MONTHYEARML0812206902008-05-0707 May 2008 GL-2008-01, Managing Gas Accumulation in ECC Decay Heat Removal and Containment Spray Systems Response to Extension Request Project stage: Other NG-08-0239, Three Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems2008-05-0808 May 2008 Three Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Request ML0819302092008-08-0606 August 2008 Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Proposed Alternative Course of Action Project stage: Other NG-08-0777, Nine-Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems2008-10-13013 October 2008 Nine-Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Request NG-09-0327, Nine-Month Supplemental (Post-Outage) Response to NRC Generic Letter 2008-012009-04-27027 April 2009 Nine-Month Supplemental (Post-Outage) Response to NRC Generic Letter 2008-01 Project stage: Request ML0923003792009-08-13013 August 2009 Draft RAI, Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems. Project stage: Draft RAI ML0922603112009-08-13013 August 2009 MD7824 - GL 2008-01 (Managing Gas Accumulation) - Request for Additional Information Project stage: RAI ML0923201162009-08-28028 August 2009 Request for Additional Information Regarding Your Nine Month Response to NRC Generic Letter 2009-01. Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: RAI NG-09-0774, Response to Request for Additional Information Regarding NextEra Energy Duane Arnold'S Nine Month Response to Generic Letter 2008-012009-10-16016 October 2009 Response to Request for Additional Information Regarding NextEra Energy Duane Arnold'S Nine Month Response to Generic Letter 2008-01 Project stage: Response to RAI ML0934310852009-12-16016 December 2009 Closeout of Generic Letter 2008-01 Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Other 2009-10-16
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML23109A1862023-04-19019 April 2023 and Turkey Point Acceptance of Requested Licensing Action Proposed Alternative to Asme Section XI Authorizing Implementation of Asme Code Case N-752-1 ML22067A0922022-03-0303 March 2022 State Consultation - Duane Arnold ISFSI-Only EP License Amendment ML22040A1162022-02-0808 February 2022 Email to G. Van Noordennen Zion and La Crosse Review Schedule Changes ML22027A3582022-01-26026 January 2022 DAEC: CY2022 Inspection Plan, Docket No: 05000331, License No: DPR-49 ML22007A3102022-01-0505 January 2022 State Consultation - Draft No Significant Hazards Determination Regarding a LAR for NextEra Energy Duane Arnold, LLC, Duane Arnold Energy Center ISFSI in Palo, Iowa ML22005A0862022-01-0404 January 2022 1-4-2022 Email Communication to Duane Arnold Regarding Its ISFSI Related Exemption Request on Supplemental Information Needed ML22005A0992022-01-0404 January 2022 Email from a Snyder to a Leek Re State Consultation - Draft No Significant Hazards Determination - License Amend. Req. for NextEra Energy, LLC, DAEC ISFSI in Palo, Iowa ML22005A1012022-01-0404 January 2022 Email from a Leek to a Snyder Re State Consultation - Draft No Significant Hazards Determination - License Amend. Req. for NextEra Energy, LLC, DAEC ISFSI in Palo Iowa ML22004A0122022-01-0303 January 2022 E-mail from M. Davis, NextEra, to A. Snyder, NRC, - Duane Arnold Energy Center - Supplement Information to Technical Specification Amendment Application ML21354A6722021-12-17017 December 2021 Email to State of Iowa - Draft EA on Duane Arnold Exemption ML21214A0482021-08-0101 August 2021 Acceptance of License Amendment Request to Adopt an ISFSI-Only Emergency Plan ML21214A0502021-08-0101 August 2021 Acceptance of License Amendment Request to Adopt an ISFSI-Only Physical Security Plan ML21165A1212021-06-10010 June 2021 E-mail from M. Davis, Duane Arnold, to M. Doell and R. Edwards, NRC - Duane Arnold Defueled Emergency Plan Implementation Confirmation ML21117A2752021-04-26026 April 2021 Acceptance of Updated Spent Fuel Management Plan ML21089A2092021-03-19019 March 2021 Spent Fuel Pattern Procedure ML21068A3352021-03-0707 March 2021 Acceptance of License Amendment Request to Adopt ISFSI-Only Technical Specifications ML21056A2172021-02-17017 February 2021 Acceptance of License Amendment Request to Revise the Physical Security Plan Requirements ML21032A1852021-02-0101 