of the director's decision. (5)
Finally, 90 days after issuance of the director's decision, the petition manager will remove the petitioner's name from distribution and/or the service list(s) and inform the licensee that it may also stop sending documents associated with the petition to the petitioner. (6)
.Commission Actions (I)
SECY will inform the Commission of the availability of the director's.
decision. The Commission, at itsdiscretion, may determine to review the director's decision within 25 days of the date of the decision and may direct the staff to take some other action than that in the director's decision. If the, Commission does not act on the director's decision
. within 25 days (unless the Commission extends the review time), the director's decision becomes the final agency action and SECY sends a letter to the petitioner informing the petitioner that the Commission has taken no further action on the petition.
"Approved: July 1, 1999 (Revised; October 25, 2000) 30
c c
,e
~~
2.*"S (I) 0 nl <
Q,n
- . C.
o..
~~
g.<<
w......
til \\0
... \\0
=
w\\O g
w I. ParenthcllcallDformatlon Isassoclalcd Ibndboolc pangnph number.
Rerer to Another PI'llCCSS (e.g..
Rulemaldng)
(111.0.1)
Inronn Petitioner.
OfTcrMt&or Tclccon (I1I.E.tF)
AtPRB address:
2.206? Schedule?
)
"I Immediate Actions?
i Partial DO? Future PRBs? (111.0)
Petitioner AddreSSI
~
~
PRB (III.F.2)
Petitioner Address PRB (111.8.4.9)
Copy orLenerto L1cCMCC <".C.4)
Treat asAllegation I
'lOrRoutine Corresp. (IIA1)
Contact Pctkioncr, OfTerMtgor Ii"<
'c1ccon (1I.C.2&3 Letter willt IssucsfConccms
. letter that Rermnces 2.206 rn
!..... =
f'D
~
N*N
~.
""d
~.
o n f'D rn rn
~
o
~.
(i.
~.
"'1'
~
~
~
~..
,~
~
" ;:S. 0
,;~ =
- ,~a.
. "1 ttl.
000 n...
ttlt"C
. (II....
- .(11 n 1_ ttl
- 0- =
t=i"1 (II
=:..... ttl
=0 ttl
- c...... O O"'.\\.J <
o ~ ttl o.~ "1 fIl
...*,N....
9O*Nc;.
..... 0'"'"
1-lQ\\"'l:'
~'~a
~~~
.... ~ =
O"'O~
.... =~
fit (II (II
Volume 8, Licensee Oversight Programs Review Process for 10 CFR 2.206 Petitions Handbook 8~11 Exhibits:.:
Exhibit 1 Simplified 2.206 Process Flow Chart (continued).
- i a:
o~ "3 >" *
- 05 a
'1~~~r
- 5-6 :
~-------~
au
>------I~f~~1....U~I--~
~~
~ j I
I I
I I
I I
.J
~ r°G; l>
Approved: July 1, i999,*.
(Revised: October 25, 2000) 32
Volume 8, Licensee Oversight Programs ReviewProcess for 10CFR 2.206 Petitions Handbook 8.11 'Exhibits' Exhibit 2 Petition Manager Checklist o Review the petition for allegations and sensitive material. If sensitive, prevent releasing the document to the public. Also determine whether or not any immediate actions requested require expedited staff response.
o Contact the petitioner and discuss the public nature of the process. Offer a pre-PRB meeting or telecon to the petitioner.
o Send a copy of the incoming petition to the licensee and Document Control Desk (Public), with redactions as appropriate.
o If a pre-PRB meeting or telecon is held, notice it (meeting only) and arrange for it to be recorded and transcribed (meeting or telecon), Arrange the meeting and the PRB meeting which will follow it.
o Prepare a PRB presentation. Include the following information:
Does the request meet the criteria for review under 2.206?
What are the issues and their significance?
Is there a need for immediate action (whether requested or not)?
Is there a need for OE, 01, OIG, or OGC involvement?
What is your recommended approach to the response?
What schedule is proposed?
o Hold the pre-PRB meeting or telecon.
o Address the PRB at its meeting.
o Ensure assigned office management agrees with the PRB recommendations, o Inform the petitioner of the PRB recommendations, Offer a post-PRB meeting.
o If a post-PRB meeting or telecon is held, notice it (meeting only) and arrange for it to be recorded and transcribed. Arrange the meeting and the PRB meetingwhich Will follow it o Hold the post-PRB meeting or telecon.
o Address the PRB at its meeting.
o Prepare a meeting summary f~rih~ pre-and post-PRB meetings, if heid. This step is not r~q~ired for a telecon.
. j ";
o Ensure the transcripts of the pre-and post-PRBmeetings or telecons, if held, are added to ADAMS and made publicly available. For meetings, this step can be done using the meeting summary....
