Individual Notice of Consideration of Issuance of Amendment to Facility Operating License Proposed No Significant Hazards Consideration Determination, and Opportunity for Hearing (TAC Nos. ME2160 and ME2161)
ML092470187
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 09/08/2009
From: Mozafari B
Plant Licensing Branch II
To: Nazar M
Florida Power & Light Co
Orf, T J, NRR/DORL/301-415-2788
References
NRC-2009-0402, TAC ME2160, TAC ME2161
Download: ML092470187 (11)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 8, 2009 Mr. Mano Nazar Senior Vice President, Nuclear and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, Florida 33408-0420

SUBJECT:

TURKEY POINT, UNITS 3 AND 4 - INDIVIDUAL NOTICE OF CONSIDERATION OF ISSUANCE OF AMENDMENT TO FACILITY OPERATING LICENSE, PROPOSED NO SIGNIFICANT HAZARDS CONSIDERATION DETERMINATION, AND OPPORTUNITY FOR HEARING (TAC NOS. ME2160 AND ME2161)

Dear Mr. Nazar:

The U.S. Nuclear Regulatory Commission has forwarded the enclosed "Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing," to the Office of the Federal Register for publication.

This notice relates to your application dated September 1,2009, in which you request to delay the date specified in License Amendments 234 and 229 for the implementation of the Boraflex Remedy in the Turkey Point Units 3 and 4 spent fuel pools.

If you have any questions, please contact me at 301-415-2020.

Sincerely, Brenda L. Mozafari, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-250 and 50-251

Enclosure:

Notice of Consideration cc w/encl: Distribution via Listserv

7590-01-P NUCLEAR REGULATORY COMMISSION TURKEY POINT DOCKET NOS. 50-250 AND 50-251 NRC-2009-0402 NOTICE OF CONSIDERATION OF ISSUANCE OF AMENDMENT TO FACILITY OPERATING LICENSE, PROPOSED NO SIGNIFICANT HAZARDS CONSIDERATION DETERMINATION, AND OPPORTUNITY FOR A HEARING The U.S. Nuclear Regulatory Commission (the Commission) is considering issuance of an amendment to Facility Operating License No. DPR-31 and Facility Operating License No.

DPR-41 issued to Florida Power & Light (FPL, the licensee) for operation of the Turkey Point, Units 3 and 4 located in Florida City, Florida The proposed amendment would delay the date specified in License Amendments 234 and 229 for the implementation of the Boraflex Remedy in the Turkey Point Units 3 and 4 spent fuel pools.

Before issuance of the proposed license amendment, the Commission will have made findings required by the Atomic Energy Act of 1954, as amended (the Act), and the Commission's regulations.

The Commission has made a proposed determination that the amendment request involves no significant hazards consideration. Under the Commission's regulations in Title 10 of the Code of Federal Regulations (10 CFR), Section 50.92, this means that operation of the facility in accordance with the proposed amendment would not (1) involve a significant increase in the probability or consequences of an accident previously evaluated; or (2) create the possibility of a new or different kind of accident from any accident previously evaluated; or (3) involve a significant reduction in a margin of safety. As required by 10 CFR 50.91 (a), the

-2 licensee has provided its analysis of the issue of no significant hazards consideration, which is presented below:

1. Does the proposed change involve a significant increase in the probability or consequences of an accident previously evaluated?

Response: No.

The proposed license amendments extend the implementation period specified in License Amendments 234 and 229. The delay will allow FPL to continue to work with our vendor to successfully fabricate the Metamic inserts to the design requirements for insertion until both SFPs [spent fuel pools] are configured in accordance with the previously approved Boraflex Remedy license amendments.

During this extension period, FPL will continue to rely on the current Turkey Point licensing basis, including the presence of Boraflex, the continuation of existing administrative controls, and our currently approved monitoring and surveillance program until such time that the Boraflex Remedy license amendments are fully implemented. These measures will continue to ensure required margins to criticality are maintained such that the consequences of an accident are not increased. As the delay in implementation of the Boraflex Remedy does not affect any accident initiation sequences, the probability of occurrence on an accident in the SFPs is not increased by delay in implementation of License Amendment Nos. 234 and 229. Therefore, the proposed change does not involve a significant increase in the probability or consequences of an accident previously evaluated.

2. Does the proposed change create the possibility of a new or different kind of accident from any previously evaluated?

Response: No.

The proposed license amendments extend the implementation period specified in License Amendments 234 and 229. The delay will allow FPL to continue to work with our vendor to successfully fabricate the Metamic inserts to the design requirements for insertion until both SFPs are configured in accordance with the previously approved Boraflex Remedy license amendments.

During this extension period, FPL will continue to rely on the current Turkey Point licensing basis, including the presence of Boraflex, the continuation of existing administrative controls, and our currently approved monitoring and surveillance program until such time that the Boraflex Remedy license amendments are fully implemented. As no unapproved physical changes to the spent fuel storage cells are involved with this delay in implementation of the Boraflex Remedy, no new failure modes are created by an extended

-3 implementation date. Therefore, the proposed change does not create the possibility of a new or different kind of accident from any previously evaluated.

3. Does the proposed change involve a significant reduction in the margin of safety?

Response: No.

The proposed license amendments extend the implementation period specified in License Amendments 234 and 229. The delay will allow FPL to continue to work with our vendor to successfully fabricate the Metamic inserts to the design requirements for insertion until both SFPs are configured in accordance with the previously approved Boraflex Remedy license amendments.

During this extension period, FPL will continue to rely on the current Turkey Point licensing basis, including the presence of Boraflex, the continuation of existing administrative controls, and our currently approved monitoring and surveillance program until such time that the Boraflex Remedy license amendments are fully implemented. These measures will continue to ensure required margins to criticality are maintained. As no unapproved physical changes to the spent fuel storage cells are involved with this delay in implementation of the Boraflex Remedy and since Boraflex degradation will continue to be closely monitored to ensure acceptable margins to criticality are maintained, the proposed change does not involve a significant reduction in a margin of safety.

The NRC staff has reviewed the licensee's analysis and, based on this review, it appears that the three standards of 10 CFR 50.92(c) are satisfied. Therefore, the NRC staff proposes to determine that the amendment request involves no significant hazards consideration.

The Commission is seeking public comments on this proposed determination. Any comments received within 30 days after the date of publication of this notice will be considered in making any final determination.

Normally, the Commission will not issue the amendment until the expiration of 60 days after the date of publication of this notice. The Commission may issue the license amendment before expiration of the 60-day period provided that its final determination is that the amendment involves no significant hazards consideration. In addition, the Commission may issue the amendment prior to the expiration of the 30-day comment period should

- 4 circumstances change during the 30-day comment period such that failure to act in a timely way would result, for example, in derating or shutdown of the facility. Should the Commission take action prior to the expiration of either the comment period or the notice period, it will publish in the Federal Register a notice of issuance. Should the Commission make a final No Significant Hazards Consideration Determination, any hearing will take place after issuance. The Commission expects that the need to take this action will occur very infrequently.

Written comments may be submitted by mail to the Chief, Rulemaking and Directives Branch (RDB), TWB-05-B01 M, Division of Administrative Services, Office of Administration, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, and should cite the publication date and page number of this Federal Register notice. Written comments may also be faxed to the RDB at 301-492-3446. Documents may be examined, and/or copied for a fee, at the NRC's Public Document Room (PDR), located at One White Flint North, Public File Area 01 F21, 11555 Rockville Pike (first floor), Rockville, Maryland.

Within 60 days after the date of publication of this notice, any person(s) whose interest may be affected by this action may file a request for a hearing and a petition to intervene with respect to issuance of the amendment to the subject facility operating license. Requests for a hearing and a petition for leave to intervene shall be filed in accordance with the Commission's "Rules of Practice for Domestic Licensing Proceedings" in 10 CFR Part 2. Interested person(s) should consult a current copy of 10 CFR 2.309, which is available at the Commission's PDR, located at One White Flint North, Public File Area 01 F21, 11555 Rockville Pike (first floor),

Rockville, Maryland. Publicly available records will be accessible from the Agencywide Documents Access and Management System's (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, http://www.nrc.gov/reading-rm/doc-collections/cfr/. If a request for a hearing or petition for leave to intervene is filed by the above date, the Commission or a presiding officer designated by the Commission or by the Chief Administrative

-5 Judge of the Atomic Safety and Licensing Board Panel, will rule on the request and/or petition; and the Secretary or the Chief Administrative Judge of the Atomic Safety and Licensing Board will issue a notice of a hearing or an appropriate order.

As required by 10 CFR 2.309, a petition for leave to intervene shall set forth with particularity the interest of the petitioner in the proceeding, and how that interest may be affected by the results of the proceeding. The petition should specifically explain the reasons why intervention should be permitted with particular reference to the following general requirements: 1) the name, address and telephone number of the requestor or petitioner; 2) the nature of the requestor's/petitioner's right under the Act to be made a party to the proceeding;

3) the nature and extent of the requestor's/petitioner's property, financial, or other interest in the proceeding; and 4) the possible effect of any decision or order which may be entered in the proceeding on the requestor's/petitioner's interest. The petition must also identify the specific contentions which the petitioner/requestor seeks to have litigated at the proceeding.

Each contention must consist of a specific statement of the issue of law or fact to be raised or controverted. In addition, the petitioner/requestor shall provide a brief explanation of the bases for the contention and a concise statement of the alleged facts or expert opinion which support the contention and on which the petitioner intends to rely in proving the contention at the hearing. The petitioner/requestor must also provide references to those specific sources and documents of which the petitioner is aware and on which the petitioner intends to rely to establish those facts or expert opinion. The petition must include sufficient information to show that a genuine dispute exists with the applicant on a material issue of law or fact. Contentions shall be limited to matters within the scope of the amendment under consideration. The contention must be one which, if proven, would entitle the petitioner to relief.

A petitioner/requestor who fails to satisfy these requirements with respect to at least one contention will not be permitted to participate as a party.

- 6 Those permitted to intervene become parties to the proceeding, subject to any limitations in the order granting leave to intervene, and have the opportunity to participate fully in the conduct of the hearing.

If a hearing is requested, the Commission will make a final determination on the issue of no significant hazards consideration. The final determination will serve to decide when the hearing is held. If the final determination is that the amendment request involves no significant hazards consideration, the Commission may issue the amendment and make it immediately effective, notwithstanding the request for a hearing. Any hearing held would take place after issuance of the amendment. If the final determination is that the amendment request involves a significant hazards consideration, any hearing held would take place before the issuance of any amendment.

All documents filed in NRC adjudicatory proceedings, including a request for hearing, a petition for leave to intervene, any motion or other document filed in the proceeding prior to the submission of a request for hearing or petition to intervene, and documents filed by interested governmental entities participating under 10 CFR 2.315(c), must be filed in accordance with the NRC E-Filing rule, which the NRC promulgated on August 28,2007 (72 FR 49139). The E Filing process requires participants to submit and serve all adjudicatory documents over the internet, or in some cases to mail copies on electronic storage media. Participants may not submit paper copies of their filings unless they seek an exemption in accordance with the procedures described below.

To comply with the procedural requirements of E-Filing, at least ten (10) days prior to the filing deadline, the petitioner/requestor should must contact the Office of the Secretary bye-mail at hearing.docket@nrc.gov, or by calling (301) 415-1677, to request (1) a digital 10 certificate, which allows the participant (or its counselor representative) to digitally sign documents and access the E-Submittal server for any proceeding in which it is participating; and/or (2) creation

-7 of an electronic docket for the proceeding (even in instances in which the petitioner/requestor (or its counselor representative) already holds an NRC-issued digital 10 certificate). Each petitioner/ requestor will need to download the Workplace Forms Viewer' to access the Electronic Information Exchange (EIE), a component of the E-Filing system. The Workplace Forms Viewer' is free and is available at http://www.nrc.gov/site-help/e-submittals/install viewer.html. Information about applying for a digital 10 certificate is available on NRC's public Web site at http://www.nrc.gov/site-help/e-submittals/apply-certificates.html.

Once a petitioner/requestor has obtained a digitallD certificate, had a docket created, and downloaded the EIE viewer, it can then submit a request for hearing or petition for leave to intervene. Submissions should be in Portable Document Format (PDF) in accordance with NRC guidance available on the NRC public Web site at http://www.nrc.gov/site-help/e submittals.html. A filing is considered complete at the time the filer submits its documents through EIE. To be timely, an electronic filing must be submitted to the EIE system no later than 11 :59 p.m. Eastern Time on the due date. Upon receipt of a transmission, the E-Filing system time-stamps the document and sends the submitter an e-mail notice confirming receipt of the document. The EIE system also distributes an e-mail notice that provides access to the document to the NRC Office of the General Counsel and any others who have advised the Office of the Secretary that they wish to participate in the proceeding, so that the filer need not serve the documents on those participants separately. Therefore, applicants and other participants (or their counselor representative) must apply for and receive a digital ID certificate before a hearing request/petition to intervene is filed so that they can obtain access to the document via the E-Filing system.

A person filing electronically using the agency's adjudicatory e-filing system may seek assistance through the "Contact Us" link located on the NRC website at http://www.nrc.gov/site help/e-submittals.html or by calling the NRC Meta-System Help Desk, which is available

-8 between 8:00 a.m. and 8:00 p.m., Eastern Time, Monday through Friday, excluding government holidays. The Meta-System Help Desk can be contacted by telephone at 1-866-672-7640 or by e-mail at MSHD.Resource@nrc.gov.

Participants who believe that they have a good cause for not submitting documents electronically must file an exemption request, in accordance with 10 CFR 2.302(g), with their initial paper filing requesting authorization to continue to submit documents in paper format.

Such filings must be submitted by: (1) first class mail addressed to the Office of the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention: Rulemaking and Adjudications Staff; or (2) courier, express mail, or expedited delivery service to the Office of the Secretary, Sixteenth Floor, One White Flint North, 11555 Rockville Pike, Rockville, Maryland, 20852, Attention: Rulemaking and Adjudications Staff. Participants filing a document in this manner are responsible for serving the document on all other participants. Filing is considered complete by first-class mail as of the time of deposit in the mail, or by courier, express mail, or expedited delivery service upon depositing the document with the provider of the service.

Non-timely requests and/or petitions and contentions will not be entertained absent a determination by the Commission, the presiding officer, or the Atomic Safety and Licensing Board that the request and/or petition should be granted and/or the contentions should be admitted, based on a balancing of the factors specified in 10 CFR 2.309(c)(1 )(i)-(viii).

Documents submitted in adjudicatory proceedings will appear in NRC's electronic hearing docket which is available to the public at http://ehd.nrc.gov/ehd proceeding/home. asp, unless excluded pursuant to an order of the Commission, an Atomic Safety and Licensing Board, or a Presiding Officer. Participants are requested not to include personal privacy information, such as social security numbers, home addresses, or home phone numbers in their

-9 filings, unless an NRC regulation or other law requires submission of such information. With respect to copyrighted works, except for limited excerpts that serve the purpose of the adjudicatory filings and would constitute a Fair Use application, participants are requested not to include copyrighted materials in their submissions.

For further details with respect to this license amendment application, see the application for amendment dated [date], which is available for public inspection at the Commission's PDR, located at One White Flint North, File Public Area 01 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records will be accessible electronically from the Agencywide Documents Access and Management System's (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, http://www.nrc.gov/reading rm/adams.html. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS, should contact the NRC PDR Reference staff by telephone at 1-800-397-4209,301-415-4737, or bye-mail to pdr.resource@nrc.gov.

Attorney for licensee: M.S. Ross, Attorney, Florida Power & Light, P.O. Box 14000, Juno Beach, Florida 33408-0420.

Dated at Rockville, Maryland, this 8th day of September, 2009.

FOR THE NUCLEAR REGULATORY COMMISSION Brenda L. Mozafari, Senior Project a ager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

September 8, 2009 Mr. Mano Nazar Senior Vice President, Nuclear and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, Florida 33408-0420 SUB..IECT: TURKEY POINT, UNITS 3 AND 4 - INDIVIDUAL NOTICE OF CONSIDERATION OF ISSUANCE OF AMENDMENT TO FACILITY OPERATING LICENSE, PROPOSED NO SIGNIFICANT HAZARDS CONSIDERATION DETERMINATION, AND OPPORTUNITY FOR HEARING (TAC NOS. ME2160 AND ME2161)

Dear Mr. Nazar:

The U.S. Nuclear Regulatory Commission has forwarded the enclosed "Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing," to the Office of the Federal Register for publication.

This notice relates to your application dated September 1, 2009, in which you request to delay the date specified in License Amendments 234 and 229 for the implementation of the Boraflex Remedy in the Turkey Point Units 3 and 4 spent fuel pools.

If you have any questions, please contact me at 301-415-2020.

Sincerely, IRA!

Brenda L. Mozafari, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-250 and 50-251

Enclosure:

Notice of Consideration cc w/encl: Distribution via Listserv DISTRIBUTION:

PUBLIC Branch Reading RidsAcrsAcnw_MailCTR Resource RidsNrrDorlDpr Resource RidsNrrDorlLpl2-2 Resource RidsNrrLABClayton Resource RidsNrrPMTurkeyPoint Resource RidsOgcRp Resource RidsRgn2MailCenter Resource ADAMS Accession Nos ML092470187 OFFICE NRRlLPL2-2/PM NRR/LPL2-2/PM NRR/LPL2-2/LA NRR/LPL2-2/BC NRR/LPL2-2/PM NAME TOrf for JPaige BMozafari BClayton EBrown for TBoyce BMozafari DATE 09/08/09 09/08/09 09/04/09 09/08/09 09/08/09 OFFICIAL AGENCY RECORD