RAI for SER - RAI Letter No. 045, Related to Part 1 General and Financial Information of the Virgil C. Summer Nuclear Station Units 2 and 3 Cola
ML091160005
Person / Time
Site: Summer  
Issue date: 04/26/2009
From: Sujata Goetz
Office of New Reactors
To: Paglia A
South Carolina Electric & Gas Co
References
Download: ML091160005 (6)


Text

1 SummerRAIsPEm Resource From:

Sujata Goetz Sent:

Sunday, April 26, 2009 12:50 PM To:

SummerRAIsPEm Resource

Subject:

RAI letter NO. 045, RELATED TO PART 1 GENERAL AND FINANCIAL INFORMATION OF THE VIRGIL C. SUMMER NUCLEAR STATION UNITS 2 AND 3 COLA Attachments:

Sum-RAI-LTR-045.doc

Hearing Identifier:

Summer_COL_eRAIs Email Number:

48 Mail Envelope Properties (83F82891AF9D774FBBB39974B6CB134F92A78B99CB)

Subject:

RAI letter NO. 045, RELATED TO PART 1 GENERAL AND FINANCIAL INFORMATION OF THE VIRGIL C. SUMMER NUCLEAR STATION UNITS 2 AND 3 COLA Sent Date:

4/26/2009 12:49:51 PM Received Date:

4/26/2009 12:49:52 PM From:

Sujata Goetz Created By:

Sujata.Goetz@nrc.gov Recipients:

"SummerRAIsPEm Resource" <SummerRAIsPEm.Resource@nrc.gov>

Tracking Status: None Post Office:

HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 8

4/26/2009 12:49:52 PM Sum-RAI-LTR-045.doc 50682 Options Priority:

Standard Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date:

Recipients Received:

April 27, 2009 Alfred M. Paglia Manager, Nuclear Licensing MC P40 South Carolina Electric & Gas Company PO Box 88 Jenkinsville, SC 29065

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION LETTER NO. 045, RELATED TO PART 1 GENERAL AND FINANCIAL INFORMATION OF THE VIRGIL C.

SUMMER NUCLEAR STATION UNITS 2 AND 3 COMBINED LICENSE APPLICATION

Dear Mr. Paglia:

By letter dated March 27, 2008, South Carolina Electric & Gas Company submitted its application to the U. S. Nuclear Regulatory Commission (NRC) for a combined license (COL) for two AP1000 advance passive pressurized water reactors pursuant to 10 CFR Part 52. The NRC staff is performing a detailed review of this application to enable the staff to reach a conclusion on the safety of the proposed application.

The NRC staff has identified that additional information is needed to continue portions of the review. The staffs request for additional information (RAI) is contained in the enclosure to this letter.

To support the review schedule, you are requested to respond within 30 days of the date of this letter. If changes are needed to the final safety analysis report, the staff requests that the RAI response include the proposed wording changes.

If you have any questions or comments concerning this matter, you may contact me at 301-415-8004 or you may contact Ravindra Joshi, the lead project manager for the Summer combined license at 301-415-6191.

Sincerely,

/RA/

Sujata Goetz, Project Manager AP1000 Projects Branch 1 Division of New Reactor Licensing Office of New Reactors Docket Nos.52-027 52-028

Enclosure:

Request for Additional Information CC: see next page

If you have any questions or comments concerning this matter, you may contact me at 301-415-8004 or you may contact Ravindra Joshi, the lead project manager for the Harris combined license at 301-415-6191.

Sincerely,

/RA/

Sujata Goetz, Project Manager AP1000 Projects Branch 1 Division of New Reactor Licensing Office of New Reactors Docket Nos.52-027 52-028 eRAI Tracking No. 2557

Enclosure:

Request for Additional Information Distribution:

Public BHughes SHaggerty SGoetz RidsNroDnrlNwe1 SCoffin MComar CAraguas RidsNroLAKGoldstein TSimms JSebrosky ASzabo RidsOgcMailCenter BAnderson RJoshi RidsAcrsAcnwMailCenter RidsRgn2MailCenter LGoldin NRO-002 OFFICE NWE1/BC NWE1/PM OGC NWE1/L-PM NAME SCoffin

  • SGoetz LGoldin RJoshi*

DATE 4/7/09 4/7/09 4/13/09 4/13/09

  • Approval captured electronically in the electronic RAI system.

OFFICIAL RECORD COPY

Request for Additional Information Virgil C. Summer Nuclear Station, Units 2 and 3 South Carolina Electric and Gas Company Docket No.52-027 and 52-028 SRP Section: 01 - Introduction and Interfaces Application Section: Part 1 General and financial Information QUESTIONS for AP1000 Projects Branch 1 (NWE1) 01-3 In section 1.3.3.2 of the Summer COL application, the applicant states that they will be using an external sinking fund to decommission the facility. However the applicant does not state whether they will provide certification within 30 days after the Commission publishes a notice in the Federal Register as required by 10 CFR 50.75(b) (1), which states that:

[....] For an applicant for a combined license under subpart C of 10 CFR part 52, the report must contain a certification that financial assurance for decommissioning will be provided no later than 30 days after the Commission publishes notice in the Federal Register under § 52.103(a) in an amount which may be more, but not less, than the amount stated in the table in paragraph (c)(1) of this section, adjusted using a rate at least equal to that stated in paragraph (c)(2) of this section.

Please specify that this certification information will be provided.