ML100780551

From kanterella
Jump to navigation Jump to search

Acceptance of LAR for Clinton Power Station, Unit 1 Regarding TSTF-425 Risk-Informed Relocation of Surveillance Frequency Requirements (ME3332)
ML100780551
Person / Time
Site: Clinton Constellation icon.png
Issue date: 03/19/2010
From: Nicholas Difrancesco
Plant Licensing Branch III
To: Hansen J, Matthew Mitchell
Exelon Corp
DiFrancesco N, NRR/DORL/LPL3-2, 415-1115
References
TAC ME3332
Download: ML100780551 (2)


Text

From:

DiFrancesco, Nicholas Sent:

Friday, March 19, 2010 2:47 PM To:

Mitchel.Mathews@exeloncorp.com; jeff.hansen@exeloncorp.com Cc:

Howe, Andrew; Waig, Gerald

Subject:

Acceptance of LAR for Clinton Power Station, Unit 1 Regarding TSTF-425 Risk-Informed Relocation of Surveillance Frequency Requirements (ME3332)

Mr. Mathews, By letter dated February 15, 2010, Exelon Generation Company, LLC (the licensee) submitted license amendment request (LAR) for Clinton Power Station, Unit 1 (ADAMS Accession No. ML100470787). The LAR proposes to modify the Clinton Technical Specifications (TS) using a risk-informed approach by relocating specific surveillance frequencies to a licensee-controlled program with the implementation of Nuclear Energy Institute 04-10, in accordance with TS Task Force (TSTF) change traveler TSTF-425, Revision 3, with certain deviations/variations. The purpose of this message is to provide the results of the Nuclear Regulatory Commission (NRC) staff's acceptance review of this LAR. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review was also intended to identify whether the applications have any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license must fully describe the changes requested and follow, as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application and has concluded that it provides technical information in sufficient detail to enable the NRC staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendments in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the NRC staff to complete its technical review, you will be advised by separate correspondence.

In accordance with our process as described in LIC-109, "ACCEPTANCE REVIEW PROCEDURES," I am placing a copy of this email in ADAMS as a publicly-available, official agency record.

Sincerely, Nicholas DiFrancesco Project Manager Nuclear Regulatory Commission Division of Operating Reactor Licensing nicholas.difrancesco@nrc.gov Tel: (301) 415-1115 Fax: (301) 415-1222

E-mail Properties Mail Envelope Properties (0046140293E11F408991442DB4FE25CA069EDE2AF7)

Subject:

Acceptance of LAR for Clinton Power Station, Unit 1 Regarding TSTF-425 Risk-Informed Relocation of Surveillance Frequency Requirements (ME3332)

Sent Date: 03/19/2010 2:47:31 PM Received Date: 03/19/2010 2:47:31 PM From: DiFrancesco, Nicholas Created By: Nicholas.DiFrancesco@nrc.gov Recipients:

Mitchel.Mathews@exeloncorp.com (Mitchel.Mathews@exeloncorp.com)

Tracking Status: None jeff.hansen@exeloncorp.com (jeff.hansen@exeloncorp.com)

Tracking Status: None Andrew.Howe@nrc.gov (Howe, Andrew)

Tracking Status: None Gerald.Waig@nrc.gov (Waig, Gerald)

Tracking Status: None Post Office:

HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 19396 03/19/2010 Options Expiration Date: