UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406-1415 March 19, 2009 MN No.09-009 U.S. NUCLEAR REGULATORY COMMISSION REGION I NOTICE OF LICENSEE MEETING Licensee:
Entergy Nuclear Operations, Inc.
Facility:
Vermont Yankee Nuclear Power Station Docket No.
50-271 Date and Time:
Annual Assessment Meeting: April 16, 2009, 3:30 p.m. - 5:30 p.m.
Town Hall Style Meeting: April 16, 2009, 7:00 p.m. - 9:30 p.m.
Location:
Ramada Hotel and Conference Center 1380 Putney Road Brattleboro, VT 05301
Purpose:
The NRC requested an Annual Assessment Meeting with Entergy to discuss the NRCs assessment of the safety performance of the Vermont Yankee Nuclear Power Station for calendar year 2008. The NRCs assessment is documented in a letter dated March 4, 2009. Time will be provided for questions related to the 2008 assessment of Vermont Yankee.
In addition, a Town Hall Style Meeting will be held in the evening to answer questions on the role of the NRC in ensuring safe plant operations. This meeting will be dedicated to answering questions from the public.
Attendees:
NRC:
D. Roberts, Director, Division of Reactor Safety D. Jackson, Chief, Projects Branch 5 M. Marshfield, Acting Senior Resident Inspector J. Kim, Vermont Yankee Project Manager Entergy:
M. Colomb, Site Vice President C. Wamser, General Manager of Plant Operations J. Dreyfuss, Director - Nuclear Safety Assurance N. Rademacher, Director - Engineering
2 Public Participation*: The Vermont Yankee Annual Assessment Meeting is a Category 1 Meeting. The public is invited to observe the meeting and will have opportunities to communicate with the NRC staff following the business portion, before the meeting is adjourned. Several NRC representatives will also be available for a Town Hall Style Meeting in the evening. The Town Hall Style Meeting is being provided to maximize discussion with the public to ensure that issues and concerns may be presented, understood, and considered by the NRC.
The NRCs Annual Assessment Letter for Vermont Yankee Nuclear Power Station can be located in ADAMS with Accession Number ML090630467. ADAMS is accessible from the NRC Web Site at: http://www.nrc.gov/reading-rm/adams.html.
Additional information relative to the NRC's Annual Assessment Process and the safety performance of Vermont Yankee Nuclear Power Station can be found on the NRC's web site at:
www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.
Meeting
Contact:
Donald E. Jackson, Chief, Projects Branch 5 (610) 337-5306 E-mail: donald.jackson@nrc.gov
- The NRC provides reasonable accommodation to individuals with disabilities where appropriate. If you need a reasonable accommodation to participate in this meeting, or need this meeting notice or the transcript or other information from the meeting in another format (e.g.
braille, large print), please notify the NRC meeting contact no later than 2 business days prior to the meeting. Attendance by NRC personnel at this meeting should be made known by April 14, 2009, via telephone to the NRC meeting contact.
Approved by:
/RA/ Original Signed By:
Donald E. Jackson, Chief Projects Branch 5 Division of Reactor Projects cc w/ encl:
Vice President, Operations, Entergy Nuclear Operations Senior Vice President, Entergy Nuclear Operations Vice President, Oversight, Entergy Nuclear Operations Senior Manager, Nuclear Safety & Licensing, Entergy Nuclear Operations Senior Vice President and COO, Entergy Nuclear Operations Assistant General Counsel, Entergy Nuclear Operations Manager, Licensing, Entergy Nuclear Operations Hon. Molly Kelly, New Hampshire Senate S. Lousteau, Treasury Department, Entergy Services, Inc.
D. O Dowd, Administrator, Radiological Health Section, DPHS, State of New Hampshire W. Irwin, Chief, CHP, Radiological Health, Vermont Department of Health Chief, Safety Unit, Office of the Attorney General, Commonwealth of Mass.