Approved: July 1, 1999 (Revised: October 25~ 2000) 33
Volume 8, Licensee Oversight Programs Review Process for 10 CFR*2.206 Petitions Handbook 8.11 Exhibits' Exhibit 2 (continued) o Ensure assigned office management agrees with the PRB final recommendations.
o If the assigned office's management agrees with the PRB that the request is not a 2.206 petition, send a letter to the petitioner, treat any open issues under the appropriate process (e.g., rolemaking). Stop here.
. 0 If the assigned office's management agrees with the PRB that the request is a 2206 petition, continue with this checklist.
o Add petitioner to appropriate service list(s).
o Issue acknowledgment letter and associated Federal Register notice.
o If licensee input is needed, send a written request.
o If further petitioner input is needed, arrange for a technical review meeting.
o Make periodic status updates to the petitioner.
o Prepare the director's decision, addressing:
Each of the petitioners' issues The safety significance of each issue The staff's evaluation of each issue and actions taken o Ensure all referenced documents are added to ADAMS and made publicly available.
o Send the proposed director's decision to the petitioner and licensee for comment.
o After the comment period closes, give the schedule for the director's decision to the Agency 2.206 Petition Coordinator for inclusion in the next 'status report.
o Include comments received and their resolution in the director's decision.
o.Prepare the Federal Register notice for the director's decision.
o As soon as the director's decision is signed:
Inform the petitioner of the substance of the decision and that issuance is imminent.
Hand-carry two full copies ofthe package (including the incoming(s) and distribution and service lists) and five additional copies to the Rulemakings and Adjudication Staff in SECY Hand-carry the original signedFederal Register notice (ONLY), fivecopies ofthe notice, and a disk with the notice on it. to the Rules and Directives Branch. Do NOT include the director's decision in this package.
Approved: July 1, 1999*
(Revised: October 25, 2000f 34
Volume 8, Licensee Oversight Programs ReviewProcess for 10 CFR 2.206 Petitions Handbook 8.11 Exhibits Exh:ibit 2 (continued)
Immediately dispatch the signed original letter and decision and a copy of the FederalRegister notice to the petitioner.
o Within 2 working days of issuing the Director's decision:'
Provide a copy of the director's decision to the OGC special counsel assigned to 2.206 matters.
E-mail and send two paper copies of the director's decision to the NRC Issuances Project Officer in oao..
E-mail a signed, dated, and numbered copy of the director's decision to "NRCWEB."
E-mail headnotes on the petition to the NRC Issuances Project Officer in oao.
Approved: July 1, 1999.
(Revised: October 25, 2000) 35 '
Volume 8, Licensee Oversight Programs Review Process for 10 CFR 2.206 Petitions Handbook 8.11 Exhibits Exhibit 3 Sample Closure Letter for Requests That Are Not 2.206 Petitions
[Petitioner's Name]
[Petitioner's Address]
Dear Mr.:
Your petition dated [insert date] and addressed to the [insert addressee] has been referred to the Office of [insert] pursuant to 10 CFR 2.206 of the Commission's regulations. You request [state petitioner's requests]..As the basis for your request, you state that [insert basis for request].
[You met with our petition review board (PRB) on [insert date] to discuss your petition.
The results of that discussion have been considered in the PRB's determination regarding your request for immediate action and whether or not the petition meets the criteria for consideration under 10 CFR 2.206]. OR [Our petition review board has reviewed your submittal]. The staff has concluded that your submittal does not meet the criteria for
.~
. consideration under 10 CPR 2.206 because [explain our basis, addressing all aspects of the submittal and making reference to the appropriate criteria in this MD].
[Provide the staWs response, ifavailable, to the issues raised]. AND/OR [Explain what further actions, ifany, the staff intends to take in response to the request (e.g., treat it as an allegation or routine correspondencej],
Thank you for bringing these issues to the attention of the NRC.
Sincerely,
[Insert Division Director's Name]
[Office of [insert Office Name]
Docket Nos. [ ]
cc: [Licensee (w/copy of incoming 2.206 request) & Service List]
Approved: July 1, 1999 (Revised: October 25,2000) 36
Volume 8,'Licensee Oversight Programs ReviewProce-ss for 10'CFR 2.206 Petitions Handbook 8.11 Exhibits
- u Exhibit 4 Sample Acknowledgment Letter (petitioner's Name]
[petitioner's Address]
Dear Mr.:
Your petition dated [insert date] and addressed to the [insert addressee] has been referred to me pursuant to 10 CFR 2.206 of the Commission's regulations. You request [state petitioner's requests]. As the basis for your request, you state that [insert basis for request]. I would like to express my sincere appreciation for your effort in bringing these matters to the attention of the NRC.
[You met with our Petition Review Board (pRB) on [insert date] to discuss your petition.
The results of that discussion have been considered in the PRB's determination regarding
[your request for immediate action and in establishing] the schedule for the review of your petition]. Your request to [insert request for immediate action] at [insert facility name] is
[granted or denied] because [staff to provide explanation].
As provided by Section 2.206, we will take action on your request within a reasonable time.
I have assigned [first and last name of petition manager] to be the petition manager for your petition. Mr. [last name of petition manager] can be reached at [301-415-extension of
. petition manager] Your petition is being reviewed by [organizational units] within the Office of [name of appropriate Office]. [If necessary, add: I have referred to the NRC.
- Office of the Inspector General (OIG) those.allegations. of NRCwrongdoing contained in' your petition]. I have enclosed for your information'a 'copy ofthe notice' that is being filed with the Office of the Federal Register for publication. I have also enclosed foryour information a 'copy of Management Directive 8~1l "Review Process for 10 CFR 2.206 Petitions," and the associated brochure NUREG/BR-0200, "Public Petition Process,"
prepared by the NRC Office of Public Affairs..
Sincerely,.
[Office Director]
Enclosures:
FederalRegister Notice Management Directive8.11 NUREG/BR-0200 cc: [Licensee (w/copy of incoming 2.206 request) & Service List]
Approved: July 1,1999 (Revised: October 25, 2000) 37
. Vol~me 8, Licensee.Oversight Programs Review: Process for 10 eFR 2.206 Petitions Handbook 8.11.Exhibits Exhibit 5
[7590-01-P]
Sample Federal Register Notice u.s. NUCLEAR REGULATORY COM1vfiSSION Docket No(s).
License No(s).
[Name of Licensee]
RECEIPT OF REQUEST FOR ACTION UNDER 10 CFR 2.206 Notice is hereby given that by petition dated [insert date]; [insert petitioner's name]
(petitioner) has requested that the NRC take action with regard to [insert facility or licensee name]. The petitioner requests [~tate petitioner's requests].
As the basis for this request, the petitioner states that [state petitioner's basis for
\\..J request].
The request is being treated pursuant to 10 CFR 2.206 of the Commission's regulations. The request has been referred to the Director of the Office of [insert action office]. As provided by Section 2.206, appropriate action will be taken on this petition'.'
within a reasonable time. [The petitioner met with the [insert action office] petition review board on [insert date] to discuss the petition. The results of that discussion were considered in the board's determination regarding [thepetitioner's request for immediate action and in establishing] the schedule for the review of the petition]. [If necessary, add] By letteri.
dated
, the,Director (granted or denied) petitioner's request for [insert request.
for immediate action] at [insert facility/licensee name]. A copy of the petition is available
.in ADAMS for inspection at the Commission's Public Document Room, located at One '
White Flint North, 11555 Rockville Pike (first floor), Rockville, Maryland, and from the.
ADAMS Public Library component on the NRC's Web site, http://www.nrc.gov (the Public Electronic Reading Room).
FOR THE NUCLEAR REGULATORY COMMISSION
[Office Director]
Dated at Rockville, Maryland This day of
-', 200X.
.~'
Approved: July 1, 1999 (Revised; October 25, 2000) 38
~..;.
Volume 8, Licensee Oversight Programs ReviewProcess for 10 CFR 2.206 Petitions Handbook 8.11 Exhibits Exhibit 6
'. Sample Director's Decision'and Cover Letter
[Insert petitioner's name & address]
Dear [insert petitioner's name]:
This letter responds to the petition you filed With [EDO or other addressee of petition]
pursuant to Section 2.206 of Title 10 of the Code ofFederal Regulations (10 CPR 2.206) on
[date of petition] as supplemented on [dates of any supplements]. In your petition you requested that the NRC [list requested actions].
On [date of acknowledgment letter] the NRC staff acknowledged receiving your petition and stated pursuant to 10 CFR 2.206 that your petition was being referred to me for action and that it would be acted upon within a reasonable time. Youwere also told that[staff response to any request for immediate action].
[You met with the petition review board on Idate(s) of the pre-and/or post.PRB..
meeting(s)] to clarify the bases for your'petliion. T1.Ie transcripus) of this/these meeting/s) waslwere treated as (a) supplement(s) to the petition and are available in ADAMS for inspection at the Commission's Public Document Room, located at One White Flint North, 11555 Rockville Pike (first floor), Rockville, Maryland, and from the ADAMS Public Library component on the NRC's Web site, http://www.nrc.gov (the Public Electronic Reading Room)].
[Byletter dated [insert date], the NRC staffrequested [name of licensee] to provide information related to the petition. [Name of licensee] responded on [insert date] and the information provided was considered by the staff in its evaluation of the petition].
