MONTHYEARIR 05000413/20240032024-11-0404 November 2024 Integrated Inspection Report 05000413/2024003 and 05000414/2024003 ML24297A6222024-10-11011 October 2024 PCA Letter to NRC Catawba Hurricane Helene IR 05000413/20240112024-10-0101 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000413/2024011 and 05000414/2024011 ML24255A8312024-09-23023 September 2024 Project Manager Assignment ML24261B9782024-09-19019 September 2024 Notification of an NRC Fire Protection Team Inspection NRC Inspection Report 05000413-2024010, 05000414-2024010 and Request for Information IR 05000414/20240912024-09-0505 September 2024 Final Significance Determination of a White Finding and Nov and Assessment Followup Letter-NRC Inspection Report 05000414-2024091 IR 05000413/20240052024-08-26026 August 2024 Updated Inspection Plan for Catawba Nuclear Station (Report 05000413/2024005 & 05000414/2024005) ML24235A1542024-08-22022 August 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000413-2024402 and 05000414-2024402) IR 05000413/20240022024-08-0808 August 2024 Integrated Inspection Report 05000413-2024002 and 05000414-2024002 and Apparent Violation IR 05000413/20244032024-08-0101 August 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000413/2024403; 05000414/2024403 ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 ML24178A0552024-06-26026 June 2024 Requalification Program Inspection – Catawba Nuclear Station IR 05000414/20240902024-06-24024 June 2024 NRC Inspection Report 05000414/2024090 and Preliminary White Finding and Apparent Violation ML24170A8632024-06-11011 June 2024 Flowserve June 11, 2024, Part 21 Notification - Redacted Version for Publishing ML24149A1772024-05-28028 May 2024 NRC Response to Duke Energy 2025 FOF Schedule Change Request (Catawba and McGuire) ML24144A1162024-05-28028 May 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc IR 05000413/20240012024-05-10010 May 2024 Integrated Inspection Report 05000413/2024001 and 05000414/2024001 and Apparent Violation ML24095A1072024-04-0808 April 2024 – Review of the Spring 2023 Steam Generator Tube Inspection Report (C1R27) IR 05000413/20243012024-03-12012 March 2024 – Notification of Licensed Operator Initial Examination 05000413/2024301 and 05000414/2024301 ML24017A0652024-03-0808 March 2024 Issuance of Amendment Nos. 319 and 315 to Technical Specification 3.7.11, Control Room Area Chill Water System (Cracws) 05000414/LER-2024-001, Condition Prohibited by Technical Specifications and Loss of Safety Function Due to Failed Damper Controller for the 2A1 Emergency Diesel Generator Room Ventilation Fan2024-03-0404 March 2024 Condition Prohibited by Technical Specifications and Loss of Safety Function Due to Failed Damper Controller for the 2A1 Emergency Diesel Generator Room Ventilation Fan IR 05000413/20230062024-02-28028 February 2024 Annual Assessment Letter for Catawba Nuclear Station Units 1 and 2 - (NRC Inspection Report 05000413/2023006 and 05000414/2023006) IR 05000413/20230042024-02-0202 February 2024 – Integrated Inspection Report 05000413-2023004 and 05000414-2023004 ML24005A2512024-01-26026 January 2024 Exemption from Select Requirements of 10 CFR Part 73 - Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000413/20230102023-10-11011 October 2023 NRC Inspection Report 05000413/2023010 and 05000414/2023010 ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000413/20230052023-08-25025 August 2023 Updated Inspection Plan for Catawba Nuclear Station Units 1 and 2 (Report 05000413/2023005 and 05000414/2023005) ML23233A1692023-08-17017 August 2023 EN 56683 - Curtiss Wright, Interim Notification Report for PotentialPurt2l IR 05000413/20230022023-07-25025 July 2023 Integrated Inspection Report 05000413/2023002 and 05000414/2023002 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23237A2672023-06-13013 June 2023 June 13, 2002 - Meeting Announcement - McGuire and Catawba Nuclear Stations 50-369, 50-370 and 50-413, 50-414 ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined IR 05000413/20230012023-05-0505 May 2023 – Integrated Inspection Report 05000413/2023001 and 05000414/2023001 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI IR 05000413/20230112023-04-25025 April 2023 Focused Engineering Inspection Report 05000413/2023011 and 05000414/2023011 ML23107A2542023-04-14014 April 2023 301 Examination Report Letter and Report (Merged) ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000413/20234012023-03-0101 March 2023 – Security Baseline Inspection