The NMP Project Update for the Independent Spent Fuel Storage Installation (ISFSI)
Project September 15, 2009
- Nine Mile Point (NMP) Unit 1 & 2 Spent Fuel Pools will lose full core off-load reserve in 2011 and 2012 respectively unless additional storage capacity is added.
Additi l f l t ill b id d b
- Additional fuel storage will be provided by installation of an Independent Spent Fuel Storage Installation (ISFSI).
- NMP has standardized on the TransNuclear (TN)
NUHOMS system.
- Plant modifications and crane verifications
- New Dry Fuel Storage site
- Pad capacity for 80 Horizontal Storage Modules (HSMs) 3 Pad capacity for 80 Horizontal Storage Modules (HSMs)
- Future expansion capability to 200 HSMs
- Installation of 40 NUHOMS HSM-102s
- Acquisition of 40 61BT Dry Shielded Canisters (DSCs)
- New Haul Path
- New Equipment Storage Building
- New Transport System and Operations Equipment
- Turnover for Initial Unit 1 Loading Campaign
- Detailed Engineering to complete - September 2010
- Pad Construction to complete - October 2010
- HSM Installation - August 2011
- Licensing Compliance - 2011 4
- NRC Dry Run Observation - May 2012
- Initial Loading Campaign - August 2012
Nine Mile Point ISFSI Layout 5
NMP Dry Run Strategy
- Develop Fleet Procedures for common (NMP & Ginna) functions
- Weld to Pad Procedures Vacuum Drying Canister Welding Lid Removal 6
Lid Removal
- HSM Loading Transport to Pad Canister insertion / extraction
- Develop Site Procedures for specific functions
- Pool to Weld Procedures Fuel Moves Crane Operations Transfer Cask Manipulations in Buildings
Questions Questions 8