Franke, Mark From:
Chou, Rich' Sent:
Wednesday, January 20, 2010 11:52 AM To:
Herrini Dennis W.
Cc:
Sykes, Marvin; Morrissey, Thomas;.Reyes Rogerio; Franke, Mark; Lake, Louis; Chou, Rich; Ninh, Son
Subject:
RE: SGR Inspection Dennis:
The tentative inspection schedule is as-follow:
- 1. Detension 2/1-2/5/2010
- 2. Concrete Removal 2/15 - 2/19/2010 3.: Concrete Forming, Rebar, Pour 2/27 -3/9/2010 (could be two persons, I do not know another to be.)
- 4. Retension 3/12 - 3/21/2010
- 5. Concrete Scan/Boring 3/21 - 3/23/2010
- 6. Document Review 3/24 - 3/30/2010 This schedule was based on your scheduler Calvin Goering provided schedule. Generally, just myself will be there except as noted.'::The inspection-schedule could be changed-and additional-inspections could be addedin depend on your activities and work complexity:
From: Herrin, Dennis W. [mailto: Dennis.Herrin@pgnmail.com]
Sent: Friday, January 15, 2010 2:08 PM To: Chou, Rich Subje*c*tGR Inspection Can you, provide your estimate for onsite visits to-CR-3 in the near-term?
Lead Enqgineer.:- LicensinglA Regulatory Programs Progres5 Energy Florida, Inc.
Crys, talI iver Unit I3 352-563-4633 (b)(6)
Cell)-
)
Voicenet' 240ý-3299 Dennis.Herrin@pgnmail.com l