UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 May 14, 2009 LICENSEE: NextEra Energy Point Beach, LLC FACILITY: Point Beach Nuclear Plant

SUBJECT:

SUMMARY

OF THE APRIL 29, 2009, PUBLIC MEETING TO DISCUSS THE 2008 POINT BEACH END-OF-CYCLE PERFORMANCE ASSESSMENT On April 29, 2009, the Nuclear Regulatory Commission (NRC) held a public meeting at the Two Creeks Town Hall in Two Creeks, Wisconsin. The meeting was between NRC Region III management and NextEra Energy Point Beach, LLC representatives to discuss the NRCs 2008 End-of-Cycle Assessment of the Point Beach Nuclear Plants safety performance. The results of that assessment were discussed in a letter to the licensee dated March 4, 2009, (ADAMS ML090630351).

The NRC began the meeting with an overview of the NRC, the NRCs Reactor Oversight Process (ROP), national ROP results, and the Action Matrix. This was followed by a summary of the NRCs assessment of Point Beach performance in 2008. The NRCs meeting presentation slides can be found in ADAMS at ML091200734. A list of principal meeting attendees can be found in the attached Enclosure.

Following the NRCs presentation, the licensee discussed its efforts to make sustained improvements in its longstanding substantive cross-cutting issues in the human performance and problem identification and resolution areas. In addition, the licensee briefly spoke on its efforts taken in response to a nuclear safety culture survey conducted in 2008. The licensees presentation slides can be found in ADAMS at ML091200704.

L. Meyer At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials.

/RA/

Michael A. Kunowski, Chief Branch 5 Division of Reactor Projects Docket Nos. 50-266; 50-301;72-005 License Nos. DPR-24; DPR-27

Enclosure:

As stated DISTRIBUTION:

See next page

Letter to L. Meyer from M. Kunowski dated May 14, 2009

SUBJECT:

SUMMARY

OF THE APRIL 29, 2009, PUBLIC MEETING TO DISCUSS THE 2008 POINT BEACH END-OF-CYCLE PERFORMANCE ASSESSMENT cc w/encl: M. Nazar, Senior Vice-President and Chief Nuclear Officer A. Khanpour, Vice-President, Engineering Support Licensing Manager, Point Beach Nuclear Plant M. Warner, Vice-President, Nuclear Plant Support M. Ross, Managing Attorney A. Fernandez, Senior Attorney T. O. Jones, Vice-President, Nuclear Operations Mid-West Region P. Wells, Vice-President, Nuclear Safety Assessment J. Bjorseth, Plant General Manager R. Hughes, Director, Licensing and Performance Improvement K. Duveneck, Town Chairman Town of Two Creeks Chairperson Public Service Commission of Wisconsin J. Kitsembel, Electric Division Public Service Commission of Wisconsin P. Schmidt, State Liaison Officer Chairman, Manitowoc County Board County Executive, Manitowoc Director, Manitowoc County Emergency Management Agency Chairman, Kewaunee County Board Mayor of Kewaunee City Manager, Two Rivers Director, Kewaunee County Emergency Management Agency President, Village of Mishicot Chairman, Village of Two Creeks G. Mortensen, INPO

L. Meyer At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials.

/RA/

Michael A. Kunowski, Chief Branch 5 Division of Reactor Projects Docket Nos. 50-266; 50-301;72-005 License Nos. DPR-24; DPR-27

Enclosure:

As stated DISTRIBUTION:

See next page DOCUMENT NAME: G:\1-Secy\1-Work In Progress\PTBH Summary Letter 04-29-09.doc G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" =

Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME MKunowski:cms DATE 05/14/09 OFFICIAL RECORD COPY

Letter to L. Meyer from M. Kunowski dated May 14, 2009

SUBJECT:

SUMMARY

OF THE APRIL 29, 2009, PUBLIC MEETING TO DISCUSS THE 2008 POINT BEACH END-OF-CYCLE PERFORMANCE ASSESSMENT DISTRIBUTION:

Tamara Bloomer RidsNrrDorlLpl3-1 RidsNrrPMPointBeach RidsNrrDirslpab Resource Patrick Hiland Kenneth Obrien Jared Heck Allan Barker DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports Resource

PUBLIC MEETING PRINCIPAL ATTENDEES April 29, 2009 NextEra Energy Point Beach T. Jones, Corporate Vice-President, Operations Midwest L. Meyer, Site Vice-President J. Bjorseth, Plant Manager T. Vehec, Maintenance Manager R. Harrsch, Operations Manager B. Castiglia, Performance Manager J. Costedio, Licensing Manager Nuclear Regulatory Commission M. Kunowski, Branch Chief, Division of Reactor Projects J. Jandovitz, Senior Resident Inspector, Point Beach R. Ruiz, Resident Inspector, Point Beach K. Barclay, Resident Inspector, Kewaunee P. Chandrathil, Public Affairs Officer A. Becker, Resident Office Assistant, Point Beach and Kewaunee Other Attendees N. Crowley, Emergency Management Director, Manitowoc County Enclosure