John Carlin Site Vice President R.E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, New York 14519-9364 585.771.5200 585.771.3943 Fax John.Carlin@cenglic.com CENG
- a joint venture of 0Constellation EmeWrgeD December 14, 2009 U. S. Nuclear Regulatory Commission Washington, DC 20555 - 0001 ATTENTION:
SUBJECT:
Document Control Desk R.E. Ginna Nuclear Power Plant Docket No. 50-244 Correction to Reply to Request for Additional Information RE: Revisions to Loss-of-Power Diesel Generator Start Instrumentation Limiting Safety System Settings and Diesel Generator Load Test Value
REFERENCES:
(a) Letter from Mr. J. T. Carlin (Ginna LLC) to Document Control Desk (NRC) dated November 23, 2009, Reply to Request for Additional Information RE:
Revisions to Loss-of-Power Diesel Generator Start Instrumentation Limiting Safety System Settings and Diesel Generator Load Test Value On November 23, 2009, R.E. Ginna Nuclear Power Plant, LLC submitted a Reply to Request for Additional Information, Reference (a). Subsequently, it was identified that page 2 of Attachment 1 was missing from the response. Attached is the missing page.
No new commitments are being made in this submittal. Should you have questions regarding the information in this submittal, please contact Mr. Thomas Harding at (585) 771-5219 or via email at Thomas.HardingJr(acenallc.com.
AoC(
14j pLNjZC -- O) 0 ýQL
Document Control Desk December 14, 2009 Page 2 STATE OF NEW YORK
- TO WIT:
COUNTY OF WAYNE I, John Carlin, being duly sworn, state that I am Vice President, R.E. Ginna Nuclear Power Plant, LLC (Ginna LLC), and that I am duly authorized to execute and file this request on behalf of Ginna LLC. To the best of my knowledge and belief, the statements contained in this document are true and correct. To the extent that these statements are not based on my personal knowledge, they are based upon information provided by other Ginna LLC employees and/or consultants. Such information has been reviewed in accordance with company practice and I believe it to be reliable.
I,/
Subscribed and sworn before me, a Notary Public in and for the State of New York and County of Ao0i (t0 L.,
this J+/-E day of L).f(.-)1ktL, 2009.
WITNESS my Hand and Notarial Seal:
My Commission Expires:
Date Notary Public-,--
SHARON L.MILLER Notary Publc, State of New York Registrati6h No,01M160 17755 MonhroeCounty Commission Expires Deýember1l, 20 /
-C-.2r
".° : Response to Request for Additional Information Missing Page cc:
S. J. Collins, NRC D. V. Pickett, NRC Ginna Resident Inspector, NRC P. D. Eddy, NYSDPS A. L. Peterson, NYSERDA
ATTACHMENT 1 Response to Request for Additional Information Missing Page R.E. Ginna Nuclear Power Plant, LLC December 14, 2009
Attachment I Response to Request for Additional Information Regarding Revisions to Loss-of-Power Diesel Generator Start Instrumentation Limiting Safety System Settings and Diesel Generator Load Test Value is initiated with subsequent closing of the diesel generator supply breaker(s) to the bus(es) that experienced the UV. Component cooling water pumps are tripped if a safety injection signal is present and safeguards loads are sequenced on.
When being fed from the onsite diesel generators, actuation of the bus UV system strips all bus loads, except containment spray, MCC C and D and required downstream MCCs and component cooing water breakers on buses 14 and 16. The diesel generator supply breakers to its respective safeguards buses are not tripped. If a safety injection signal is present then safeguards loads will be re-sequenced onto their respective bus once voltage recovers above the UV relay reset values, component cooling water pumps will not be in-service. If a safety injection signal is not present then loads are started upon bus voltage recovery, as required.
R.E. Ginna Nuclear Power Plant, LLC November 23, 2009 Page 2