Summary of Meeting with Entergy Operations, Inc. to Discuss Plans to Evaluate Steam Dryers for Grand Gulf Nuclear Station, Unit 1s Future Extended Power Uprate
ML093210329
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 11/18/2009
From: Lyon C
Plant Licensing Branch IV
To:
Entergy Operations
Lyon C Fred, NRR/DORL/LPL4, 301-415-2296
References
TAC ME2423
Download: ML093210329 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 18, 2009 LICENSEE:

Entergy Operations, Inc.

FACILITIES: Grand Gulf Nuclear Station, Unit 1 SUB-JECr:

SUMMARY

OF MEETING ON NOVEMBER 12, 2009, TO DISCUSS THE LICENSEE'S ANALYSIS METHODOLOGY FOR STEAM DRYERS FOR A PROPOSED POWER UPRATE APPLICATION (TAC NO. ME2423)

On November 12, 2009, members of the U.S. Nuclear Regulatory Commission (NRC) staff met with representatives from Entergy Operations, Inc. (Entergy, the licensee), at NRC Headquarters, Two White Flint North, 11545 Rockville Pike, Rockville, MD. The licensee was accompanied by representatives from its contractors, General Electric - Hitachi Nuclear Energy (GEH) and Lucius Pitkin, Inc. The meeting was a Category 1 public meeting. Portions of the meeting were closed due to the proprietary nature of the information that was discussed.

The meeting was requested by the licensee to discuss its use of the GEH plant based load evaluation methodology to analyze the steam dryers as part of a proposed extended power uprate (EPU) application for Grand Gulf Nuclear Station, Unit 1 (GGNS). The licensee currently intends to submit its application in July 2010.

The licensee presented a status of its steam dryer analysis and how the analysis may be integrated into the EPU application. The licensee then described the GEH methodology and the bias, uncertainties, and margins used in the steam dryer evaluation.

The NRC staff provided comments for consideration by the licensee in the preparation of its application.

- 2 No regulatory decisions were made at the meeting. The meeting agenda was provided with the meeting notice (Agencywide Documents Access and Management System (ADAMS) Accession No. ML092920427). The licensee's presentation slides have been placed in ADAMS (ADAMS Accession No. ML093080687, proprietary version; ML093210200, public version). A list of attendees is enclosed.

Carl F. Lyon, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-416

Enclosure:

Attendance List cc w/encl: Distribution via Listserv

ATTENDANCE LIST NRC MEETING WITH ENTERGY OPERATIONS. INC.

PROPOSED ANALYSIS METHODOLOGY FOR STEAM DRYERS GRAND GULF NUCLEAR STATION, UNIT 1.

NOVEMBER 12. 2009 J. Burford, Entergy F. Lyon, NRR M. Krupa. Entergy N. DiFrancesco, NRR P. Bruck, Lucius Pitkin, Inc.

W. Jessup. NRR B. Newell, Entergy S. Philpott. NRR H. Goodman, Entergy C. Basavaraju, NRR A. Alford, Entergy M. Khanna, NRR P. Campbell, GEH A. Russell, NRR C. Brinkman, Westinghouse S. Verrochi, Entergy E. Betti, GEH M. James, GEH Enclosure

Meeting Notice ML092920427, Meeting Summary ML093210329 Licensee Slides ML093210200 OFFICE NRR/LPL4/PM NRR/LPL4/LA NRR/LP4/BC NRR/LPL4/PM NAME FLyon JBurkhardt MMarkley JRHall for FLyon DATE 11/18/09 11/18/09 11/18/09 11/18/09