Email from M. Sykes to D. Ayres, Subj: Re; Crystal River Support
ML100750391
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 10/09/2009
From: Marvin Sykes
NRC/RGN-II/DRP/RPB3
To: Ayres D
NRC/RGN-II/DCP
References
FOIA/PA-2010-0010
Download: ML100750391 (1)


Text

Ayres, David From:

Sykes, Marvin Sent:

Friday, October 09, 2009 11:28 AM To:

Ayres, David Cc:

Morrissey, Thomas; Reyes, Rogerio

Subject:

RE: Crystal River support

David, At this point, we don't have any reason to delay Brannen's plans to visit CR3. we think it's a great opportunity for him to observe the refueling and generator replacement activities. The licensee is performing several major upgrades to the primary and secondary plant components and I can't recall another outage with this many major mods being implemented.

Marvin From: Morrissey, Thomas Sent: Thursday, October 08, 2009 5:12 PM To: Sykes, Marvin

Subject:

FW: Crystal River support From: Ayres, David Sent: Thursday, October 08, 2009 5:09 PM To: Adkins, Brannen; Reyes, Rogerio Cc: Morrissey, Thomas

Subject:

Re: Crystal River support Would it be better to postpone until this issue is resolved or repairs begin?

This email is being sent from an NRC Blackberry device.

From: Adkins, Brannen To: Reyes, Rogerio Cc: Morrissey, Thomas; Ayres, David Sent: Thu Oct 08 16:53:46 2009

Subject:

Crystal River support Tom/Roger, Given the current situation at Crystal River (discovery of crack in concrete containment), I wanted to make sure that you still want me to provide resident/outage support between 10/19 - 11/13/09.

Thanks, Bpuzrnn Construction Project Inspector Construction Projects Branch 4 Division of Construction Projects U.S. Nuclear Regulatory Commission - Region II 404-562-6340 office

\\

I