UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 30, 2010 Vice President, Operations Entergy Operations, Inc.
Waterford Steam Electric Station, Unit 3 17265 River Road Killona, LA 70057-0751
SUBJECT:
WATERFORD STEAM ELECTRIC STATION, UNIT 3 - CLOSEOUT OF BULLETIN 2007-01 "SECURITY OFFICER ATTENTIVENESS" (TAC NO.
MD7667)
Dear Sir or Madam:
On December 12,2007, the U.S. Nuclear Regulatory Commission (NRC) issued Bulletin 2007 01, "Security Officer Attentiveness" (Agencywide Documents Access and Management System (ADAMS) Accession No. ML073400150).
Entergy Operations, Inc. (the licensee) provided a response dated February 7,2008, (ADAMS Accession No. IVIL080430053) to Bulletin 2007-01. The NRC staff reviewed the licensee's response for Waterford Steam Electric Station, Unit 3 (Waterford) and staff identified a need for additional information. The NRC staff issued a Request for Additional Information (RAI) to the licensee on June 30,2008 (ADAMS Accession No. ML081780438). The licensee provided a response to the RAI on August 13, 2008 (ADAMS Accession No. ML082280142), which included detailed descriptions of the administrative and managerial controls to deter and address inattentiveness and complicity among licensee security personnel at Waterford. Due to the sensitivity of the subject matter, some responses may contain Security-Related Information and may not be publicly available.
The NRC staff has reviewed the submitted information and has concluded that the response to Bulletin 2007-01 and the subsequent RAI is adequate for Waterford. The bases for the NRC's conclusion have been documented in a memorandum, "Security Bulletin 2007-01, Security Officer Attentiveness: Summary Report" (ADAMS Accession No. ML093440311). Based on this review,Bulletin 2007-01 will be closed and no further action is required.
If you have any questions regarding this letter, please feel free to contact me at (301) 415-1480.
Sincerely, ~
N. Kaly Kalyanam, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-382 cc: Distribution via Listserv
March 30, 2010 Vice President, Operations Entergy Operations, Inc.
Waterford Steam Electric Station, Unit 3 17265 River Road Killona, LA 70057-0751
SUBJECT:
WATERFORD STEAM ELECTRIC STATION, UNIT 3 - CLOSEOUT OF BULLETIN 2007-01 "SECURITY OFFICER ATTENTIVENESS" (TAC NO.
MD7667)
Dear Sir or Madam:
On December 12,2007, the U.S. Nuclear Regulatory Commission (NRC) issued Bulletin 2007 01, "Security Officer Attentiveness" (Agencywide Documents Access and Management System (ADAMS) Accession No. ML073400150).
Entergy Operations, Inc. (the licensee) provided a response dated February 7,2008, (ADAMS Accession No. ML080430053) to Bulletin 2007-01. The NRC staff reviewed the licensee's response for Waterford Steam Electric Station, Unit 3 (Waterford) and staff identified a need for additional information. The NRC staff issued a Request for Additional Information (RAI) to the licensee on June 30, 2008 (ADAMS Accession No. ML081780438). The licensee provided a response to the RAI on August 13, 2008 (ADAMS Accession No. ML082280142), which included detailed descriptions of the administrative and managerial controls to deter and address inattentiveness and complicity among licensee security personnel at Waterford. Due to the sensitivity of the subject matter, some responses may contain Security-Related Information and may not be publicly available.
The NRC staff has reviewed the submitted information and has concluded that the response to Bulletin 2007-01 and the subsequent RAI is adequate for Waterford. The bases for the NRC's conclusion have been documented in a memorandum, "Security Bulletin 2007-01, Security Officer Attentiveness: Summary Report" (ADAMS Accession No. ML093440311). Based on this review,Bulletin 2007-01 will be closed and no further action is required.
If you have any questions regarding this letter, please feel free to contact me at (301) 415-1480.
Sincerely, Ira!
N. Kaly Kalyanam, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-382 cc: Distribution via Listserv DISTRIBUTION:
PUBLIC LPLIV Reading RidsAcrsAcnw_MailCTR Resource RidsNrrDorlLpl4 Resource RidsOgcRp Resource RidsRgn4MailCenter Resource RidsNrrPMWaterford Resource RidsNrrLA.IBurkhardt SStuchell, DPR/PGCB ADAMS Accession No.: ML100820317 OFFICE LPL4/PM LPL1-2/LA LPL4/BC LPL4/PM NAME KKalyanam ABaxter MMarkley (BSinqal for) KKalyanam DATE 3/24/10 3/24/10 3/30/10 3/30/10