E-mail from T. Ohara of USNRC to J. Richmond of USNRC, Regarding Oyster Creek Drywell Inspection
ML091460615
Person / Time
Site: Oyster Creek
Issue date: 08/12/2008
From: O'Hara T
NRC Region 1
To: Richmond J
NRC Region 1
References
FOIA/PA-2009-0070
Download: ML091460615 (5)


Text

' John Richmond From:

Timothy OHara Sent:

Tuesday, August 12, 2008 6:11 PM To:

John Richmond Cc:

John White

Subject:

RE: Oyster Creek Drywell Inspection

John, Tuesday, 8/19, at 3:00 PM will be fine. Just email the number when you get it.

Tim OHara From: John Richmond Sent: Tuesday, August 12, 2008 3:03 PM To: Timothy OHara

Subject:

RE: Oyster Creek Drywell Inspection Can you support a conference call with Oyster Creek, next Tuesday (Aug 19) at 3 pm??

Contact will be Pete Tamburro [609-971-4141]. Pete remembers you.

I will get a bridge line for us.

PS: Pete said their outage has slipped by 4-days from the previous schedule that he send me, and the Cschedule duration of only 2 days, for all of the drywell liner ISI work was unrealistic, and will need to bJ J*i.etched out over a longer time period.

Thanks From: Timothy OHara Sent: Monday, August 11, 2008 3:30 PM To: John Richmond Cc: John White; Richard Conte

Subject:

RE: Oyster Creek Drywell Inspection

John, he external drywell UT measurements are essential to compare with the readings taken in 2006. They will need to match up the exact locations from 2006 (which they marked), take thickness readings with UT and compare to the same locations. This is as important as the 19 UT reading locations inside containmenI Also, do they plan on removing any concrete grout inside the two trenches to look for evidence of water?

If you let me know the conference number I could call into the discussion next week. I'll be at Salem part of the week, but can arrange to call in. I'd prefer to listen and participate. A copy of their inspection procedures for these efforts would be good to review also.

Thanks.

Tim OHara 1/

From: John Richmond Sent: Monday, August 11, 2008 12:21 PM To: Timothy OHara Cc: John White; Richard Conte

Subject:

RE: Oyster Creek Drywell Inspection

Tim, their outage schedule is preliminary. As such, it's subject to change without notice, but outage schedules tend to not change vert much.

For Drywell Bay access, their schedule shows re-installation of bay shield bags and floor plugs within 1 to 2 days after their ISI VT & UT of the Bay is done. So, I would have to say that the Bays would probably not be accessable by Nov 2 or 4.

The schedule does show an ROV Video activity for the Bays, about a day prior to the ISI activities.

When you sak about "external drywell UT" do you mean from the sand bed area?

I plan to have a call with OC next week, to get more details of scope and schedule, so any additional questions or comments you have, will only help me better the right info from them.

Thanks From: Timothy OHara Sent: Monday, August 11, 2008 10:33 AM To: John Richmond Cc: John White; Richard Conte

Subject:

RE: Oyster Creek Drywell Inspection

John, Please see my comments below:

Tim OHara From: John Richmond Sent: Thursday, August 07, 2008 3:19 PM To: Timothy OHara

Subject:

Oyster Creek Drywell Inspection Tim, for the 00 License Renewal Outage Inspection, here's their schedule for drywell liner work.

1) Can you still support the 00 inspection on Oct 28-29?

This conflicts with Salem but can be worked out. How firm do you think this schedule is? Can all the bays be available for our inspection on 11/2 & 11/3?

2) Is there anything noticeably missing from their work list?

Where are the external drywell UT measurements? (I think this is important to our position.) Are they plannina pn video taping the Bay visual inspections? When will they complete VT data sheets for the Bays?

,3) Is there a particular Sand Bed Bay of greater interest to focus on?

2

I would say, at least, the Bays (3, I think) we looked at during the 2006 inspection. I'd have to go back and Idok at the Inspection Report to be sure which ones they were.

Drywell Liner UT in Sand Bed Region from Inside Drywell at 19 Locations (SP-1302-12-261)

Oct 28, 0900 Upper Drywell Liner UT Inspection Oct 28, 2200 Inspect Drywell Exterior Service Level II Coating in Sand Bed Bays Sorted by Date & Time Oct 28, 0900 Bay 3 VT Oct 28, 0900 Bay 5 UT Oct 28, 0900 Bay 7 VT Oct 28, 0900 Bay 9 VT Oct 28, 0900 Bay 11 VT Oct 28, 0900 Bay 19 VT Oct 28, 1400 Bay 3 UT Oct 28, 1400 Bay11 UT Oct 28, 1700 Bay 7 UT Oct 28, 1700 Bay 9 UT Oct 28, 1700 Bay 13 VT Oct 28, 1700 Bay 19 UT Oct 28, 1900 Bay 1 VT Oct 28, 1900 Bay 17 VT Oct 29, 0000 Bay 17 UT Oct 29, 0100 Bay 13 UT Oct 29, 0100 Bay 15 VT Oct 29, 0300 Bay 1 UT Oct 29, 0900 Bay 15 UT Nov 2, 0400 Bay 5 VT Inspect Drywell Exterior Service Level II Coating in Sand Bed Bays SAME as above but Sorted by Bay No.

Bay 1 VT Oct 28, 1900 Bay 1 UT Oct 29, 0300 Bay 3 VT Oct 28, 0900 Bay 3 UT Oct 28, 1400 Bay 5 UT Oct 28, 0900 [schedule shows UT as occurring 1st]

Bay 5 VT Nov 2, 0400 Bay 7 VT Oct 28, 0900 Bay 7 UT Oct 28, 1700 Bay 9 VT Oct 28, 0900 Bay 9 UT Oct 28, 1700 Bay 11 VT Oct 28, 0900 Bay 11 ULT Oct 28, 1400 Bay 13 VT Oct 28, 1700 Bay 13 UT Oct 29, 0100 Bay 15 VT Oct29, 0100 Bay 15 UT Oct 29, 0900 Bay 17 VT Oct 28, 1900 Bay 17 UT Oct 29, 0000 Bay 19 VT Oct 28, 0900 3

'Bay 16 UT Oct 28, 1700 4

lif Received: from RICLSTR01.nrc.gov ([148.184.99.7]) by R1 MS01.nrc.gov (Q148.184.99.10]) with mapi; Tue, 12 Aug 2008 18:11:11 -0400 Content-Type: application/ms-tnef; name="winmail.dat" Content-Transfer-Encoding: binary From: Timothy OHara <Timothy.OHara@nrc.gov>

To: John Richmond <John.Richmond@nrc.gov>

CC: John White <John.White@nrc.gov>

Date: Tue, 12 Aug 2008 18:11:10 -0400

Subject:

RE: Oyster Creek Drywell Inspection Thread-Topic: Oyster Creek Drywell Inspection Thread-Index: Acj4wnni4ShS+ndjSL+kljyVcLy+LgC+3/VAAAN/dSOABup20AAxZf7gAAa7ZbA=

Message-ID: <2856BC46F6A308418F033D973BBOEE72841C89E6EF@R1CLSTR01.nrc.gov>

References:

<2856BC46F6A308418F033D973BBOEE72841 CBEOCD5@R1 CLSTR01. nrc.gov>,<2856BC46 F6A308418F033D973BBOEE72841 CBE1 4FF@R1 CLSTRO1.nrc.gov>

<2856BC46F6A308418F033D973BBOEE72841 CCA2F3C@R1 CLSTRO1. nrc.gov>

<2856BC46F6A308418F033D973BBOEE72841 CCA04C7@R1 CLSTRO1. nrc.gov>

<2856BC46F6A308418F033D973BBOEE72841 CCAOA4E@R1 CLSTR01. nrc.gov>.

In-Reply-To: <2856BC46F6A308418F033D973BBOEE72841CCAOA4E@R1 CLSTR01.nrc.gov>

Accept-Language: en-US Content-Language: en-US X-MS-Has-Attach:

X-MS-Exchange-Organization-SCL: -1 X-MS-TNEF-Correlator:

<2856BC46F6A308418F033D973BBOEE72841 C89E6EF@R1 CLSTR01.nrc.gov>

MIME-Version: 1.0