In your petition you stated that [summarize the Issues raised]. [Briefly summarize the safety significance of the issues and the staWs response]. '.:.'
[The NRC issued a Partial Director's Decision (DD-YY*XX) dated [insert] which [explain what aspects of the petition were addressed]. [Explain which Issues remained to be addressed in this director's decision and briefly explain the reason for the delay on these issues)).
The staffsent a copy of the proposed director's decision to you and to [licensee(s)] for comment on [date]. [You responded with comments on [date] and the licensee responded on [date]. The comments and the staff's response to them are included in the director's decision]. OR The staffdid not receive any comments on the proposed director's decision].
Approved: July 1, 1999 (Revised: October 25, 2000) 39
V~Ium~ 8, Licensee Oversight Programs ReviewProcess for 10 CFR 2.206Petitions Handbook 8.11 Exhibits Exhibit 6 (continued)
[Summarize the issues addressed in this director's decision and the staffs response].
A copy of the Director's Decision (DD-YY-XX) will be filed with the Secretaryof the Commission for the Commission to review in accordance with 10 CFR 2.206(c). As provided for by this regulation, the decision will constitute the final action of the Commission 25 days after the date of the decision unless the Commission, on its own
. motion, institutes a review of the decision within that time. [The documents cited in the enclosed decision are available in ADAMS for inspection at the Commission's Public Document Rooin, located at One White Flint North, 11555Rockville Pike (first floor),
Rockville, Maryland, and from the ADAMS Public Library component on the NRC's Web site; http://www.nrc.gov (the Public Electronic Reading Room) (cite any exceptions involving' proprietary or other protected information)].
I have also enclosed a copy of the notice of "Issuance of the Director's Decision Under 10 CPR 2.206" that has been filed with the Office of the Federal Register for publication.
[If appropriate, acknowledge the efforts of the petitioner in bringing the issues to the attention of the NRC]. Please feel free to contact [petition manager name and number] to
\\
j discuss any questions related to this petition.
Sincerely;
[Insert Office Director's Name]
Docket Nos. [ ]
Enclosures:
Director's Decision YY-XX Federal Register Notice Approved: July 1, 1999 (Revised: 'October 25, 2000) 40
1 Volume 8, Licensee Oversight Programs Review Process for 10 CFR 2.206 Petitions Handbook 8.11 Exhibits DD*YY*XX UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION OFFI~E OF [INSERT]
[Office Director Name], Director In the Matter of
)
Docket No(s). [Insert]
)
)
[LICENSEE NAME]
)
License No(s). [Insert]
)
)
([plant.or facility name(s)])
)
DIRECTOR'S DECISION UNDER 10 CFR 2.206
- 1. Introduction By letter dated [insert date]. as supplemented on [dates of supplements], [petitioner names and, ifapplica"le, represented organizations] filed a Petition pursuant to Title 10 of the Code ofFederal Regulations, Section 2.206. The petitioner(s) requested that the U.S.
Nuclear Regulatory Commission (NRC) take the following actions: [list requests]. The bases for the requests werel describe].
In a letter dated [insert], the NRC informed the Petitioners that their request for [list immediate actions requested] was approved/denied and that the issues in the Petition were being referred to the Office of [insert] for appropriate action.
[The Petitioner(s) met with the (assigned o~ce abbreviation) petition review,board on
[date(s) ofthe pre-and/or post-PRB meeting(s)] to clarify the bases for the Petition. The transcript(s) of this/these meeting(s) was/Weretreated as (a) supplemenus) to the petition and are available in ADAMS for inspection at the Commission's Public Document Room, located atOne White Flint North, 11555Rockville Pike (first floor), Rockville, Maryland, and from the ADAMS Public Library.component on the NRC~s Web site, http://www.
nrc.gov (the Public Electronic Reading Room)].
[Byletter dated [insert date], the NRC staff requested [name oflicensee] to provide information related to the petition. [Name of licensee] responded on [insert date] and the information provided was considered by the staff in its evaluation of the petition].
[The NRC issued a Partial Director's Decision (DD-YY-XX) dated [insert] which [explain what aspects of the petition were addressed]. [Explain which issues remained to be Approved: July 1,1999' (Revised:.October 25, 2000) 41
Volume 8, Licensee Oversight Programs ReviewProcess for 10 CFR 2.206 Petitions Handbook 8.11 Exhibits addressed in this director's decision and briefly explain the reason for the delay on these
,issues]).
The NRC sent a copy of the proposed director's decision to the Petitioner and to
[licensee(s)] for comment on [date]. [The Petitioner responded Withcomments on [date]
and the licensee(s) responded on [date]. The comments and the NRC staff's response to them are included in the director's decision]. OR [The staff did not receive any comments on the proposed director's decision].
II. Discussion
[Discuss the issues raised, the significance of the issues (or lack thereof), and the staWs response with supporting bases. Acknowledgeany validated issues, even if the staff or the licensee decided to take corrective actions other than those requested by the petitioner.
Clearly explain all 'actions taken by the staff or the licensee to address the issues, even if these actions were under way or completed before the petition was received. This discussion must clearly present the staffresponse to all orthe valid issues so that it is clear that they have been addressed].
Ill. Conclusion
[Summarize the staWs conclusions with respect to the issues raised and how they have been, or will be, addressed].
As provided in 10 CFR 2.206(c), a copy of this Director's Decision will be filed with the Secretary of the Commission for the Commission to review. As provided for by this regulation, the decision will constitute the final action of the Commission 25 days after the date ofthe decision unless the Commission; on its own motion, institutes a review of the decision within that time.
Dated at Rockville, Maryland, this [insert date] day of [insert month, year].
[Office director's name], Director Office of [insert]
Approved: July 1, 1999 (Revised: :October 25, 2000) 42
Volume'S, Licensee Oversight Programs Review Process for io CFR2.206 Petitions Handbook 8.11 Exhibits'
- Exhibit 7
[7590-01...:P]
Sample Federal Register Notice for Dlrector'sDeclslon u.s. NUCLEAR'REGULATORY COMMISSION Docket No(s).
License No(s)..
[Name of Ucensee]
NOTICE OF ISSUANCE OF DlRECfOR'S DECISION UNDER 10 CPR 2.206 Notice is hereby given that the Director, [name of office], has issued a director's decision with regard to a petition dated [insert date], filed by [in'sert petitioner's name],
hereinafter referred to as the "petitioner." [The petition was' supplemented on [insert date,'
include transcripts from meetlngfs) with the*PRB)). The petition concerns the operation of the [insert facility or licensee name]..'.
The petition requested that [insert facility or licensee name] should be [insert request for enforcement-related action]. [lfnecessarY,"add] The petitioner also requested that a public meeting be held to discuss this matter in theWashington, DC, area.
(-
1""
As the basis for the [insert date] 'request, the petitioner raised concernsstemming from [insert ~etitioner's supporting ba~is'for the' requestj: The [ins~rt petitioner's' name].
considers such operation to be potentially ~ris~ei ~rid to;beiin Violation ofFecleral r."
~
\\.
- I
~
regulations. In the petition, a number of references to [insert references] were cited that the petitioner believes prohibit operation of the facilitywith [ilisert the c3~se'for the requested enforcement-relatedactlonl..
.r.'
- The petition of [insert date] raises concerns originating from [insert summary information on more bases/rationale/discussion and supporting facts used in the
.l*
disposition of the petition and the development of the'director's decision].
Approved: July 1,1999 (Revised: October 25, 2000) 43
Volume8, Licensee,Oversight Programs ReviewProcess for 10 CFR 2.206 Petitions Handbook 8.11 'Exhibits Exhibit 7 (continued)
[On [insert date], the petitioner [and the licensee] met with the staff's petition review board]. [On [insert date of public meeting], the NRC conducted a meeting regarding [insert
, facility or licensee name]. The(se) meeting(s) gave the petitioner and the licensee an opportunity to provide additional information and to clarify issues raised in the petition].
The NRC sent a copy of the proposed Director's Decision to the Petitioner and to (licensee(s)] for comment on [date]. [The Petitioner responded with comments on [date] and
'the licensee(s) responded on [date]. The comments and the NRC staff's response to them are included in the Director's Decision]. OR [The staff did not receive any comments on the '
proposed Director's Decision].
The Director of the Office of [name of office] has determined that the request(s), to require [insert facility or licensee name] to be [insert request for enforcement-related action], be [granted/denied]. The reasons for this decision are explained in the director's decision pursuant to 10 CFR 2.206 [Insert DD No.], the complete text of which is available in ADAMS for inspection at the Commission's Public Document Room, located at One White Flint North, 11555 Rockville Pike (first floor), Rockville, Maryland, and via the NRC's Web site (http://www.nrc.gov) on the World Wide Web, under the "Public Involvement" icon.
(Briefly summarize the staff's findings and conclusions].
A copy of the director's decision will be filed with the Secretary of the Commission for the _Commission's review in accordance with 10 CFR 2.206 of the Commission's regulations. As provided ~or by this regulation, the director's decision will constitute the '
final action of the Commission 25 days after the date of the decision, u~ess the Commission, on its own motion, institutes a review of the director's decision in that time.
Dated at Rockville, Maryland, this [insert date] day of [insert month, year].
FOR THE NUCLEAR REGULATORY COMMISSION Original Signed By
[Insert Office Director's Name],
Office of [insert Office Name],
"~
Approved: July 1, 1999 (ReVised: October 25, 2000).
