MONTHYEARML24284A1972024-10-10010 October 2024 Cover Letter Oyster Creek, License Termination Plan Acceptance Review ML24269A0462024-10-0404 October 2024 Cover Letter for Oyster Creek Nuclear Generating Station, License Amendment Request, License Termination Plan, Acceptance Review Request for Additional Information ML24274A0822024-09-25025 September 2024 Independent Spent Fuel Storage Installation Security Plan, Training Qualification Plan, Safeguards Contingency Plan, Revisions 1 and 2 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 05000219/20240022024-09-0505 September 2024 – NRC Inspection Report 05000219/2024002 and 07200015/2024001 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 ML24214A0372024-08-0101 August 2024 License Amendment Request to Revise Renewed Facility Operating License to Add License Condition 2.C.(18) to Include License Termination Plan Requirements ML24179A1842024-07-23023 July 2024 June 20, 2024, Clarification Call on Preapplication Readiness Assessment of the Holtec Decommissioning International License Termination Plan ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000219/20240012024-05-14014 May 2024 Decommissioning Intl, LLC Oyster Creek Nuclear Generating Station - NRC Inspection Report No. 05000219/2024001 ML24120A0412024-04-29029 April 2024 Annual Radioactive Environmental Operating Report for 2023 L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 ML24120A0402024-04-29029 April 2024 Annual Radioactive Effluent Release Report for 2023 ML24094A2142024-04-19019 April 2024 Preapplication Readiness Assessment of the Holtec Decommissioning International License Termination Plan ML24089A2492024-03-29029 March 2024 Reply to Notice of Violation EA-2024-024 L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) ML24085A7902024-03-28028 March 2024 – Preapplication Readiness Assessment of the License Termination Plan ML24081A2882024-03-21021 March 2024 Request Preliminary Review and Feedback on Chapter 6 of the Draft License Termination Plan ML24046A1242024-02-29029 February 2024 – NRC Inspection Report 05000219/2023003 ML24033A3272024-02-0202 February 2024 Request Preliminary Review and Feedback on Chapter 5 of the Draft License Termination Plan ML23342A1162024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 IR 05000219/20230022023-11-0909 November 2023 EA-23-076 Oyster Creek Nuclear Generating Station - Notice of Violation and Proposed Imposition of Civil Penalty - $43,750 - NRC Inspection Report No. 05000219/2023002 ML23286A1552023-10-13013 October 2023 Defueled Safety Analysis Report (DSAR) ML23249A1212023-09-0606 September 2023 NRC Inspection Report 05000219/2023002, Apparent Violation (EA-23-076) ML23242A1162023-08-30030 August 2023 Biennial 10 CFR 50.59 and 10 CFR 72.48 Change Summary Report January 1, 2021 Through December 31, 2022 ML23214A2472023-08-22022 August 2023 NRC Inspection Report 05000219/2023002 IR 05000219/20230012023-05-31031 May 2023 NRC Inspection Report No. 05000219/2023001 IR 07200015/20234012023-05-16016 May 2023 NRC Independent Spent Fuel Storage Installation Security Inspection Report 07200015/2023401 L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 ML23114A0912023-04-24024 April 2023 Annual Radioactive Effluent Release Report for 2022 ML23114A0872023-04-24024 April 2023 Annual Radioactive Environmental Operating Report for 2022 L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000219/20220022023-02-0909 February 2023 NRC Inspection Report No. 05000219/2022002 ML23031A3012023-02-0808 February 2023 Discontinuation of Radiological Effluent Monitoring Location in the Sewerage System ML23033A5052023-02-0202 February 2023 First Use Notification of NRC Approved Cask RT-100 ML23025A0112023-01-24024 January 2023 LLRW Late Shipment Investigation Report Per 10 CFR 20, Appendix G ML22347A2732022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 ML22297A1432022-12-15015 December 2022 Part 20 App G Exemption Letter L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 IR 07200015/20224012022-12-0606 December 2022 NRC Independent Spent Fuel Storage Installation Security Inspection Report 07200015/2022401 (Letter & Enclosure 1) ML22280A0762022-11-0202 November 2022 Us NRC Analysis of Holtec Decommissioning Internationals Funding Status Report for Oyster Creek, Indian Point and Pilgrim Nuclear Power Station ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22286A1402022-10-13013 October 2022 NRC Confirmatory Order EA-21-041 IR 05000219/20220012022-08-11011 August 2022 NRC Inspection Report 05000219/2022001 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22214A1732022-08-0202 August 2022 Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E ML22207B8382022-07-26026 July 2022 NRC Confirmatory Order EA-21-041 2024-09-05
[Table view] |
Text
April 14, 2010 Patricia A. Kurkul Regional Administrator NMFS Northeast Regional Office 55 Great Republic Drive Gloucester, MA 01930
SUBJECT:
REINITIATION OF FORMAL CONSULTATION FOR ENDANGERED SEA TURTLES AT THE OYSTER CREEK NUCLEAR GENERATING STATION
Dear Ms. Kurkul:
The U.S. Nuclear Regulatory Commission (NRC) requests reinitiation of formal consultation under Section 7 of the Endangered Species Act regarding the continued operation of the Oyster Creek Nuclear Generating Station (OCNGS). The current incidental take statement (ITS) from your November 21, 2006, biological opinion authorizes the annual take no more than eight total sea turtles captured or impinged annually (with no more than three dead), of which three are likely to be loggerheads (with no more than one dead) and no more than one green sea turtle (with no more than one dead). The ITS assumes that all sea turtles captured or impinged have been injured from interactions with the trash bars. The take includes sea turtles that may have died prior to impingement at the OCNGS intakes.
