ML092920427

From kanterella
Jump to navigation Jump to search

Notice of Forthcoming Pre-Application Meeting with Entergy Operations, Inc. to Discuss Plans to Evaluate Steam Dryers for Grand Gulf Nuclear Station, Unit 1s Future Extended Power Uprate Request
ML092920427
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 10/21/2009
From: Lyon C
Plant Licensing Branch IV
To: Markley M
Plant Licensing Branch IV
Lyon C Fred, NRR/DORL/LPL4, 301-415-2296
References
Download: ML092920427 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 21, 2009 MEMORANDUM TO: Michael T. Markley, Branch Chief Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation FROM:

Carl F. Lyon, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

SUBJECT:

FORTHCOMING MEETING WITH ENTERGY OPERATIONS, INC.,

GRAND GULF NUCLEAR STATION, UNIT 1 DATE & TIME:

Thursday, November 12, 2009 1:00 p.m. - 4:00 p.m.

LOCATION:

U.S. Nuclear Regulatory Commission Two White Flint North 11545 Rockville Pike, Room T-7A1 Rockville, Maryland PURPOSE:

The purpose of this pre-application meeting is to discuss Entergy Operations, Inc. (Entergy), plans to evaluate the steam dryers for Grand Gulf Nuclear Station, Unit 1 (GGNS) for Entergy's future Extended Power Uprate (EPU) request.

CATEGORY 1*:

This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.

Certain portions of this meeting will be closed to the public because the staff has determined that the information is proprietary in nature.

PARTICIPANTS:

Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR). Participants from Entergy include those from General Electric - Hitachi (GEH).

NRC Entergy F. Lyon C. Basavaraju J. Burford B. Newall M. Khanna A. Russell H. Goodman A. Alford M. Markley et al.

S. Verrochi et al.

T. Alexion MEETING CONTACT:

Fred Lyon, NRR 301-415-2296 Fred.Lyon@nrc.gov

  • Commission's Policy Statement on "Enhancing Public Participation in NRC Meetings" (67 FR 36920), May 28, 2002.

M. Markley

- 2 The NRC provides reasonable accommodation to individuals with disabilities where appropriate. If you need a reasonable accommodation to participate in a meeting, or need a meeting notice or a transcript or other information from a meeting in another format (e.g., Braille, large print), please notify the NRC's meeting contact. Determinations on requests for reasonable accommodation will be made on a case-by-case basis.

To receive a summary of this meeting and begin receiving other plant-specific e-mail distributions, you must subscribe to the Operating Reactor Correspondence electronic distribution for this plant via http://www.nrc.gov/public-involve/listserver/plants-by-region.html.

Once subscribed, if you wish to discontinue receiving electronic distribution, you may unsubscribe at any time by visiting the same web address above.

Docket No. 50-416

Enclosure:

Agenda cc w/encl: Distribution via Listserv

MEETING AGENDA ENTERGY OPERATIONS, INC.

GRAND GULF NUCLEAR STATION, UNIT 1 PRE-APPLICATION MEETING Thursday, November 12, 2009 1:00 p.m. to 4:00 p.m.

1.

Introductions

2.

Overview of GGNS EPU project

3.

Current status of GGNS steam dryer evaluation

4.

Overview of the GEH plant-based load evaluation methodology

5.

Summary / Adjournment Parts 1, 2, and 3 are estimated to take a total of about 45 minutes and are non-proprietary. Part 4 is estimated to take about 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> and is proprietary.

Enclosure

ML092920427 OFFICE DORLlLPL4/PM DORLlLPL4/LA DORLlLPL4/BC DORLlLPL4/PM NAME FLyon JBurkhardt MMarkley FLyon NDiFrancesco for DATE 10/20/09 10/20/09 10/21/09 10/21/09