February 2021 Daec_ CY2021 Inspection Plan ML21006A4052021-01-0606 January 2021 NRR E-mail Capture - Final RAI - Duane Arnold - Post-Shutdown Decommissioning Activities Report ML20338A0032020-12-0101 December 2020 Letter from EPRI to Mr. Scott Wall, BWRVIP 2020-100, 288 Surveillance Capsule Test Results Report ML20316A0212020-11-10010 November 2020 NRR E-mail Capture - Final RAI - Duane Arnold - Duane Arnold Amendment for Proposed Defueled EP and EAL Scheme ML20289A3522020-10-14014 October 2020 NRR E-mail Capture - Duane Arnold Energy Center -Acceptance of Requested Licensing Action, One-Time Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Pandemic (EPID No. L-2020-LLE-01 ML20153A3772020-05-28028 May 2020 NRR E-mail Capture - Request for Additional Information - Duane Arnold Energy Center Quality Assurance Topical Report (FPL-3) - EPID L-2020-LLQ-0002) ML20154K6202020-05-27027 May 2020 COVID-19 Preparedness Assessments for FEMA Region VII Duane Arnold Energy Center (DAEC) and Quad Cities Generating Station (Qcgs) ML20141L8132020-05-19019 May 2020 NRR E-mail Capture - Request for Additional Information - Duane Arnold Energy Center (DAEC) - Exemption Request for Security Training Requirements Due to COVID-19 Pandemic - EPID L-2020-LLE-0042 to 45, L-2020-LLE-0051 ML20129J8282020-05-0606 May 2020 NRR E-mail Capture - LIC-109 Acceptance Review of Duane Arnold Request for Exemption from Portions of 10 CFR 50.47 and Appendix E - EPID L-2020-LLE-0023 ML20127H8662020-05-0505 May 2020 NRR E-mail Capture - Duane Arnold Energy Center (DAEC) - Request for Additional Information (RAI) - Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 1O CFR 50.75(h)(1)(iv) - EPID L-2020-LLE-0011 ML20122A1152020-04-30030 April 2020 NRR E-mail Capture - Duane Arnold Energy Center -Acceptance of Post-Shutdown Decommissioning Activities Report ML20087F2872020-03-26026 March 2020 NRR E-mail Capture - LIC-109 Acceptance Review of Duane Arnold Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) and 1O CFR 50.75(h)(1)(iv) - EPID L-2020-LLE-0011 ML20129J8322020-03-19019 March 2020 NRR E-mail Capture - (External_Sender) Teleconference with Nextra Energy - Duane Arnold Physical Security Plan LIC-109 Review Status ML20022A3602020-01-22022 January 2020 NRR E-mail Capture - Duane Arnold Energy Center - Acceptance of Requested Licensing Action, Proposed Partial Exemption from Record Retention Requirements ML19352G6872019-12-11011 December 2019 12-11-19 Email to FEMA: Response to FEMA Questions on Proposed DAEC Emergency Plan ML19302G3212019-10-29029 October 2019 LIC-109 Acceptance of Duane Arnold Energy Center (DAEC) - License Amendment Request (TSCR- 186) - Removal of License Condition 2.C.(3), Fire Protection Program - EPID L-2019-LLA-0211 ML19302G9732019-10-29029 October 2019 NRR E-mail Capture - LIC-109 Acceptance of Duane Arnold Energy Center (DAEC) - License Amendment Request (TSCR- 186): Removal of License Condition 2.C.(3), Fire Protection Program - EPID L-2019-LLA-0211 ML19280A0352019-10-0404 October 2019 NRR E-mail Capture - Final - RAI Related to License Amendment Request (TSCR-182) for Proposed Changes to the Emergency Plan for Permanently Defueled Conditions at Duane Arnold Energy Center (DAEC) - L-2019-LLA-0075 ML19206A2182019-07-25025 July 2019 NRR E-mail Capture - LIC-109 Acceptance of Duane Arnold Energy Center (DAEC) - License Amendment Request (TSCR-183) - Application to Revise Operating License and TS for Permanently Defueled Condition - EPID L-2019-LLA-0130 ML19183A0172019-06-26026 June 2019 NRR E-mail Capture - LIC-109 Acceptance of Request for Change in the BWRVIP Integrated Surveillance Program Test Schedule to Accommodate Early Closure of the Duane Arnold Energy Center - EPID L-2019-LRO-0042 ML19122A4882019-04-29029 April 2019 NRR E-mail Capture - LIC-109 Acceptance of License Amendment Request (TSCR-182) for Duane Arnold Energy Center (DAEC) - Proposed Changes to the Emergency Plan for Permanently Defueled Condition - EPID L-2019-LLA-0075 ML19086A3502019-03-27027 March 2019 NRR E-mail Capture - LIC-109 Acceptance of the Request for Exemption from 10 CFR 73.55(p)(1)(I) and 10 CFR 73.55(p)(1)(ii) for Duane Arnold Energy Center - EPID L-2019-LLE-0003 ML19064A2032019-03-0404 March 2019 NRR E-mail