Review of the 2008 Steam Generator Tube Inservice Inspections
ML093500669
Person / Time
Site: Millstone Dominion icon.png
Issue date: 12/22/2009
From: Sanders C
Plant Licensing Branch 1
To: Heacock D
Dominion Nuclear Connecticut
Sandeers, Carleen, NRR/DORL, 415-1603
References
TAC ME0942, FOIA/PA-2011-0115
Download: ML093500669 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 22, 2009 Mr. David A. Heacock President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.

Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

MILLSTONE POWER STATION, UNIT NO.3 - REVIEW OF THE 2008 STEAM GENERATOR TUBE INSERVICE INSPECTION REPORT (TAC NO. ME0942)

Dear Mr. Heacock:

By letter dated March 13, 2009, as supplemented by letter dated November 23, 2009 (Agencywide Documents Access and Management System (ADAMS) Accession Nos.

ML090850344 and ML093350528, respectively), Dominion Nuclear Connecticut, Inc. (DNC or the licensee), submitted information summarizing the results of the 2008 steam generator tube inspections at Millstone Power Station, Unit NO.3 (MPS3). These inspections were performed during the twelfth refueling outage. Additional details of these inspections are documented in a conference call summary dated December 12, 2008 (ADAMS Accession No. ML083370136).

The Nuclear Regulatory Commission (NRC) staff has completed its review of the information provided and concludes that DNC provided the information required by the MPS3 technical specifications and that no additional follow-up is required. The NRC's review is enclosed.

If you have any questions, please contact me at 301-415-1603.

I i/n/. f-reIY,

/1

/

I Carleen J. an ers, Project Manager Plant Lice sin Branch 1-2 Division of rating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-423

Enclosure:

As stated cc wi encl: Distribution via Listserv

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 REVIEW OF THE 2008 STEAM GENERATOR TUBE INSERVICE INSPECTION REPORT MILLSTONE POWER STATION, UNIT NO.3 DOCKET NUMBER 50-423 By letter dated March 13, 2009, as supplemented by letter dated November 23, 2009 (Agencywide Documents Access and Management System (ADAMS) Accession Nos.

ML090850344 and ML093350528, respectively), Dominion Nuclear Connecticut, Inc. (DNC or the licensee), submitted information summarizing the results of the 2008 steam generator (SG) tube inspections at Millstone Power Station, Unit NO.3 (MPS3). These inspections were performed during the twelfth refueling outage (3R12). Additional details of these inspections are documented in a conference call summary dated December 12, 2008 (ADAMS Accession No. ML083370136).

MPS3 has four Westinghouse Model F SGs, each of which contains 5,626 thermally-treated Alloy 600 tubes. Each tube has a nominal outside diameter of 0.688 inches and a nominal wall thickness of 0.040 inches. During SG fabrication, the tubes were hydraulically expanded at both ends, over the full depth of the 21.23-inch thick tubesheet. The tubesheet was drilled on a square pitch with 0.98-inch spacing. There are 59 rows and 122 columns in each SG. The radius of the row 1 U-bends is 2.20 inches. The U-bends in Rows 1 through 10 were stress relieved after bending. Eight Type 405 stainless steel support plates, which have broached quatrefoil holes, support the vertical section of the tubes, and six anti-vibration bars support the U-bend section of the tubes.

As of the end of Cycle 12 (October 2008), the SGs had approximately 16.6 effective full-power years of operation. A 7% power uprate was implemented for Cycle 13.

DNC provided the scope, extent, methods, and results of their SG tube inspections in the documents referenced above. In addition, DNC described corrective actions (i.e., tube plugging) taken in response to the inspection findings.

After review of the information provided by the licensee, the NRC staff has the following comments/observations:

  • Tube end cracking indications were detected on the hot-leg side of all four SGs and on the cold-leg side of SG D. Axial and circumferential indications were reported in the tube end examination.
  • J-Tubes 1, 15, 16, and 30 in all four SGs have shown signs of flow-accelerated corrosion (FAC) at the interface between the nozzle weld and the header interface, on the inside diameter of the header. The FAC at these locations was previously repaired via the weld overlay process in all four SGs. During 3R12, the upper bundle region of SG B was inspected, including the J-tubes and weld overlay repair locations. No new signs of FAC Enclosure

-2 were identified and the weld overlays were intact with no degradation. Some minor surface rust was observed on the upper internals, which are fabricated from carbon steel.

Based on a review of the information provided by DNC, the NRC staff concludes that DNC provided the information required by the MPS3 technical specifications. The SG tube inspections at MPS3 appear to be consistent with the objective of detecting potential tube degradation and the inspection results appear to be consistent with industry operating experience at similarly designed and operated units.

Principal Contributor: 1. Morgan Date: December 22, 2009

December 22, 2009 Mr. David A. Heacock President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.

Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

MILLSTONE POWER STATION, UNIT NO.3 - REVIEW OF THE 2008 STEAM GENERATOR TUBE INSERVICE INSPECTIONS (TAC NO. ME0942)

Dear Mr. Heacock:

By letter dated March 13, 2009, as supplemented by letter dated November 23, 2009 (Agencywide Documents Access and Management System (ADAMS) Accession Nos.

ML090850344 and ML093350528, respectively), Dominion Nuclear Connecticut, Inc. (DNC or the licensee), submitted information summarizing the results of the 2008 steam generator tube inspections at Millstone Power Station, Unit NO.3 (MPS3). These inspections were performed during the twelfth refueling outage. Additional details of these inspections are documented in a conference call summary dated December 12, 2008 (ADAMS Accession No. ML083370136).

The Nuclear Regulatory Commission (NRC) staff has completed its review of the information provided and concludes that DNC provided the information required by the MPS3 technical specifications and that no additional follow-up is required. The NRC's review is enclosed.

If you have any questions, please contact me at 301-415-1603.

Sincerely,

/raJ Carleen J. Sanders, Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-423

Enclosure:

As stated cc wI encl: Distribution via Listserv Distribution:

PUBLIC Branch Reading RidsAcrsAcnw_MailCTR Resource RidsNrrDorlLpl1-2 Resource RidsNrrDciCsgbResource RidsNrrLAABaxter Resource RidsNrrPMMilistone Resource RidsOgcRp Resource RidsRgn1 MailCenter Resource LTrocine, EDO R-1 KKarwoski, NRR TMorgan, NRR ADAMS Accession N0.: ML093500669

  • Bsy Memo Dated LPL1-2/BC HChernoff OFFICE LPL1-2/PM LPL1-2/LA DCI/CSGB NAME CSanders ABaxter RTavlor*

DATE 12/22/09 12/22/09 12/10/2009 12/22/09 OFFICAL RECORD COpy