In 2009, OCNGS had 11 incidental total takes of sea turtles, four of which were dead at recovery and one of which died afterwards. Ten of the total turtles were Kemps ridleys and one was an Atlantic green turtle (live). These numbers exceed both the total sea turtle take and the number of dead Kemps ridley turtles. You should have received detailed information on the takes in Excelons Annual Sea Turtle Tale Report for 2009 dated December 31, 2009 (ADAMS Accession Number ML100060068). The NRC requests a reinitiation of formal consultation because OCNGS exceeded the take level authorized by the ITS. As part of this reinitiation of consultation, the NRC requests a revision to the 2006 ITS. Plant design and operating procedures have not changed since the 2006 ITS. In its biological assessment dated March 29, 2005 (ADAMS Accession Number ML050900162), NRC staff anticipated that a trend of increasing takes would continue for some years due in part to modifications to the Barnegat Bay Inlet and in part to increases in turtle populations.
P. Kurkul The sea turtle season at OCNGS begins roughly on June 1st. The NRC looks forward to working closely with National Oceanic and Atmospheric Administration Fisheries in this reinitiation of Section 7 consultation for protection of sea turtles. If you have any questions regarding the staffs request, please contact Dennis Logan of the Environmental Review Branch, Division of License Renewal by phone at 301-415-0490 or by e-mail at dennis.logan@nrc.gov.
Sincerely,
/RA/
Andrew Imboden, Chief Environmental Review Branch Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-219
ML100760288 OFFICE AB:RERB:DLR LA:RPOB: BC:RERB:ASI PM:DORL:GEM NAME DLogan IKing AImboden EMiller DATE 4/07/10 4/5/10 4/14/10 4/7/10 Letter to P. Kurkul from A. Imboden dated April 14, 2010
SUBJECT:
REINITIATION OF FORMAL CONSULTATION FOR ENDANGERED SEA TURTLES AT THE OYSTER CREEK NUCLEAR GENERATING STATION DISTRIBUTION:
HARD COPY:
DLR RF E-MAIL:
PUBLIC [or NON-PUBLIC, if appropriate]
RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRerb Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDraAfpb Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenterResource RidsOpaMailResource L. Regner A. Hiser B. Pham D. Tifft, RI N. McNamara, RI D. Scenci, RI R. Conte, RI B. Harris, OGC
Oyster Creek Nuclear Generating Station cc:
Site Vice President - Oyster Creek Senior Resident Inspector Nuclear Generating Station U.S. Nuclear Regulatory Commission AmerGen Energy Company, LLC P.O. Box 445 P.O. Box 388 Forked River, NJ 08731 Forked River, NJ 08731 Director - Licensing and Regulatory Affairs Senior Vice President- Operations Support AmerGen Energy Company, LLC AmerGen Energy Company, LLC Correspondence Control 4300 Winfield Road P.O. Box 160 Warrenville, IL 60555 Kennett Square, PA 19348 Ms. Kathryn M. Sutton, Esquire Manager Licensing - Oyster Creek Morgan, Lewis, & Bockius LLP Exelon Generation Company, LLC 1111 Pennsylvania Avenue, NW Correspondence Control Washington, DC 20004 P.O. Box 160 Kennett Square, PA 19348 Mr. Patrick Mulligan, Chief Bureau of Nuclear Engineering Mr, Ron Bellamy, Region I New Jersey Department of U.S. Nuclear Regulatory Commission Environmental Protection 475 Allendale Road 25 Arctic Parkway King of Prussia, PA 19406-1415 Ewing, NJ 08638 Correspondence Control Desk Vice President - Licensing and AmerGen Energy Company, LLC Regulatory Affairs 200 Exelon Way, KSA 1-N-1 AmerGen Energy Company, LLC Kennett Square, PA 19348 4300 Winfield Road Warrenville, IL 60555 Plant Manager Oyster Creek Nuclear Generating Station Regional Administrator, Region I AmerGen Energy Company, LLC U.S. Nuclear Regulatory Commission P.O. Box 388 475 Allendale Road Forked River, NJ 08731 King of Prussia, PA 19406-1415 Associate General Counsel Mayor of Lacey Township Exelon Generation Company, LLC 818 West Lacey Road 4300 Winfield Road Forked River, NJ 08731 Warrenville, IL 60555 Manager Regulatory Assurance Chief Operating Officer (COO)
Oyster Creek Generating Station AmerGen Energy Company, LLC AmerGen Energy Company, LLC 4300 Winfield Road P.O. Box 388 Warrenville, IL 60555 Forked River, NJ 08731
Oyster Creek Nuclear Generating Station cc:
Senior Vice President - Mid-Atlantic Operations AmerGen Energy Company, LLC 200 Exelon Way, KSA 3-N Kennett Square, PA 19348 Mr. Michael P. Gallagher Vice-President, License Renewal Exelon Nuclear 200 Exelon Way Kennett Square, PA 19348 Julie Crocker Fisheries Biologist NMFS Northeast Regional Office 55 Great Republic Drive Gloucester, MA 01930 Malcolm Browne Oyster Creek Nuclear Generating Station Exelon Generation 741 U.S. Route 9 South Forked River, NJ 08731-0388 Samuel Collins, Regional Administrator USNRC, Region 1 475 Allendale Road King of Prussia, PA 09406-1415