Capture - Results of LIC-109 Acceptance Review - Duane Arnold Energy Center - Request for Approval of Certified Fuel Handler Training Program, EPID L-2019-LLL-0003 ML18283B0522018-10-0909 October 2018 NRR E-mail Capture - Final Second Round - Request for Additional Information (RAI) - Duane Arnold Energy Center (DAEC) - LAR TSCR-166, Adoption of EAL Scheme Pursuant to NEI 99-01 - EPID L-2017-LLA-0420 ML18255A2922018-09-11011 September 2018 NRR E-mail Capture - Draft Second Round - Request for Additional Information (RAI) - Duane Arnold Energy Center (DAEC) - LAR TSCR-166, Adoption of EAL Scheme Pursuant to NEI 99-01 - EPID L-2017-LLA-0420 ML18166A2982018-06-15015 June 2018 NRR E-mail Capture - Draft Request for Additional Information (RAI) - Duane Arnold Energy Center (DAEC) - LAR TSCR-166, Adoption of EAL Scheme Pursuant to NEI 99-01 - EPID L-2017-LLA-0420 ML18108A3102018-04-12012 April 2018 NRR E-mail Capture - Audit at NextEra Headquarters, Juno Beach, Florida - April 24, 2018 Through April 26, 2018 - 50.69 LARs for Duane Arnold Energy Center (Daec), and Point Beach Nuclear Plant (Pbnp), Units 1 and 2 - EPIDs L-2017-LLA-0283/ ML18088A0102018-03-28028 March 2018 NRR E-mail Capture - Final RAI for Duane Arnold (DAEC) 5th-10 Year ISI (RR-05) ML18037B0032018-02-0606 February 2018 NRR E-mail Capture - Draft Request for Additional Information - Duane Arnold Energy Center (DAEC) - License Amendment Request (TSCR-170), Revision to Technical Specification 3.5.1, ECCS-Operating - EPID L-2017-LLA-0288 ML18025A2362018-01-24024 January 2018 NRR E-mail Capture - Resent - LIC-109 Acceptance - Duane Arnold LAR (TSCR-166) - Adoption of Emergency Action Level (EAL) Scheme Pursuant to NEI 99-01, Revision 6, Development of EALs for Non-Passive Reactors ML18023A0752018-01-22022 January 2018 NRR E-mail Capture - LIC-109 Acceptance - Duane Arnold License Amendment Request (LAR) (TSCR-179) - Application to Add Technical Specification 3.2.3, Linear Heat Generation Rate - EPID: L-2017-LLA-0436 ML18019A0732018-01-18018 January 2018 NRR E-mail Capture - LIC-109 Acceptance - Duane Arnold License Amend Request (LAR)(TSCR-178) - Application to Reduce the Required Number of Operable Suppression Chamber-to-Drywell Vacuum Breakers ML17355A0132017-12-20020 December 2017 NRR E-mail Capture - LIC-109 Acceptance of Duane Arnold LAR TSCR-177, Application to Revise Tech Spec to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements - EPID: L-2017-LLA-0385 2023-04-19
[Table view] |
Text
From: Feintuch, Karl Sent: Thursday, August 13, 2009 5:25 PM To: 'Tony.Browning@nexteraenergy.com' Cc: Razzaque, Muhammad
Subject:
MD7824 - Generic Letter 2008-01 (Managing Gas Accumulation...) - Request for Additional Information (RAI)
Attachments: MD7824 draft RAI Reqst to DAEC due 25Sep09.doc Attached is an draft RAI document pertaining to GL 2008-01. We would like to schedule a conference call with your staff to verify your understanding of the items being requested, clarify the nature of the needed response, and affirm the date associated with the response (September 25, 2009).
The NRC participants in the call will be Muhammad Razzaque of the Reactor Systems Branch and myself. We propose a nominal one hour conference call on either Monday (August 17) or Wednesday (August 19 - the preferred date) within the period from 1:00 PM ET ending not later than 5:00 PM ET (12:00 PM to 4:00 PM CT).
Subsequent to the conference call we will provide a letter including the RAIs as discussed and the requested date of response as confirmed during the conversation.
Karl Feintuch Project Manager USNRC 301-415-3079 E-mail Properties Mail Envelope Properties (3D27D29AB75BCD4BAE913B63CBFBBEDFDE75B18A81)
Subject:
MD7824 - Generic Letter 2008-01 (Managing Gas Accumulation...) - Request for Additional Information (RAI)
Sent Date: 8/13/2009 5:25:26 PM Received Date: 8/13/2009 5:25:00 PM From: Feintuch, Karl Created By: Karl.Feintuch@nrc.gov Recipients:
Tony.Browning@nexteraenergy.com ('Tony.Browning@nexteraenergy.com')
Tracking Status: None Muhammad.Razzaque@nrc.gov (Razzaque, Muhammad)
Tracking Status: None Post Office:
HQCLSTR01.nrc.gov
Files Size Date & Time MESSAGE 73370 8/13/2009 MD7824 draft RAI Reqst to DAEC due 25Sep09.doc 63266 Options Expiration Date: