ML101110615

From kanterella
Jump to navigation Jump to search
Watt Bar 2 Construction Project 2009 Annual Assessment - Meeting Presentation Slides
ML101110615
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 04/20/2010
From: James Baptist
NRC/RGN-II/DCP/CPB3
To:
References
Download: ML101110615 (11)


Text

Watts Bar 2 Construction Project 2009 Annual Assessment April 20, 2010 1

Purpose of Meeting

  • Discuss the NRCs 2009 annual assessment of the Watts Bar 2 construction project.
  • Provide an overview of the construction inspection program for Watts Bar 2.
  • Introduce Resident Staff
  • Respond to questions and comments from the public.

2

Background

  • 1985; TVA suspended construction of Watts Bar Unit 2.
  • 1990-1995; TVA concentrated on construction of Unit 1 and addressed quality issues on Unit 1.
  • July 2000; TVA informs NRC that Unit 2 is in a deferred status in accordance with Commission Policy Statement
  • August 3, 2007; TVA informed NRC of its plan to resume construction of Watts Bar Unit 2.
  • July 7, 2008, the NRC issued an Order extending the Watts Bar Unit 2 construction permit completion date to March 31, 2013.

3

Construction Inspection Organization Region II Construction Inspection Program Division Division of Of Construction Inspection Construction Projects Construction Inspection Construction Projects Branches Branch 3 Senior Project Inspector Specialist Inspectors Project Inspector Senior Resident Inspector Resident Inspectors 4

Construction Inspection Program

  • IMC 2517, Watts Bar Unit 2 Construction Inspection Program, supplements traditional inspection program NRC Construction Inspection Program Preop Testing Construction Phase & Operational Prep Startup Testing IMC 2512 IMC 2513 IMC 2514 5

Assessment Process Cross-cutting aspects reviewed Increased during Mid Cycle & End of Cycle Inspections Assessments Inspection (Quarterly, Significant Cause Program Mid Cycle , Issues Evaluation Results End Of Cycle)

Special Inspections Annual Public Meeting 6

Scope of Inspections in 2009

  • Completed four quarterly inspections; in addition to three resident inspectors, 11 regional inspectors conducted inspections for one or more weeks in 2009.
  • Completed Problem Identification and Resolution Inspection in June 2009.
  • Completed Engineering Document Inspection in August 2009
  • Key areas of 2009 inspections; quality assurance program; TVAs oversight of contractors; procedure and program development; training and qualification of key personnel; procurement; and actual construction activities.

7

Inspection Program Results

  • Overall the inspections concluded that TVAs program and procedures were adequate to support ongoing construction activities.
  • With the exception of two severity level IV violations, construction activities were performed in accordance with NRC regulations and requirements.
  • The corrective program was generally effective in identifying, classifying, and resolving problems.

8

Watts Bar Unit 2 Resident Inspectors Bill Bearden - Senior Resident Inspector Tomy Nazario - Resident Inspector Russ Lewis - Resident Inspector Ken Miller - Resident Inspector 9

Upcoming Inspection Activities

  • Continue to inspect activities specified in IMC 2512
  • Inspect Refurbishment activities
  • Inspect Other Areas

- Corrective Action Programs (CAPs)

- Special Programs (SPs)

- Generic Communication items

- Open Items

  • Perform Problem Identification and Resolution inspection.
  • Perform Engineering Inspection 10

QUESTIONS?

11