Offsite Planning Deficiency Identified During the October 6, 2009 Oyster Creek Nuclear Generating Station Emergency Preparedness Exercise
ML093070475
Person / Time
Site: Oyster Creek
Issue date: 11/03/2009
From: James Trapp
Plant Support Branch 1
To: Pardee C
Exelon Generation Co, Exelon Nuclear
References
Download: ML093070475 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION}

475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406-1415 November 3, 2009 Mr. Charles G. Pardee Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

OFFSITE PLANNING DEFICIENCY IDENTIFIED DURING THE OCTOBER 6, 2009 OYSTER'CREEK NUCLEAR GENERATING STATION EMERGENCY PREPAREDNESS EXERCISE

Dear Mr. Pardee:

Enclosed is a copy of a letter from the Federal Emergency Management Agency (FEMA),

Region II Office, to the New Jersey State Police Emergency Management Section dated October 19, 2009. This letter discusses a planning deficiency identified during evaluation of the October 6, 2009, emergency preparedness exercise at the Oyster Creek Nuclear Generating Station. FEMA defines a deficiency as "an observed or identified inadequacy of organizational performance in an exercise that could cause a finding that offsite emergency preparedness is not adequate to provide reasonable assurance that appropriate measures can be taken in the event of a radiological emergency to protect the health and safety of the public living in the vicinity of a nuclear power plant." Specifically, the deficiency in this case resulted from a number of the municipalities not receiving notice of the Protective Action DeCision, which recommended evacuation of a number of Emergency Response Planning Areas (ERPAs) and sheltering-in place for the rest of the ERPAs in the Emergency Planning Zone {EPZ} for over an hour..

The purpose of this letter is to communicate FEMA's official notification of the deficiency that was sent to the New Jersey State Police. This letter is in accordance with the NRC-FEMA Memorandum of Understanding. No response to the NRC is required.

The NRC encourages Exelon to work with the appropriate offsite governmental agencies to ensure a timely resolution of this issue. The Nf~C will continue to monitor the status of this issue. It is our understanding that a focused dE~monstration of this aspect of the exercise has been scheduled for December 8, 2009. In accordance with the NRC-FEMA Memorandum of Understanding, the NRC and the FEMA Region II Office will assess the progress made toward resolution of the issue, and will decide at that time if additional measures are necessary.

If this issue is not adequately resolved by February 4, 2010, FEMA may withdraw the finding of reasonable assurance according to the requirements of 44 CFR 350.13(a). At that time, the NRC would take appropriate action according to the requirements of 10 CFR 50.54(5)(2) and 50.54(s)(3).

C. Pardee 2 In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-<

rm/adams.html (the Public Electronic Reading Room).

If you have any further questions, please contact Cherie J. Crisden at (610) 337-5061.

Sincerely, (71nj~

J~lmes M. Trapp, Chief Plant Support Branch 1 Division of Reactor Safety Docket No: 50-219 License No: DPR-16

Enclosure:

Letter from the Federal Emergency Management Agency, Region II Office, to the New Jersey State Police Emergency Management Section dated October 19, 2009 cc w/

Enclosure:

Distribution via ListServ

C. Pardee 2 In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.govlreading

. rm/adams.html {the Public Electronic Reading Room}.

If you have any further questions, please contact Cherie J. Crisden at (610) 337-5061.

Sincerely,

/f..~A/

James M. Trapp, Chief Plant Support Branch 1 Division of Reactor Safety Docket No:* 50-219 License No: DPR-16

Enclosure:

Letter from the Federal Emergency Management Agency, Region II Office, to the New Jersey State Police Emergency Management Section dated October 19,2009 cc w/Enciosure: Distribution via ListServ SUNSI Review Complete: _ _ _......=J.:.:,M:..:,T_ _ (Reviewer's Initials)

DOCUMENT NAME: G:\DRS\PLANT SUPPORT BRANCH 1\CRISDEN\EP EX 09 OC\OYSTER CREEK 09 EP EX FEMA DEV REFERRAL.DOCdoc ADAMS ACCESSION NO. ML093070475 After declaring this document "An Official Agency Record" it will be released to the Public.

To receive a copy*of th'IS d ocumen. t tta chmentJencI osure "E" ::: Co>py WI*th a ttachmenIIencI osure "N° = NoCOPY

. d'Icate'In t he box: *C" = Co:lPY'withou:a t In OFFICE RVDRS I RI/ORA I RIIDRP I HQlNSIR I RIIDRS I NAME CCrisden/CJC NMcNamara/NTM RBeliamy/RRB RKahlerlvia e-mail JTrapp/JMT DATE 10/23/09 10/27/09 10/29/09 29/09 11/03/09 OFFICIAL RECORD COpy

C. Pardee 3 Distribution wlo encl:

S. Collins, RA (R10RAMaii Resource)

M. Dapas, DRA (R10RAMaii Resource)

D. Lew. DRP (R1DRPMaii Resource)

J.. Clifford, DRP (R1DRPMaii Resource)

R. Bellamy. DRP S. Barber, DRP C. Newport, DRP, Acting RI J. Kulp, DRP, SRI J. DeVries, DRP, OA L Trocine, RI OEDO RidsNrrPMOysterCreek Resource RidsNrrDorlLpl1-2 Resource Region I Docket Room (with concurrences)

D. Roberts. DRS (R1DRSMaif Resource)

P. Wilson, DRS (R1DRSMaii Resource)

J. Trapp, DRS S. Barr. DRS C. Crisden, DRS

.. ,- ';--.7:!.!:..';;;.::.'t;..