Report 05000413 2023401 and 05000414 2023401 IR 05000413/20220062023-03-0101 March 2023 Annual Assessment Letter for Catawba Nuclear Station, Units 1 and 2 (NRC Inspection Report 05000413/2022006 and 05000414/2022006) IR 05000413/20233012023-02-17017 February 2023 Operator Licensing Examination Approval 05000413/2023301 and 05000414/2023301 IR 05000413/20220042023-01-31031 January 2023 Integrated Inspection Report 05000413/2022004 and 05000414/2022004 05000414/LER-2022-003, Manual Reactor Trip and Auxiliary Feedwater System Actuation2022-12-23023 December 2022 Manual Reactor Trip and Auxiliary Feedwater System Actuation IR 05000413/20220112022-12-15015 December 2022 Biennial Problem Identification and Resolution Inspection Report 05000413/2022011 and 05000414/2022011 ML22356A0512022-12-14014 December 2022 Curtiss-Wright Nuclear Division, Letter Regarding Potential Efect in a Configuration of the 11/2 Inch Quick Disconnect Connector Cable Assemblies Supplied to Duke Energy (See Attached Spreadsheet) for a Total of 460 of Connectors Only Suppl 05000414/LER-2022-002, Indications Identified During Reactor Vessel Head Penetration Embedded Flaw Repair Surface Examination2022-12-0606 December 2022 Indications Identified During Reactor Vessel Head Penetration Embedded Flaw Repair Surface Examination ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 2024-09-05
[Table view] Category:Safety Evaluation
MONTHYEARML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 ML24017A0652024-03-0808 March 2024 Issuance of Amendment Nos. 319 and 315 to Technical Specification 3.7.11, Control Room Area Chill Water System (Cracws) ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 ML22242A0022022-09-12012 September 2022 Issuance of Amendments to Adopt TSTF 569, Revision 2, Revise Response Time Testing Definition ML22213A2532022-08-31031 August 2022 Authorization and Safety Evaluation for Alternative Request RA-21-0144 to Use Reactor Vessel Head Penetration Embedded Flaw Repair Method ML22164A0362022-07-19019 July 2022 Mcguire Nuclear Station, Units 1 and 2; Issuance of Amendments to Revise the Conditional Exemption of the End-Of-Cycle Moderator Temperature Coefficient Measurement Methodology (EPID L-2021-LLA-0198) Public ML22046A0222022-06-14014 June 2022 Issuance of Amendments to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO ML22010A2812022-03-0404 March 2022 Issuance of Amendments to Adopt TSTF-577, Rev. 1 Revised Frequencies for Steam Generator Tube Inspections (EPID L-2021-LLA-0161 ML22007A3452022-01-11011 January 2022 Proposed Alternative to Use the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Case N-885 ML21266A0112021-10-0505 October 2021 Staff Evaluation Related to Aging Management Program and Inspection Plan of Reactor Vessel Internals Per MRP-227, Revision 1-A ML21253A0822021-09-20020 September 2021 Proposed Alternative Request RA-21-0145 to Use Reactor Vessel Head Penetration Embedded Flaw Repair Method ML21155A2132021-08-26026 August 2021 Plant ML21131A0262021-06-23023 June 2021 Issuance of Amendments to Change Technical Specification 3.8.1, to Reduce Emergency Diesel Generator Maximum Voltage ML21113A0132021-05-0606 May 2021 Request for Use of a Later Edition of ASME Boiler and Pressure Vessel Code, Section XI for Repair and Replacement Activities ML21029A3352021-02-16016 February 2021 Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML20300A2062020-11-0909 November 2020 Duke Fleet - Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML20258A2712020-09-21021 September 2020 Correction Letter to Amendment Nos. 301, 329, 307, 303, 178, 317, 296, 416, 418, 417, and 268 ML20083F9272020-08-12012 August 2020 Issuance of Amendments to Relocate the Unit/Facility/Plant Staff Qualification Requirements to the Duke Energy Quality Assurance Program Description ML20174A0452020-08-0404 August 2020 Issuance of Amendment No. 306 to Revise Technical Specification 3.4.3, RCS (Reactor Coolant System) Pressure and Temperature (P/T) Limits ML19296D1192020-01-31031 January 2020 Issuance of Amendment Nos. 305 and 301 to Revise Technical Specification 3.0, Surveillance Requirement (SR) Applicability ML19254A6202019-09-17017 September 2019 Duke Energy Fleet (Brunswick, Catawba, Robinson, McGuire, Oconee, and Shearon Harris) - Alternative to Use Encoded Phased Array Ultrasonic Examination in Lieu of Radiography ML19212A6552019-08-27027 August 2019 Issuance of Amendment Nos. 304 and 300 to Technical Specification 3.8.1, AC Sources - Operating