44
Volume 8,Licensee Oversight Programs Review Process for 10 eFR 2.206 Petitions Handbook 8.11.Exhibits Exhibit 8*
Sample Letters Requesting Comments on the Proposed Director's Decision (Note: For clarity,separate letters willneed to be sent to the petitioner and the licensee.
Thissample providesguidancefor both letters.)
[Insert petitioner's address]
Dear [Insert petitioner's name]
Yourpetition dated [insert date] and addressed to the [insertaddressee) has been reviewed by the NRC staff pursuant to 10 CFR 2.206 of the Commission's regulations. The staff's proposed director's decisionon the petition is enclosed. I request that you provide commentsto me on anyportions of the decision that youbelieve involve errors or any issues in the petition that youbelieve have not been fullyaddressed. The staff ismaking a similarrequest of the licensee.The staffwillthen reviewanycommentsprovided byyou and the licensee and consider them in the final version of the director's decisionwith no further opportunity to comment.
Please provide your commentsby [insert date, nominally 2 weeks from the date of this letter].
Sincerely,
[Signed byDivisionDirector)
Docket Nos. 0 ccw/oencl: [Service List]
[Insert licensee's address]
Dear [Insert licensee's name]
By letter dated [insertdate], [insertname of petitioner] submitted a petitionpursuantto 10CFR 2206 of the Commission's regulations with respectto [insertname(s) of affected facilities). The petition hasbeen reviewed by the NRC staffand the staff's proposed director's decision on the petitionisenclosed. I request that you provide comments to me on any portions of the decision that youbelieveinvolve.errors or anyissues in the petitionthat you believe have not been fully addressed. The staff is makinga similarrequest of the petitioner.
The staffwill then review anycomments providedby youand the petitionerand consider them in the final version of the director'sdecision with no furtheropportunity to comment Approved: July 1,1999 (Revised: October 25, 2000)
.0
Volume 8, Licensee Oversight Programs Review Process for 10 CFR 2.206 Petitions Handbook 8.11 Exhibits Exhibit 8 (continued)
Please provide your comments by [insert date, nominally 2 weeks from the date ofthis letter].
Sincerely,
[Signed by Division Director]
Docket Nos. [ ]
cc w/enel: [Service List]
Approved: July 1, 1999 (Revised: October 2S, 2000),
46 NUREG/BR-0200 Public Petition Process ADAMS Accession No. ML050900248
Inlroduction The U.S. Nuclear Regulatory Commission (NRC) wax esrahfishcd in 197510 protect public health and safety in the civilian use of nuclear power and materials in the United States. As parr of its responsibilities, NRC assesses all potential health and safely issues related to licensed activities and encourages members of the public to bring safety issues to its allen Lion.
Section 2.201> of Title I [) of the C",It, 0(
Federal Re/ill/",;o/!.\\ (10 eFR 2.2(6) Jescribc's the petition process-the primary mechanism for the public to request enforcement action by NRC in a public process. *' This process permit." anyone to petition NRC 10 take enforcement action related to NRC licensee...
or licensed activities. Depending on the results of its evaluation, NRC could modify. suspend.
or revoke an NRC-issucd license or take unv other appropriate enforcement action t~l resolve a problem, Requests that raise health and safety issue s without request ing enforcement action are reviewed by means other than the 2.206 process.
In il~ effort III improve public confidence, the NRC periodically reassesses the 2.206 petition process to enhance its effectiveness, timeliness and credibility. As pan ofthese reassessment>>.
the NRC seeks feedback from petitioners and other stakeholders through public meetings and workshops., surve)s and Fet/era/ Rc,;;s/('"
notices, as well as from its own slafl experience. Specific irnprovement~ ((l the 2.206 process resulting from these iniliative:-.
include:
- Offering petitioner~ two opportunities Lo discuss the petition with the NRCs petition review board (PRB). The first i" 10 allow the pelifioncr to provide elaboration and claritication oflhe petilion
- Th~ NRC al",) ha-' an alkgalltln pnxe." In WhKh1I1l1l\\,..llI,lh whu liii,c pOlcmial ~aft:ly ~'(lnCt'rrJ' for NRC revicw
~rc iltlorded a dcgret" of pwtcl.'(wn of lhclr lllenlll)'. OIIl.:T prllccs~s for puhll(' in\\(lh'clnt'1Il ar.. 11,h,.'lI.ilthe ('II'"of,hi' pamphkl before the PRB meets (0 discuss the petition. The second opportunity comes after the PRB has discussed the merits of the petition and allows the petitioner to comment on the PRB's recommendations regarding acceptance of the petition and any requests for immediate action.
- Offering an opportunity for a 'Iaff petitioner-licensee meeting to discuss the details of the issue during the course of the review, Providing bcuer, more frequent cornmu nicatiuns between the staff and petitioner throughout the process Providing copies of all pertinent petition related correspondence and other doc umenis 10 the petitioners Providing a copy of the proposed director's dccisiou un the petition. hoth to the petitioner and the aflecred licensee for l'(IIl'Il~nt,. and considering such cornmcru before i....~uing the decision ill final form.
The Petition P.,,,,ess The ~.206 process provides a..imple. effective mechanism for anyone to request enforcement action and obtain NRC's prompl. thorough.
and objecuve evaluation of underlying safety issue>>. It is :'.l."paratc and distinct from Ihe prnce"iSC"i for ruknwking and liccnsing.
although they too allow the puhlic to raise safcty l'oncerns 10 NRC.
Under the 2.206pnx:css, Ihe petitioner submits a request in wriling Lo NRC's Executive Director for Operations, identifying the affected licensee or licensed activity, the requcslcd enforcement action to he taken, and the facts the petitioner helievcs provide sufficient grounds for NRC to take enforcclnem action. UnslIppc.)ned assenions of "safet)' prohlems,"
gcnt:r~1 Opposiliun hi nuclear power, or identification of safety issues wilhout seeking enforcement action are not considered sufficient ground" for consideralion as a 2.206 petition.
After receiving a request, NRC determines whether the request qualifies as a 2.201>
petition. If the request is accepted for review as a 2.206 pctition, the NRC sends an acknowledgment letter to the petitioner and a copy to the appropriate licensee and publishes a notice in the Federal Register: If the request is not accepted. NRC notifies the petitioner of its decision and indicates that the petitioner's underlying safety concerns will be considered outside the 2.206 process.
On the basis of an evaluation of the petition.
the appropriate office director issues J decision
<Ind. if wurrarued, NRC lakes appropnatc enforcement action. Throughout (he evaluation process. NRC sends copies of all pertinent correspondence 10 the petitioner and the affected licensee. NRC places all related correspondence in it~ Public D(X'UIl1Cllt Room IPDR) in Rockville. Marvland. and in the agency document control system. However.
the agency withhold.. information IhJI would compromise all invcvugation or ongPlng enforcement action relating lO ISMll'S in the petit ion. The NRC al...o sends the pcutionet other information such as pertinent generic letters and hullcunv.
The NRC noli ties the petitioner (If the petition....
status every 60 days, or more frequently if a significant action occur..... Monthly updates on all pending 2.100 petitions arc availahlc on NRC's web site at http://\\,,'ww.nrc.go\\/
readin\\:*rmhJoc-colleqjon~ipc-titions"'-206/
index.htm!. and in the PDR.
Pelilion Techniral Review Meerinl:
A petition technical review meeting sc-rves not only as a snurel' llf potentially valuahk infnrmalion for NRC to cvalu:.ltc ;J 1.206 petilion, bUI also ilffnrd:-. rhe pelitioner substanlive involvement in the revie\\J, and decision-making proee:-.s through direct discussions with NRC and the licensee. SUl'h a meeting will he held whenever theSlafi believes thaL it would be beneficial to the review of the pelition. Note that the meeling can be offered at allY lime duling NRC's review of a petition lJnd is open to puhlil' ohservation.
Director's Decision The NRC" official response 10 a 2.206 petition is a written decision by the director of the appropriate office that addresses the concerns raised in the petition, The agency's goal is to issue a proposed decision for comment within 120 dav.. from the date ofthe ucknowlcdamem kiter. Howc\\'C'r. additional time may be n~ccded to conduct an investigation. complete an inspection. or analyze particularly complex technical Issues.Ifthe goal is not met. the NRC staff will promptly inform the petitioner 01 a
..chcdule change.
The d ircctnrx decision includes the protcxsional staff... evaluation of all pertinent mformation from the petition. correspondence wu h the peuuuner and the lice nscc.
mtonuation from any meeting. results of any ill\\T"iligalion or inspection. and any othe:
documcrus n-latcd hJpetition issucs. Following resolution of JIl\\, comments received 011 the proposed dccistt~lIl. the director's decision i.,
provided 10 the petitioner and the licensee. and i.... posted In NRC's wch..ne and made available
[11 the PDR. A notice of uvuil abi lit v i-,
pohlishcd in the Federal Register:
Dirccturs dcci..inns may he issued as follows:
- A dec-ision granting a petition. III full.
explains the hasis fur the decision and grants the action requested in the petition (e.g., NRC iSSllill~ an order to modif)',
su~pcnd, or rc\\'oke a license).
A decision denying a pelition. In full.
provides th~ reason for the denial and discusses all m~lllers raised in the petition.
