E-Mail from Chou to Herrin, Sgr Inspection
ML101190449
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 01/20/2010
From: Chou R
NRC/RGN-II/DRS/EB3
To: Herrin D
Progress Energy Florida
References
FOIA/PA-2010-0116
Download: ML101190449 (1)


Text

Franke, Mark From:

Chou, Rich' Sent:

Wednesday, January 20, 2010 11:52 AM To:

Herrini Dennis W.

Cc:

Sykes, Marvin; Morrissey, Thomas;.Reyes Rogerio; Franke, Mark; Lake, Louis; Chou, Rich; Ninh, Son

Subject:

RE: SGR Inspection Dennis:

The tentative inspection schedule is as-follow:

1. Detension 2/1-2/5/2010
2. Concrete Removal 2/15 - 2/19/2010 3.: Concrete Forming, Rebar, Pour 2/27 -3/9/2010 (could be two persons, I do not know another to be.)
4. Retension 3/12 - 3/21/2010
5. Concrete Scan/Boring 3/21 - 3/23/2010
6. Document Review 3/24 - 3/30/2010 This schedule was based on your scheduler Calvin Goering provided schedule. Generally, just myself will be there except as noted.'::The inspection-schedule could be changed-and additional-inspections could be addedin depend on your activities and work complexity:

From: Herrin, Dennis W. [mailto: Dennis.Herrin@pgnmail.com]

Sent: Friday, January 15, 2010 2:08 PM To: Chou, Rich Subje*c*tGR Inspection Can you, provide your estimate for onsite visits to-CR-3 in the near-term?

Lead Enqgineer.:- LicensinglA Regulatory Programs Progres5 Energy Florida, Inc.

Crys, talI iver Unit I3 352-563-4633 (b)(6)

Cell)-

)

Voicenet' 240ý-3299 Dennis.Herrin@pgnmail.com l

f llumation in tis record was deleted in

&GOnjdancew i the Freedom of Information Act, 67