Summary of Meeting to Discuss Issues Related to a Future Application for Amendment Using Mellla+ Methodology
ML093451619
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 12/22/2009
From: Tam P
Plant Licensing Branch III
To:
Tam P
References
TAC ME2449
Download: ML093451619 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 22, 2009 LICENSEE:

Northern States Power Company FACILITY:

Monticello Nuclear Generating Plant SUB"IECT:

SUMMARY

OF THE DECEMBER 15, 2009, MEETING TO DISCUSS ISSUES RELATED TO A FUTURE APPLICATION FOR AMENDMENT USING MELLLA+

(TAC NO. ME2449)

On December 15, 2009, the Nuclear Regulatory Commission (NRC) staff held a Category 1 public meeting with representatives of Northern States Power Company at the office of Excel Services, 11921 Rockville Pike, Rockville, Maryland. The purpose of the meeting was for the licensee to discuss issues related to a future application for amendment using the Maximum Extended Load Line Limit Analysis Plus (MELLLA+) methodology. The Enclosure to this summary contains the list of participants.

The licensee's presentation followed the licensee's handout material (docketed at Agencywide Documents Access and Management System Accession No. ML093490876). As shown in the handout material, the licensee plans to submit the application for the amendment in January 2010, and would request that the amendment be issued in 12 months. NRC staff participants did not voice any concern about the requested turnaround time, but cautioned the licensee that the Advisory Committee for Reactor Safeguards had previously indicated interest in reviewing amendments using MELLLA+ methodology, and such review could potentially introduce some uncertainty to the turnaround time.

Members of the public were in attendance. No portion of this meeting was closed to the public because no proprietary information was used by the participants. Before the meeting adjourned, members of the public were given the opportunity to communicate with the NRC staff both verbally and through the use of public meeting feedback forms. No comment or feedback was received.

Please direct any inquiries to the undersigned (Tel. 301-41~'-e:7ail peter.tam@nrc.gov).

~

..C::: J/'

(1~/~

Peter S. Tam, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-263

Enclosure:

List of attendees cc w/encl: Distribution via ListServ

LIST OF ATTENDEES MEETING BETWEEN NUCLEAR REGULATORY COMMISSION (NRC) AND XCEL ENERGY MONTICELLO NUCLEAR GENERATING PLANT FUTURE AMENDMENT USING MELLLA+ METHODOLOGY NAME Doug Blair Greg Cranston Michael Edwards Lynne Gunderson Steve Hammer Bruce Hagemeier Ralph Hayes TaiHuang Randy Jacobs Charles Lamb Benjamin Parks Robert Pascarelli Ed Schrull Lisa Schichlien Peter Tam Mike Taylor Juswald Vedovi AI Williams Peter Yarsky December 15, 2009 ORGANIZATION Xcel Energy NRC/NRRlSRXB* (Branch Chief)

Fort Calhoun Station Xcel Energy Xcel Energy GEH Xcel Energy NRC/NRR/SRXB*

GEH GEH NRC/NRRlSRXB*

NRC/NRRlPlant Licensing Branch 111-1 (Branch Chief)

GEH GEH NRC/NRRlPlant Licensing Branch 111-1 GEH GEH Xcel Energy NRC/NRR/SNPB**

The following participated by telephone:

Bob Dulee Fort Calhoun Station Terry Cribbe Fort Calhoun Station Carmen Ovici Fort Calhoun Station

  • Office of Nuclear Reactor Regulation/Reactor Systems Branch
    • Office of Nuclear Reactor Regulation/Nuclear Performance and Code Review Branch ENCLOSURE

December 22,2009 LICENSEE:

Northern States Power Company FACILITY:

Monticello Nuclear Generating Plant

SUBJECT:

SUMMARY

OF THE DECEMBER 15, 2009, MEETING TO DISCUSS ISSUES RELATED TO A FUTURE APPLICATION FOR AMENDMENT USING MELLLA+

(TAC NO. ME2449)

On December 15, 2009, the Nuclear Regulatory Commission (NRC) staff held a Category 1 public meeting with representatives of Northern States Power Company at the office of Excel Services, 11921 Rockville Pike, Rockville, Maryland. The purpose of the meeting was for the licensee to discuss issues related to a future application for amendment using the Maximum Extended Load Line Limit Analysis Plus (MELLLA+) methodology. The Enclosure to this summary contains the list of participants.

The licensee's presentation followed the licensee's handout material (docketed at Agencywide Documents Access and Management System Accession No. ML093490876). As shown in the handout material, the licensee plans to submit the application for the amendment in January 2010, and would request that the amendment be issued in 12 months. NRC staff participants did not voice any concern about the requested turnaround time, but cautioned the licensee that the Advisory Committee for Reactor Safeguards had previously indicated interest in reviewing amendments using IVIELLLA+ methodology, and such review could potentially introduce some uncertainty to the turnaround time.

Members of the public were in attendance. No portion of this meeting was closed to the public because no proprietary information was used by the participants. Before the meeting adjourned, members of the public were given the opportunity to communicate with the NRC staff both verbally and through the use of public meeting feedback forms. No comment or feedback was received.

Please direct any inquiries to the undersigned (Tel. 301-415-1451, e-mail peter.tam@nrc.gov).

/raj Peter S. Tam, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-263

Enclosure:

List of attendees cc wtencl: Distribution via ListServ DISTRIBUTION: PUBLIC LPL3-1 RtF RidsAcrsAcnw_MailCTR Resource RidsNrrDorlLpl3-1 Resource RidsNrrPMDWright Resource RidsNrrPMPTam Resource RidsNrrLATHarris Resource RidsOgcRp Resource RidsRgn3MailCenter Resource TBloomer, EDO GCranston, NRR THuang, NRR BParks, I\\IRR RPascarelli, NRR PYarsky, NRR Package: ML093451640 Meeting Summary Accession No.: ML093451619 M

N' A N

ML093230204 L'

H d

A N

MLO 34908 6 eetinq otice ccesston 0.:

icensee's an out ccession 0.:

9 7

OFFICE NRR/LPL3-1/PM NRR/LPL3-1/LA NRR/SRXB/BC NRR/SNPB/BC NRR/LPL3-1/BC RPascarelli 12/22/2009 NAME PTam THarris GCranston (TNakanishi for)

AMendiola 12/18/

DATE 12/18/09 12/18/09 12/18/09 OFFICIAL RECORD COpy