A dccision granting a pCLition, in pan, in ca:-.es where the NRC decides nol 10 grant the action requested, but fakes olher appnlpriate enforccmcnt action or direct:-.
the licClhCC to take cCflain adions that address the identified safety conccrn:-..
A partial director's decision In;Jy be issued hv the NRC in cases where some of thc is"sues associated with the petition can he completed promptly blll significant
~ehedulc delays arc anticipated hefore
resolution of the entire petition. A final director's decision is issued at the conclusion of the effort.
The Commission will not entertain requests for review of a director's decision. However, on its own, it may review a decision within 25 calendar days.
NRC Management Directive 8.11. "Review Process for 10 CFR 2.206 Petitions:' contains more detailed information on citizen petitions.
For a free copy of the directive, write to the Superintendent of Documents, U.S.
Government Printing Office, P.O. Box 37082, Washington, DC 20013-7082, or call 202 SI2-1800.
Electronic Access Those parts of the monthly status report on 2.206 petitions that are not of a sensitive nature. as well as recently issued director's decisions, and Management Directive 8.11, are placed on the NRC's web site at http://
www.nrc.govlreading-rm/doc-collections/
petitions-2-206/index.html and in the agency's Public Document Room.
Other Processes for Public Involvement In addition to the 2.206 petition process. NRC has several other ways that permit the publ ic to express concerns on matters related to the NRC's regulatory activities.
- The NRC's allegation process affords individuals who raise safety concerns a degree of protection of their identity.
- Under the provisions of 10 CFR 2.802.
NRC provides an opportunity for the public to petition the agency for a rulemaking,
- The NRC's licensin g process offers members of the public, who are specifically affected by a licensing action.
an opportunity to formally participate in licensing proceedings. This process applies not only to the initial licensing actions but also to license amendments and other activities such as decom missioning and license renewals.
- For major regulatory actions involving preparation of environmental impact statements, NRC offers separate opportunities for public participation in its environmental proceedings.
- The public can attend a number of meetings including open Commission and staff meetings, periodic media briefings by Regional Administrators. and special meetings held near affected facilities to inform local communities and respond to their questions.
More information on these activities can be found in NRC's pamphlet entitled. "Public Involvement in the Nuclear Regulatory Process," NUREG/BR-0215.
Office of Public Affairs U. S. Nuclear Regulatory Commission Washington, DC 20555-000 1 Telephone 301-415-8200 or 1-800-368-5642 NUREG/BR-0200. Rev. 5 February 2003
P. Hodes
- 3 After reviewing the information from the extensive NRC actions to date, the NRR Director, in consultation with the Region I Regional Administrator, has concluded that there are no issues that would lead the NRC to prohibit Entergy from restarting Vermont Yankee from its current outage. The NRC has reasonable assurance that the health and safety of the public, as well as the environment, are being protected and there are no immediate safety concerns. NRR management will review the NRC staff's evaluation of the issues identified in your petition to ensure that Entergy is taking appropriate action in response to the abnormal plant leakage.
NRC inspectors continue to closely observe and review Entergy's actions. The Director of NRR will issue the final Director's Decision on your petition. We will continue to communicate with you and your staff concerning developments at Vermont Yankee, and we will ensure that you receive NRC inspection documents related to the topics in your petition as they are completed.
As required by 10 CFR 2.206, the NRC will take action on your petition within a reasonable time. John Boska has been assigned as the petition manager for your petition. He can be reached at 301-415-2901. I have enclosed for your information a copy of the notice that the NRC is filing with the Office of the Federal Register for publication. I have also enclosed for your information a copy of Management Directive 8.11, "Review Process for 10 CFR 2.206 Petitions," and the associated brochure NUREG/BR-0200, "Public Petition Process," prepared by the NRC Office of Public Affairs.
Sincerely, IRA MVirgilio fori R. W. Borchardt Executive Director for Operations Docket No. 50-271
Enclosures:
- 1. Federal Register Notice
- 3. NUREG/BR-0200 cc: Listserv DISTRIBUTION: G20100235/LTR-10-0175/EDATS: SECY-2010-0235 See next page ADAMS Accession Nos:
Package: ML101310044 Incoming: ML101120663 Letter: ML101310049 Federal Register Notice: ML101310059 Management Directive 8.11: ML041770328 NUREG/BR-0200' ML050900248
- Via email OFFICE LPL1-1/PM LPL1-1/LA*
Tech Editor*
LPL1-1/BC DPR/DD DORUD NAME JBoska SLittie KAzariah-Kribbs NSalgado TBlount JGiitter DATE 5/13/10 5/11/10 5/12/10 5/13/10 5/13/10 5/13/10 OFFICE OCA*
RI/RA*
NRR/OD EDO NAME EDacus SCali ins ELeeds RBorchardt (MVirgilio for)
DATE 5/13/10 5/14/10 5/14/10 5/20/10