ML091030172

From kanterella
Jump to navigation Jump to search
External Flooding Briefing for Commissioner Jaczko
ML091030172
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 04/09/2009
From: Boland A, Galloway M, David Skeen
Division of Engineering, NRC/NRR/DRA, NRC/RGN-III
To:
David Skeen, NRR/DE 415-3298
References
FOIA/PA-2013-0213
Download: ML091030172 (10)


Text

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION Oconee External Flooding Briefing for Commissioner Jaczko David Skeen Melanie Galloway Anne Boland April 9, 2009 ML091030172 OFFICIAL USE ONLY - SECURITY RELATED INFORMATION

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION Jocassee Dam Flood Scenario Lake Jocassee

~385-ft Oconee Site ML091030172 OFFICIAL USE ONLY - SECURITY RELATED INFORMATION 2

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION Jocassee Dam ML091030172 OFFICIAL USE ONLY - SECURITY RELATED INFORMATION 3

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION Oconee Nuclear Station Standby Sh tdo n Shutdown Facility ML091030172 OFFICIAL USE ONLY - SECURITY RELATED INFORMATION 4

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION Overview

  • The staff issued a 50.54(f) letter to Duke on August 15, 2008, requesting information regarding external flooding hazards at the Oconee facility. The letter was issued because:

- The Oconee Standby Shutdown Facility (SSF) contains the only equipment left to cool the core, containment and spent fuel pool, if all other safety-related and non-safety-related equipment are lost in the predicted worst-case external flood.

- The SSF 5-ft high flood barrier protects against Dukes licensing basis flood of 4.7 feet. Dukes licensing basis calculations, performed in the early 1980s, have been lost and Duke has not reproduced them them.

- The only flooding analysis available was one conducted by Duke in the mid-1990s which predicted onsite flood heights from approximately 12 to 17 feet. The analysis was performed for FERC emergency planning purposes, using one dimensional inundation codes, and the conservatism of the modeling is uncertain.

- In 2007, the staff was evaluating an inspection finding regarding an SSF flood barrier breach, and identified that Oconees IPEEE frequency for sunny day, or random, failure of the Jocassee dam was non-conservative by an order of magnitude, and could increase the core damage frequency from external flooding to 2E-04/yr.

ML091030172 OFFICIAL USE ONLY - SECURITY RELATED INFORMATION 5

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION Dukes Response

  • Duke committed to the following actions in its September 26, 2008 response

- Short term

  • Increase the height of the SSF flood barriers from 5-ft to 7.5-ft (Completed - 03/09)
  • Create interim guidance to mitigate postulated floods that may render the SSF inoperable (Completed 03/09)
  • Update the 1992 inundation study using a more advanced computer model (HEC-RAS),

developed by DoD and the Corp of Engineers (Completed 04/09). The updated study used the same parameters as the 1992 study, and varied some parameters to provide a sensitivity study

- Long Term

  • Contract with Utah State to perform a study of the Jocassee dam to determine the probability of potential failure modes, and assess potential adverse effects to the SSF.

Incorporate this information into a flooding evaluation using the HEC-RAS model to determine the appropriate flood height at the SSF (Expected completion date 02/10)

ML091030172 OFFICIAL USE ONLY - SECURITY RELATED INFORMATION 6

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION SSF South Wall Modification The SSF walls were extended by 2.5 ft to provide added flood protection ML091030172 OFFICIAL USE ONLY - SECURITY RELATED INFORMATION 7

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION Basis for Continued Operation

  • Estimated frequency of dam failure is low.

- No adverse trends in dam condition noted by FERC inspections.

- Licensee performs regular inspections and monitoring off th the d dam, as wellll as periodic i di surveillance ill off th the spillway gates.

- Present level of the Jocassee Lake is very low.

  • Timing of core damage scenarios allows time for mitigative measures.

ML091030172 OFFICIAL USE ONLY - SECURITY RELATED INFORMATION 8

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION Staff Concerns

  • The staff has reviewed Dukes proposed risk-informed approach to address flood height at the SSF.
  • The staff has concluded risk analysis cannot be used to demonstrate compliance with deterministic flooding safety requirements, unless the risk analysis reveals that the failure is not credible.
  • The staff and licensee agree that dam failure is a credible event.
  • The staff has requested additional data in conjunction with the licensees inundation studyy to ensure adequateq protection p of the p public health and safety. Key issues are:

- Breach size

- Lake level (Jocassee and Keowee)

- Time to dam failure

- Sensitivity analysis ML091030172 OFFICIAL USE ONLY - SECURITY RELATED INFORMATION 9

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION Path Forward

  • The staff is issuing a follow-up letter to Duke to let them know that NRC has found their risk analysis plan unacceptable to demonstrate compliance.
  • The follow-up letter also establishes NRCs expectation that the licensee perform an adequate inundation study and technically defend the assumptions and parameters used in the study.
  • The staff will meet again with Duke in May 2009 to allow the licensee to explain how the new inundation analysis code was benchmarked against the 1992 study and how the limited sensitivity analysis was performed.
  • The staff will use in-house and independent expertise to provide insights on the study.
  • If the staff determines that the study is inadequate, further regulatory action will be taken.
  • An SES manager has filed a non-concurrence on the letter to Duke.

ML091030172 OFFICIAL USE ONLY - SECURITY RELATED INFORMATION 10