Modify11ant Issue Page 1 of2 plant status daily enter daily plant status safety meeting branch chief reports focus items pita search archives information, Crystal River Information for 10/09/2009 (Modify/Update)
Unit 3 status: (no commas, please) jMode 6; GREEN RCS Leak:
9:15 mtg. C Yes ( No Routine Activities I TS Activities:
Significant TS I Issues:
9:15 mtg. C Yes (0 No add attachment Risk Significant / Emergent Activities:
The plant is in mode 6, green risk. The equipment hatch is open. Water temperature is 99F, time to boil at 2064 minutes. Defueling is in progress and is 90% complete. Full core off load completion is scheduled for this afternoon.
An NRC/Licensee conference call was held yesterday to discuss the containment issues and licensee actions. A special inspection is planned to start next week.
9:15mtg.C Yes ( No
- add afttacment Findings and Observations:
9:15mtg. C Yes (0 No Site Visits:
A. Alen onsite for 5 week training rotation.
R. Chou is onsite with his SGR team.
Chairman and Luis Reyes site visit planned for today.
9:15mtg.C Yes 6" No add attachment 1/
http://r2.nrc.gov/webapps/pita/Modifylssue.cfin?iid=15334&sname=Crystal River 10/20/2009
Modify Plant Issue Page 2 of 2 Other:
No significant findigs with chou inspection Site coverage provided by both residents for the weekend.
9:15 mtg.C Yes
- No