MONTHYEARML22005A0862022-01-0404 January 2022 1-4-2022 Email Communication to Duane Arnold Regarding Its ISFSI Related Exemption Request on Supplemental Information Needed ML21335A0712021-12-0101 December 2021 Request for Additional Information - Duane Arnold Energy Center ISFSI Only Emergency Plan ML21335A0702021-12-0101 December 2021 Cover Letter to B. Coffey from K. Conway - Duane Arnold Energy Center RAI Re License Amendment Request for ISFSI Only Emergency Plan ML21250A3002021-09-0808 September 2021 Defueled Physical Security Plan RAI Cover Letter ML21006A4052021-01-0606 January 2021 NRR E-mail Capture - Final RAI - Duane Arnold - Post-Shutdown Decommissioning Activities Report ML20316A0212020-11-10010 November 2020 NRR E-mail Capture - Final RAI - Duane Arnold - Duane Arnold Amendment for Proposed Defueled EP and EAL Scheme ML20153A3772020-05-28028 May 2020 NRR E-mail Capture - Request for Additional Information - Duane Arnold Energy Center Quality Assurance Topical Report (FPL-3) - EPID L-2020-LLQ-0002) ML20141L8132020-05-19019 May 2020 NRR E-mail Capture - Request for Additional Information - Duane Arnold Energy Center (DAEC) - Exemption Request for Security Training Requirements Due to COVID-19 Pandemic - EPID L-2020-LLE-0042 to 45, L-2020-LLE-0051 ML20133K0482020-05-14014 May 2020 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML20127H8662020-05-0505 May 2020 NRR E-mail Capture - Duane Arnold Energy Center (DAEC) - Request for Additional Information (RAI) - Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 1O CFR 50.75(h)(1)(iv) - EPID L-2020-LLE-0011 ML19280A0352019-10-0404 October 2019 NRR E-mail Capture - Final - RAI Related to License Amendment Request (TSCR-182) for Proposed Changes to the Emergency Plan for Permanently Defueled Conditions at Duane Arnold Energy Center (DAEC) - L-2019-LLA-0075 ML18283B0522018-10-0909 October 2018 NRR E-mail Capture - Final Second Round - Request for Additional Information (RAI) - Duane Arnold Energy Center (DAEC) - LAR TSCR-166, Adoption of EAL Scheme Pursuant to NEI 99-01 - EPID L-2017-LLA-0420 ML18255A2922018-09-11011 September 2018 NRR E-mail Capture - Draft Second Round - Request for Additional Information (RAI) - Duane Arnold Energy Center (DAEC) - LAR TSCR-166, Adoption of EAL Scheme Pursuant to NEI 99-01 - EPID L-2017-LLA-0420 ML18247A2002018-08-21021 August 2018 E-Mailed Request for Information for Duane Arnold, Dated 08/21/18 (DRS-M.Holmberg) ML18166A2982018-06-15015 June 2018 NRR E-mail Capture - Draft Request for Additional Information (RAI) - Duane Arnold Energy Center (DAEC) - LAR TSCR-166, Adoption of EAL Scheme Pursuant to NEI 99-01 - EPID L-2017-LLA-0420 ML18088A0102018-03-28028 March 2018 NRR E-mail Capture - Final RAI for Duane Arnold (DAEC) 5th-10 Year ISI (RR-05) ML18058A0522018-02-27027 February 2018 Enclosurequest for Additional Information (Letter: RAI Regarding Florida Power and Light/Nextera Decommissioning Funding Plan Updates for St. Lucie, Units 1 & 2; Seabrook Station; Duane Arnold Energy Center; and Point Beach, Units 1 and 2) ML18037B0032018-02-0606 February 2018 NRR E-mail Capture - Draft Request for Additional Information - Duane Arnold Energy Center (DAEC) - License Amendment Request (TSCR-170), Revision to Technical Specification 3.5.1, ECCS-Operating - EPID L-2017-LLA-0288 ML17347A8752017-12-12012 December 2017 NRR E-mail Capture - Second Round of Request for Additional Information - Duane Arnold Energy Center (DAEC) - LAR to Adopt TST-542, Revision 2, Reactor Pressure Vessel Water Inventory Control - CAC No. MF9829 ML17277A3652017-10-0404 October 2017 NRR E-mail Capture - Final Request for Additional Information - Duane Arnold - Application to Revise Technical Specifications to Adopt TSTF-542, Revision 2, Reactor Pressure Vessel Water Inventory Control - CAC No. MF9829 ML17240A0082017-08-25025 August 2017 NRR E-mail Capture - Request for Additional Information - Duane Arnold Energy Center (DAEC) - Fifth Ten Year Service Inspection Interval - Relief Request No. RR-04, Rev. 0 - Proposed Alternative for Seal Weld Procedure Qualification - MF937 ML17220A3332017-08-0808 August 2017 NRR E-mail Capture - Request for Additional Information - Duane Arnold Energy Center - Relief Request No. RR-03 - Alternative Requirements for Nozzle Inner Radius and Nozzle-To-Shell Welds - CAC No. MF9374 ML17159A7962017-06-0707 June 2017 17 Duane Arnold Energy Center - Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML17068A0632017-03-0808 March 2017 NRR E-mail Capture - Final - Request for Additional Information (RAI) - Duane Arnold Energy Center (DAEC) - Revision to Staff Augmentation Times in the Duane Arnold Energy Center (DAEC) Emergency Plan (Eplan) - MF8390 ML16333A4622016-11-28028 November 2016 NRR E-mail Capture - Final Request for Additional Information - Duane Arnold Energy Center - LAR - SFP Criticality - MF7486 ML16326A0092016-11-18018 November 2016 NRR E-mail Capture - Request for Additional Information Re. Nextera/Fpl LAR to Adopt TSTF-545 - CACs MF8203, MF8204, MF8208, and MF8209 ML16313A0742016-11-0808 November 2016 NextEra Audit Plan Nov 2016 (DAEC SFP Criticality LAR) ML16075A0032016-03-14014 March 2016 NRR E-mail Capture - Request for Additional Information - Duane Arnold Energy Center - LAR to Reduce the Reactor Steam Dome Pressure Specified in the Technical Specifications 2.1.1, Reactor Core Safety Limits - MF6618 ML16074A3142016-03-14014 March 2016 NRR E-mail Capture - Second Round RAIs - Duane Arnold Energy Center - LAR (TSCR-143) to Extend Containment Leakage Test Frequency - MF6619 ML16022A0092016-01-21021 January 2016 NRR E-mail Capture - Request for Additional Information - LAR to Revise and Relocate Pressure and Temperature Limit Curves to a Pressure and Temperature Limits Report - MF6617 ML16021A0122016-01-21021 January 2016 Request for Additional Information by the Containment & Ventilation Branch and PRA Licensing Branch License Amendment Request - Extension of the 10 CFR 50 Appendix J Containment Type a & Type C Test Intervals ML16014A6962016-01-0707 January 2016 E-Mail: Duane Arnold, MOD/50.59 Inspection Request for Information (Jsp) ML16005A6082015-12-24024 December 2015 E-Mail: Duane Arnold Request for Information; December 24, 2015 (AAS) ML15175A0652015-06-23023 June 2015 Ltr. 06/23/15 Duane Arnold Energy Center - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information Inspection Report 05000331/2015003 (Axd) ML14057A7562014-02-25025 February 2014 14 Duane Arnold CDBI Request for Information ML14031A1462014-01-29029 January 2014 Update to NextEra Energy Duane Arnold, Llc'S Response to NRC Request for Additional Information Associated with Near-Term Task Force Recommendations ML13323B4432013-11-26026 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation ML13255A1982013-09-16016 September 2013 Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) ML13175A3932013-06-27027 June 2013 Request for Additional Information for Review Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805 ML13154A5112013-06-0404 June 2013 Rai'S Following Ifib Analysis of NextEra Energy'S 2013 Decommissioning Funding Status Reports for Duane Arnold Energy Center and Point Beach Units 1 and 2 ML12107A0592012-04-11011 April 2012 NRR E-mail Capture - ME7246 - DAEC - Request for Additional Information (RAI) Relief Requests NDR-R003, R010, R011, R014, R015 ML12056A0502012-03-12012 March 2012 Enclosure 4 - Recommendation 2.3: Flooding ML12056A0482012-03-12012 March 2012 Enclosure 2 - Recommendation 2.1: Flooding ML12056A0472012-03-12012 March 2012 Enclosure 1 - Recommendation 2.1: Seismic ML12056A0492012-03-12012 March 2012 Enclosure 3 - Recommendation 2.3: Seismic ML12056A0512012-03-12012 March 2012 Enclosure 5 - Recommendation 9.3: Emergency Preparedness ML1201203182012-01-17017 January 2012 Request for Additional Information Amendment to Change Emergency Action Levels ML12011A0602012-01-0404 January 2012 NRR E-mail Capture - ME6508 - DAEC - Emergency Action Level (EAL) Changes ML1132105812011-11-28028 November 2011 Request for Additional Information Regarding 60-Day Response to Bulletin 2011-01, Mitigating Strategies. ML11147A1142011-06-0808 June 2011 Request for Additional Information Regarding License Amendment Request for Approval of Cyber Security Plan 2022-01-04
[Table view] |
Text
REQUEST FOR ADDITIONAL INFORMATION TO SUPPORT THE REVIEW OF THE DUANE ARNOLD ENERGY CENTER SPENT FUEL MANAGEMENT PROGRAM AND PRELIMINARY DECOMMISSIONING COST ESTIMATE DOCKET NO. 50-331 In reviewing Florida Power and Light (FPL) Energys submittal dated February 19, 2009, (NG-09-0038) which addressed FPL Energys Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Program for the Duane Arnold Energy Center (DAEC) in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Sections 50.75(f)(3) and 50.54(bb), the Nuclear Regulatory Commission (NRC) staff has determined the following information is needed to complete their review.
Irradiated Fuel Management Program RAI No. 1: Financial Assurance In order for a licensee to assume an earnings credit on its decommissioning funds over a DECON or SAFESTOR period that is greater than a 2 percent real rate of return, the licensee must be able to recover total decommissioning costs through rates set by itself or a regulatory authority, 10 CFR 50.75(e)(ii)(A). Such rates must be subject to adjustment upwards during the SAFESTOR period following the permanent shutdown of the plant if the actual rate of growth of the decommissioning funds does not meet or exceed the approved higher real earnings rate.
Please provide a statement and supporting references or documents that demonstrate DAECs will be able to receive upward adjustments from ratepayers to its decommissioning funds, if necessary, following permanent shutdown. FPL stated that the Corn Belt Power Cooperative (CBPC) is a 10% owner and Central Iowa Cooperative (CIPCO) is a 20% owner and both have exempt status under IRS ruling. CIPCO and CBPC both claim a higher rate of return although both CIPC and CBPC rates are not authorized by any state or federal agency but are adjusted annually by their Board of Directors. DAEC needs to provide the documented basis, as identified above, to claim a higher real rate of return (RRR) greater than 2 percent as well as recognizing that the remaining 70 percent ownership would be subject to the 2 percent RRR.
RAI No. 2: Duane Arnold Energy Center Annual Costs The staff requests that DAEC provide a break down of the estimated $4.1 million annual cost and identify the supporting activities that support spent fuel management for DECON option identified for the period 2026 - 2052, and the $5.3 million annual cost for a similar period for SAFESTOR.
ENCLOSURE
RAI No. 3: Section 3. Cost Considerations This submittal indicated that DAEC has an existing independent spent fuel storage installation (ISFSI) with sufficient capacity to accommodate the spent fuel in the reactor building pool at shutdown. What is storage capacity of the ISFSI? At the time of shutdown, how many modules will be stored on the ISFSI? How many additional multipurpose canisters will be loaded with fuel from the pool at the time of shutdown?
RAI No. 4: Cost Estimate and Funding for Spent Fuel Management based on DECON Methodology In the submittal, FPL estimated the cost for spent fuel cooling and transfer of the fuel to dry storage is approximately $129.7 million over approximately 5 years, and identified several supporting activities. For each identified activity, provide a cost breakout associated with each activity.
Preliminary Decommissioning Cost Estimate RAI No. 5: Section 1.0 Executive Summary In the submittal, FPL identified 4 possible decommissioning scenarios for DAEC, and provided the total cost for each option, including spent fuel costs and greenfield costs. Later in the cost study, FPL identified its annual costs associated with each option. However, FPL did not provide an analysis using the decommissioning funds to demonstrate that adequate funds are available to address these options. FPL needs to provide the supporting analysis for each of the identified alternatives or, at a minimum, for the selected option based on the trust fund balance as of December 31, 2008.
RAI No. 6: Section 2.1 Study Objective The submittal focuses on DECON as the preferred option for decommissioning, and Section 2.1 provided detailed discussions on the preferred DECON option as well as 3 other options. The Irradiated Fuel Management Program submittal uses the DECON option as the mechanism for addressing the radiological and spent fuel management costs. FPL needs to confirm which option is the preferred decommissioning option.
RAI No. 7: Section 3.4 Site Specific Considerations The submittal did not address why the site specific cost estimate was lower than the minimum amount established by 10 CFR 50.75(a)(1) and since it was lower, the analysis must be based on the higher amount. Since the site specific cost estimate is lower than the formula amount, FPL needs to address, in detail, why the site specific cost is less than the formula amount.