ML19191A0612019-07-15015 July 2019 Review of the Steam Generator Tube Inservice Inspection Report for the Fall 2018 Refueling Outage 24 ML19058A6322019-07-0101 July 2019 Issuance of Amendments to Revise Emergency Action Level Schemes to Incorporate Clarifications Provided by Emergency Preparedness FAQs ML19128A3262019-06-20020 June 2019 Alternative to Depth Sizing Qualification Examination of Welds ML19121A5512019-06-17017 June 2019 Issuance of Amendments Related to the Removal of Containment Valve Injection Water System Supply from Specified Containment Isolation Valves ML19050A2972019-04-18018 April 2019 McGuire Nuclear Station, Units 1 and 2, Shearon Harris Nuclear Power Plant, Unit 1, H B. Robinson Steam Electric Plant, Unit 2 - Issuance of Amendments Regarding Removal ML18275A2782018-11-28028 November 2018 Issuance of Amendments Related to the Nuclear Service Water System New Condition for Single Pond Return Header Configuration ML18172A1722018-08-15015 August 2018 Issuance of Amendments to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application ML18016A1782018-01-24024 January 2018 Request for Relief No. 17-CN-001, Regarding Category B-J Pressure Retaining Welds for the Third 10-Year Inservice Testing Interval (CAC Nos. MF9807 and MF9808; EPID L-2017-LLA-0032) ML17296A2082018-01-0404 January 2018 Issuance of Amendments Adopting Technical Specifications Task Force Traveler TSTF-197-A, Revision 2 (CAC Nos. MF8971 & MF8972, EPID L-2016-LLA-0026) ML17331A0862017-12-26026 December 2017 Alternative to Inservice Inspection Regarding Reactor Pressure Vessel Threads ML17254A1442017-10-23023 October 2017 Issuance of Amendments Adopting Technical Specifications Task Force Traveler TSTF-352-A, Revision 1 (CAC Nos. MF8969 and MF8970; EPID L-2017-LLA-0031) ML17261B2902017-10-23023 October 2017 Issuance of Amendment Nos. 296 and 292, Adopt TSTF-142-A, Revision 0, Increase the Completion Time When the Core Reactivity Balance Is Not within Limit (CAC Nos. MF8962 and MF8963); EPID L-2017-LLA-0024 ML17257A2972017-10-23023 October 2017 Issuance of Amendment Nos. 295 and 291, Adoption of TSTF-340-A, Revision 3, Allow 7-Day Completion Time for a Turbine-Driven AFW Pump Inoperable (CAC Nos. MF8979 and MF8980; EPID L-2017-LLA-0043) ML17249A1352017-09-29029 September 2017 Issuance of Amendments Adopting Technical Specifications Task Force Travelers TSTF-349-A, Revision 1, TSTF-361-A, Revision 2, and TSTF-438-A, Revision 0 ML17188A3872017-08-21021 August 2017 Issuance of Amendments Regarding Application to Consolidate Emergency Operations Facilities and Associated Emergency Plan Changes (CAC Nos. MF7650 Through MF7660) ML17172A4282017-07-26026 July 2017 Issuance of Amendments Adopting Technical Specification Task Force Traveler TSTF-315-A, Revision 0 ML17165A4412017-07-21021 July 2017 Issuance of Amendments Adopting Technical Specification Task Force Traveler TSTF-269-A, Revision 2 (CAC Nos. MF8983 and MF8984). 08/10/2017 ML17055A6472017-05-0808 May 2017 Brunswick, Catawba, McGuire, Shearon Harris, and H. B. Robinson - Issuance of Amendments to Revise Technical Specifications to Adopt TSTF-522, Revision 0 (CAC Nos. MF8422, MF8423, MF8424, MF8425, MF8426, MF8427, MF8428, and MF8429) ML17066A3742017-04-26026 April 2017 Issuance of Amendments Re. Application to Revise TSs to Adopt TSTF-427, Rev. 2, Using the Consolidated Line Item Improvement Process (CAC Nos. MF8039 Through MF8049) ML16137A3082017-02-0808 February 2017 Issuance of Amendments Regarding National Fire Protection Association Standard NFPA 805 ML16277A4042016-10-20020 October 2016 Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 ML16208A2832016-08-0808 August 2016 Correction to Issuance of Amendments Regarding Use of Optimized Zirlo ML16159A3362016-07-19019 July 2016 Issuance of Amendments Regarding Request to Use an Alternate Fission Gas Gap Release Fraction (CAC Nos. MF6480 Through MF6486) 2024-07-12
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 4, 2009 Mr. J. R. Morris Site Vice President Catawba Nuclear Station Duke Energy Carolinas, LLC 4800 Concord Road York, SC 29745
SUBJECT:
CATAWBA NUCLEAR STATION, UNITS 1 AND 2, EVALUATION OF AMENDMENT 36 TO TOPICAL REPORT ON QUALITY ASSURANCE PROGRAM (TAC NOS. MD9675 AND MD9676)
Dear Mr. Morris:
By letter dated September 18, 2008, Duke Energy Carolinas, LLC (the licensee), submitted Amendment 36 to Topical Report, "Duke-1-A, Quality Assurance Program," as it pertains to the Catawba Nuclear Station, Units 1 and 2.
The U.S. Nuclear Regulatory Commission (NRC) staff has completed its review of the changes and concludes that all the proposed changes are acceptable. The NRC staff's safety evaluation is enclosed.
If you have any questions, please call me at 301-415-1345.
Sincerely,
~~
John Stang, Senior Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-413 and 50-414
Enclosure:
As stated cc w/encl: Distribution via Listserv
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT 36 TO TOPICAL REPORT "DUKE-1-A, QUALITY ASSURANCE PROGRAM" DUKE ENERGY CAROLINAS, LLC CATAWBA NUCLEAR STATION, UNITS 1 AND 2 DOCKET NOS. 50-413 AND 50-414
1.0 INTRODUCTION
By letter dated September 18, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML082670356), Duke Energy Carolinas, LLC (the licensee), submitted Amendment 36 to the Quality Assurance (QA) Topical Report, "Duke A, Quality Assurance Program." The proposed amendment includes organizational changes, administrative, clarification and editorial changes, and a request for a QA program change previously approved by a U.S. Nuclear Regulatory Commission (NRC) safety evaluation.
The licensee's QA Program Amendment 36 delineates four changes: organizational changes; elimination of the Independent Safety Engineering Group (ISEG) Function; administrative improvements and clarifications, spelling corrections, punctuation or editorial changes; and organizational changes outside the quality organization.
The organizational and title changes related to QA functions outside the quality organization ensure that persons and organizations performing QA functions continue to have the requisite authority and organizational freedom, including sufficient independence from cost and schedule when opposed to safety considerations. Additionally, the licensee made changes considered as administrative improvements and clarifications, punctuation or editorial items.
The licensee also proposes the elimination of the Independent Safety Engineering Group (ISEG) function. According to the licensee, since the creation of the ISEG organization in the early 1980s, other onsite organizations and processes have matured such that they essentially implement the ISEG functions. These processes include a mature operating experience program, an effective corrective action program, and monitoring of system and component health. The ISEG function will be replaced at each site by the Independent Nuclear Oversight Section (INOS) - Performance Group.
Enclosure
-2 2.0 REGULATORY AND TECHNICAL EVALUATION NUREG 0737, item I.B.1.2 provides guidance for establishment of the onsite ISEG to perform independent reviews of plant operations. The principal function of the ISEG was to examine plant operating characteristics, NRC issuances, licensing information service advisories, and other appropriate sources of plant design and operating experience information that may indicate areas for improving plant safety. Since creation of ISEG organizations in the early 1980s, the licensee has developed and implemented alternate programs and processes that essentially duplicate ISEG functional responsibilities. The licensee will replace the ISEG function at each site with the INOS - Performance Group.
This group will conduct assessments and observations of specific plant operations, processes and records on the basis of their impact and importance relative to safety, reliability and functionality with respect to risk and consequences.
The NRC staff previously received and approved a similar proposal to eliminate the ISEG function from the Tennessee Valley Authority (TVA) Quality Assurance Program on August 26, 1999 (ADAMS Accession No. ML082350974). In the 1999 submittal from TVA, the licensee proposed transferring the responsibility for independent technical review to the site engineering organizations. TVA stated that ISEG functions had become redundant, in that they were accomplished by alternate means and groups at the sites. The NRC staff concluded that the proposed transfer of responsibility for independent technical reviews to the engineering organizations was acceptable.
Based on review of the proposed amendment to the QA Topical Report for Duke Energy Carolinas, LLC, the staff concludes that the licensee's program for operational reviews is consistent with the guidance of ANSI 18.7-1976 and applicable regulatory requirements.
3.0 CONCLUSION
The NRC staff finds that the proposed change with respect to ISEG is acceptable in that the ISEG functions will still be covered by other onsite organizations and processes.
Additionally, the ISEG function will be replaced by the INOS - Performance group which will conduct assessments, observations or surveillances of specific plant operations activities, and processes on the basis of their impact and importance relative to safety. The NRC staff determined that the licensee's QA program continues to satisfy the requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, applicable regulations and regulatory guidance.
The licensee's additional proposed changes (organizational changes, administrative clarification and editorial changes) were evaluated and the NRC staff 'finds that these changes were not a reduction in commitment in accordance with the guidance contained in NRC regulation 10CFR50.54(a)(3).
Principal Contributor: C. Roguecruz Date: Augu st 4, 2009
- .. ML092080516 NRR-106 *Memo from Tech Staff dated 2/10109 OFFICE NRRlLPL2-1/PM NRRlLPL4/LA NRRlEQVB/BC NRRlLPL2-1/ABC NRRlLPL2-1/PM JStang:art JStang NAME (JThompson for) MO'Brien DThatcher* UShoop (JThompson for)
DATE 8/3/09 8/3/09 2/10109 8/4109 8/3/09