UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 September 1, 2009 EA-03-0214 Mr. Barry Allen Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State Route 2, Mail Stop A-DB-3080 Oak Harbor, OH 43449-9760
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
DAVIS-BESSE NUCLEAR POWER STATION
Dear Mr. Allen:
On August 19, 2009, the NRC staff completed its performance review of the Davis-Besse Nuclear Power Station. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from July 1, 2008 through June 30, 2009.
The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only--Security Information" will include the security cornerstone review and resultant inspection plan.
Plant performance for the most recent quarter at Davis-Besse was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). As discussed during the July 15, 2009, End-of-Cycle public meeting, the NRC has completed its review of your activities to comply with the requirements of the 2004 and 2007 Confirmatory Orders. You will receive separate correspondence describing the results of our reviews. No additional inspections are planned regarding those activities. Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at the facility.
The enclosed inspection plan details the inspections, less those related to security, scheduled through December 31, 2010. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite.
Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the End-of-Cycle review.
B. Allen In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 630-829-9833 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket No. 50-346 License No. NPF-3
Enclosure:
Davis Besse Inspection/Activity Plan DISTRIBUTION See next page
Letter to B. Allen from J. Cameron dated September 1, 2009.
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
DAVIS-BESSE NUCLEAR POWER STATION cc w/encl:
Honorable Dennis Kucinich J. Hagan, President and Chief Nuclear Officer - FENOC J. Lash, Senior Vice President of Operations and Chief Operating Officer - FENOC Manager - Site Regulatory Compliance - FENOC D. Pace, Senior Vice President of Fleet Engineering - FENOC K. Fili, Vice President, Fleet Oversight - FENOC P. Harden, Vice President, Nuclear Support D. Jenkins, Attorney, FirstEnergy Corp.
Director, Fleet Regulatory Affairs - FENOC Manager - Fleet Licensing - FENOC C. OClaire, State Liaison Officer, Ohio Emergency Management Agency R. Owen, Administrator, Ohio Department of Health Public Utilities Commission of Ohio President, Lucas County Board of Commissioners President, Ottawa County Board of Commissioners Ottawa County Sheriff Director, Ottawa County EMA Lucas County Sheriff Director, Lucas County EMA Genoa Village Administrator Mayor of Clay Center Mayor of Elmore Mayor of Genoa Mayor of Oak Harbor Mayor of Toledo Mayor of Port Clinton Mayor of Marblehead Mayor of Rocky Ridge Village Administrator of Oak Harbor Mayor of Put-in-Bay G. Mortensen, INPO
B. Allen In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 630-829-9833 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket No. 50-346 License No. NPF-3
Enclosure:
Davis Besse Inspection/Activity Plan DISTRIBUTION See next page DOCUMENT NAME: G:\\Branch TSS\\ALL MOC\\midcycle 2008 to 2009\\Mid-cycle letters\\
Davis Besse 2009 MOC Letter.doc Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME GWright:dtp JCameron DATE 08/27/08 08/27/08 OFFICIAL RECORD COPY
Letter to B. Allen from J. Cameron dated September 1, 2009.
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
DAVIS-BESSE NUCLEAR POWER STATION DISTRIBUTION:
Susan Bagley RidsNrrDorlLpl3-2 RidsNrrPMDavisBesse Resource RidsNrrDirsIpob Resource Cynthia Pederson Steven Orth Jared Heck Allan Barker DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports Resource
Inspection / Activity Plan 2
09/01/2009 - 12/31/2010 Planned Dates Start End Inspection Activity Title No. of Staff on Site Davis-Besse ER F/UP
- FOLLOWUP TO NON DECLARATION OF ALERT 1
IP Followup of Events and Notices of Enforcement Discretion 71153 08/04/2009 09/30/2009 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
IP Access Control to Radiologically Significant Areas 7112101 09/14/2009 09/18/2009 IP ALARA Planning and Controls 7112102 09/14/2009 09/18/2009 IP Occupational Exposure Control Effectiveness 71151-OR01 09/14/2009 09/18/2009 BI ENG
- COMPONENT DESIGN BASES INSPECTION 6
IP Component Design Bases Inspection 7111121 10/19/2009 11/20/2009 BI ENG
- ENGINEERING INSERVICE INSPECTION 1
IP Reactor Coolant System Dissimiliar Metal Butt Welds 2515/172 02/15/2010 03/05/2010 IP Inservice Inspection Activities - PWR 7111108P 02/15/2010 03/05/2010 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
IP Access Control to Radiologically Significant Areas 7112101 02/22/2010 02/26/2010 IP ALARA Planning and Controls 7112102 02/22/2010 02/26/2010 ISFSI
- ISFSI INSPECTION 1
IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 04/01/2010 04/30/2010 BI ENG
- TRIENNIAL FIRE INS INFO GATHERING TRIP 3
IP Fire Protection [Triennial]
7111105T 04/12/2010 04/16/2010 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
IP Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 7112201 04/19/2010 04/23/2010 IP Reactor Coolant System Activity 71151-BI01 04/19/2010 04/23/2010 BI ENG
- TRIENNIAL FIRE PROTECTION INSPECTION 3
IP Fire Protection [Triennial]
7111105T 04/26/2010 05/14/2010 BI EP
- EP ROUTINE INSPECTION / PI VERIFICATION 2
IP Alert and Notification System Testing 7111402 04/26/2010 04/30/2010 IP Emergency Response Organization Augmentation Testing 7111403 04/26/2010 04/30/2010 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 04/26/2010 04/30/2010 IP Drill/Exercise Performance 71151-EP01 04/26/2010 04/30/2010 IP ERO Drill Participation 71151-EP02 04/26/2010 04/30/2010 IP Alert & Notification System 71151-EP03 04/26/2010 04/30/2010 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
IP Access Control to Radiologically Significant Areas 7112101 08/30/2010 09/03/2010 IP ALARA Planning and Controls 7112102 08/30/2010 09/03/2010 IP Occupational Exposure Control Effectiveness 71151-OR01 08/30/2010 09/03/2010
Inspection / Activity Plan 09/01/2009 - 12/31/2010 Planned Dates Start End Inspection Activity Title No. of Staff on Site Davis-Besse BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
IP Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 7112203 11/01/2010 11/05/2010 IP RETS/ODCM Radiological Effluent 71151-PR01 11/01/2010 11/05/2010 BI OL
- LIC. OPERATOR REQUAL. PROGRAM EVALUATION 2
IP Licensed Operator Requalification Program 7111111B 11/15/2010 11/19/2010