Inspection/Activity Plan 09/01/2009 - 12/31/2010
ML092440533
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 09/01/2009
From:
NRC/RGN-II
To:
Virginia Electric & Power Co (VEPCO)
References
Download: ML092440533 (2)


Text

Inspection / Activity Plan Page 1 of 2 09/01/2009 07:52:15 Report 22 09/01/2009 - 12/31/2010 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site North Anna ISFSI

- ISFSI OPERATIONAL INSPECTION 2

1, 2 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 07/01/2009 10/15/2009 TFPI

- TRIENNIEL FIRE PROTECTION INSPECTION 7

1, 2 IP Fire Protection [Triennial]

7111105T 09/14/2009 09/18/2009 1, 2 IP Fire Protection [Triennial]

7111105T 09/28/2009 10/02/2009 EB1-CDBI

- COMPONENT DESIGN BASIS INSPECTION 6

1, 2 IP Component Design Bases Inspection 7111121 10/19/2009 10/23/2009 1, 2 IP Component Design Bases Inspection 7111121 11/02/2009 11/06/2009 1, 2 IP Component Design Bases Inspection 7111121 11/16/2009 11/20/2009 1, 2 IP Component Design Bases Inspection 7111121 12/07/2009 12/11/2009 OL RQ

- REQUAL INSPECTION 3

1, 2 IP Licensed Operator Requalification Program 7111111B 01/11/2010 01/15/2010 EB3ISI

- UNIT 1 ISI 1

1 IP Inservice Inspection Activities - PWR 7111108P 03/22/2010 03/26/2010 EB3TI172

- EB3 RCS DM BUTT WELDS 1

1, 2 IP Reactor Coolant System Dissimiliar Metal Butt Welds 2515/172 03/22/2010 03/26/2010 OL EXAM

- INITIAL EXAM PREP 4

1 NORTH ANNA/JUNE 2010 EXAM AT POWER FACILITIES V23333 05/17/2010 05/21/2010 OL EXAM

- INITIAL EXAM - WEEK 1 4

1 NORTH ANNA/JUNE 2010 EXAM AT POWER FACILITIES V23333 06/07/2010 06/11/2010 OL EXAM

- INITIAL EXAM - WEEK 2 4

1 NORTH ANNA/JUNE 2010 EXAM AT POWER FACILITIES V23333 06/21/2010 06/25/2010 PSB1EP

- EMERGENCY PREPARENESS EXERCISE 3

1, 2 IP Exercise Evaluation 7111401 07/19/2010 07/23/2010 1, 2 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 07/19/2010 07/23/2010 1, 2 IP Performance Indicator Verification 71151 07/19/2010 07/23/2010 PSB1-RP

- RP OCCUPATIONAL BASELINE WEEK1 2

1, 2 IP Access Control to Radiologically Significant Areas 7112101 09/13/2010 09/17/2010 1, 2 IP ALARA - Required 7112102-7112102R 09/13/2010 09/17/2010 1, 2 IP Radioactive Material Processing and Transportation 7112202 09/13/2010 09/17/2010 1, 2 IP Performance Indicator Verification 71151 09/13/2010 09/17/2010 EB3ISI

- UNIT 2 INSERVICE INSPECTION 1

2 IP Inservice Inspection Activities - PWR 7111108P 09/20/2010 09/24/2010 EB3TI172

- EB3 RX COOLANT SYS DM BUTT WELDS 1

2 IP Reactor Coolant System Dissimiliar Metal Butt Welds 2515/172 09/20/2010 09/24/2010 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Inspection / Activity Plan Page 2 of 2 09/01/2009 07:52:15 Report 22 09/01/2009 - 12/31/2010 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site North Anna PSB1-RP

- RP OCCUPATIONAL BASELINE WEEK2 2

1, 2 IP Access Control to Radiologically Significant Areas 7112101 09/27/2010 10/01/2010 1, 2 IP ALARA - Required 7112102-7112102R 09/27/2010 10/01/2010 1

IP Radioactive Material Processing and Transportation 7112202 09/27/2010 10/01/2010 1, 2 IP Occupational Exposure Control Effectiveness 71151-OR01 09/27/2010 10/01/2010 1, 2 IP RETS/ODCM Radiological Effluent 71151-PR01 09/27/2010 10/01/2010 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure