MONTHYEARML0928902092009-10-16016 October 2009 Final Safety Evaluation Report, Related to the License Renewal of Prairie Island Nuclear Generating Plant, Units 1 and 2 Project stage: Approval ML1004801032010-02-19019 February 2010 Acceptance of Requested Licensing Action Measurement Uncertainty Recapture Power Uprate Application Project stage: Acceptance Review ML1006208982010-03-0303 March 2010 Draft Requests for Additional Information from Scvb MUR LAR Project stage: Draft RAI ML1006202712010-03-0303 March 2010 Draft RAIs Submitted by Fire Protection Branch (Afpb) for MUR LAR Project stage: Draft RAI ML1006209062010-03-0303 March 2010 Attachment to E-mail Transmitting Draft RAIs from Scvb MUR LAR Project stage: Draft RAI ML1006202642010-03-0303 March 2010 Draft Requests for Additional Information MUR LAR Project stage: Draft RAI ML1006304992010-03-0404 March 2010 Draft Requests for Additional Information (Csgb) MUR LAR Project stage: Draft RAI ML1006404832010-03-0505 March 2010 Attachment to E-Mail Transmitting Draft RAIs from Emcb MUR LAR Project stage: Draft RAI ML1006400072010-03-0505 March 2010 Draft Requests for Additional Information MUR LAR Project stage: Draft RAI ML1006400092010-03-0505 March 2010 Attachment to E-Mail Draft RAIs Submitted by Reactor Systems Branch (Srxb) for MUR LAR Project stage: Draft RAI ML1006305052010-03-0505 March 2010 Attachment to E-mail Transmitting Draft RAI from Csgb MUR LAR (TAC Nos. ME3015 and ME3016.) Project stage: Draft RAI ML1006404632010-03-0505 March 2010 Draft Requests for Additional Information MUR LAR Project stage: Draft RAI ML1006804042010-03-0909 March 2010 Request for Additional Information on Measurement Uncertainty Recapture Power Uprate License Amendment Project stage: RAI ML1006804002010-03-0909 March 2010 Draft Requests for Additional Information (Eicb) MUR LAR Project stage: Draft RAI ML1006903092010-03-10010 March 2010 Attachment to E-Mail Transmitting Draft RAIs from Eeeb MUR Power Uprate LAR Project stage: Draft RAI ML1006903012010-03-10010 March 2010 Draft Requests for Additional Information MUR Power Uprate LAR Project stage: Draft RAI ML1007003732010-03-11011 March 2010 Request for Additional Information on License Amendment Request Dated 12/28/09 for Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML1007003672010-03-11011 March 2010 Draft Request for Additional Information (Cvib) MUR Power Uprate Project stage: Draft RAI ML1007400392010-03-17017 March 2010 Requests for Additional Information Associated with License Amendment Request Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML1006902882010-03-24024 March 2010 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance L-PI-10-034, Annual Report of Personnel Radiation Exposure2010-04-19019 April 2010 Annual Report of Personnel Radiation Exposure Project stage: Request L-PI-10-036, Supplement to License Amendment Request for Measurement Uncertainty Recapture - Power Uprate - Response to Requests for Additional Information2010-04-19019 April 2010 Supplement to License Amendment Request for Measurement Uncertainty Recapture - Power Uprate - Response to Requests for Additional Information Project stage: Supplement L-PI-10-035, Supplement to License Amendment Request for Measurement Uncertainty Recapture - Power Uprate, Withdrawal of Proposed Change to Analysis Methodology for Pressure Temperature Limits Report2010-04-23023 April 2010 Supplement to License Amendment Request for Measurement Uncertainty Recapture - Power Uprate, Withdrawal of Proposed Change to Analysis Methodology for Pressure Temperature Limits Report Project stage: Withdrawal L-PI-10-061, Supplement to License Amendment Request for Measurement Uncertainty Recapture Power Uprate - Additional Information Regarding Main Steam System Stress Analyses and Electrical Output2010-06-17017 June 2010 Supplement to License Amendment Request for Measurement Uncertainty Recapture Power Uprate - Additional Information Regarding Main Steam System Stress Analyses and Electrical Output Project stage: Supplement ML1020305732010-08-18018 August 2010 Amendment Measurement Uncertainty Recapture Power Uprate Project stage: Other L-PI-10-096, Core Operating Limits Report (COLR) for Prairie Island, Unit 1, Cycle 26, Revision 2, and Unit 2, Cycle 26, Revision 22010-10-26026 October 2010 Core Operating Limits Report (COLR) for Prairie Island, Unit 1, Cycle 26, Revision 2, and Unit 2, Cycle 26, Revision 2 Project stage: Other 2010-03-03
[Table View] |
Text
ADAMS Accession No.: ML100620271 REQUESTS FOR ADDITIONAL INFORMATION Prairie Island Nuclear Generating Plant, Units 1 and 2 License Amendment Request (LAR) dated December 28, 2009 for Measurement Uncertainty Recapture Power Uprate Docket Nos. 50-282 and 50-306 TAC Nos. ME3015 and ME3016 Office of Nuclear Reactor Regulation Division of Risk Assessment Fire Protection Branch RAI Fire Protection 1 The staff notes that Enclosure 2 to the LAR,Section II.2.26, 10.3.1 - Plant Fire Protection Program (Appendix R), states that Evaluations conclude that the current safe shutdown analyses use an analytical core power of 1683 MWt (or higher) and, as such, the MUR Power Uprate has no effect on the plant equipment and systems credited with achieving safe shutdown.
Likewise, evaluations also conclude that MUR PU has no impact on Appendix R manual action constraints The staff requests the licensee to verify that the (1) measurement uncertainty recapture (MUR) power uprate will not require any new operator actions, and (2) any effects from additional heat in the plant environment from the increased power will not interfere with existing operator manual actions being performed at their designated time and place.
RAI Fire Protection 2 Some plants credit aspects of their fire protection system for other than fire protection activities, e.g., utilizing the fire water pumps and water supply as backup cooling or inventory for non-primary reactor systems.
If the Prairie Island Nuclear Generating Plant (PINGP), Units 1 and 2, credits its fire protection system for other than fire protection activities, the MUR LAR should identify the specific situations and discuss to what extent, if any, the MUR power uprate affects these non-fire-protection aspects of the plant fire protection system.
If the PINGP, Units 1 and 2, do not take such credit, the staff requests that the licensee verify this as well.