3 D. Lewis, Pillsbury, Winthrop, Shaw, Pittman LLP G. D. Bisbee, Esquire, Deputy Attorney General, Environmental Protection Bureau J. P. Matteau, Executive Director, Windham Regional Commission D. Katz, Citizens Awareness Network (CAN)
R. Shadis, New England Coalition Staff G. Sachs, President/Staff Person, c/o Stopthesale J. Volz, Chairman, Public Service Board, State of Vermont Chairman, Board of Selectman, Town of Vernon C. Pope, State of New Hampshire, SLO D. O'Brien, State of Vermont, SLO J. Giarrusso, SLO, MEMA, Commonwealth of Massachusetts J. Angil, II, Manager, Vermont Emergency Management Agency U. Vanags, State Nuclear Engineer, Vermont Department of Public Service J. Block, Esquire S. Shaw G. Edwards
4 Agendas NRCs Annual Assessment Meeting Vermont Yankee Nuclear Power Station April 16, 2009 3:30 - 5:30 p.m.
Introduction............................................................................................. NRC (5 minutes)
Review of Reactor Oversight Process.................................................... NRC (10 minutes)
Discussion of Vermont Yankee Performance.......................................... NRC (10 minutes)
Entergys Response and Remarks.................................................... Entergy (25 minutes)
Closing Remarks...................................................................................... NRC (5 minutes)
Short Break...................................................................................................... (5 minutes)
NRC to address public questions....................... NRC/Members of the Public (60 minutes)
NRCs Town Hall Style Meeting Vermont Yankee Nuclear Power Station April 16, 2009 7:00 - 9:30 p.m.
Introduction............................................................................................. NRC (5 minutes)
NRC to address public questions.......... NRC/Members of the Public (2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> 20 minutes)
Closing Remarks...................................................................................... NRC (5 minutes)
2 Public Participation*: The Vermont Yankee Annual Assessment Meeting is a Category 1 Meeting. The public is invited to observe the meeting and will have opportunities to communicate with the NRC staff following the business portion, before the meeting is adjourned. Several NRC representatives will also be available for a Town Hall Style Meeting in the evening. The Town Hall Style Meeting is being provided to maximize discussion with the public to ensure that issues and concerns may be presented, understood, and considered by the NRC.
The NRCs Annual Assessment Letter for Vermont Yankee Nuclear Power Station can be located in ADAMS with Accession Number ML090630467. ADAMS is accessible from the NRC Web Site at: http://www.nrc.gov/reading-rm/adams.html.
Additional information relative to the NRC's Annual Assessment Process and the safety performance of Vermont Yankee Nuclear Power Station can be found on the NRC's web site at:
www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.
Meeting
Contact:
Donald E. Jackson, Chief, Projects Branch 5 (610) 337-5306 E-mail: donald.jackson@nrc.gov
- The NRC provides reasonable accommodation to individuals with disabilities where appropriate. If you need a reasonable accommodation to participate in this meeting, or need this meeting notice or the transcript or other information from the meeting in another format (e.g.
braille, large print), please notify the NRC meeting contact no later than 2 business days prior to the meeting. Attendance by NRC personnel at this meeting should be made known by April 14, 2009, via telephone to the NRC meeting contact.
Approved by :
/RA/ Original Signed By:
Donald E. Jackson, Chief Projects Branch 5 Division of Reactor Projects Distribution:
See attached SUNSI Review Complete: jl (Reviewer=s Initials)
DOC NAME: G:\\DRP\\BRANCH5\\Annual Assessment Meetings\\2008 EOC\\Meeting Notices\\Vermont ROP 9 Annual Assessment Meeting Notice rev3.doc After declaring this document AAn Official Agency Record@ it will be released to the Public. ML090780293 To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP NAME JLillendahl/jl DJackson/dej DATE 03/18 /09 03/19/09 OFFICIAL RECORD COPY
3 Distribution: (Via E-Mail):
Executive Director for Operations, OEDO (RIDSEDOMAILCENTER RESOURCE)
Deputy Executive Director for Reactor Programs, OEDO (RIDSEDOMAILCENTER RESOURCE)
Director, Office of Nuclear Reactor Regulation, NRR (RIDSNRROD)
Deputy Director, Office of Nuclear Reactor Regulation, NRR/ADPR (RIDSNRROD)
Associate Director, Office of Operating Reactor Oversight and Licensing,NRR/ADRO (RIDSNRRADRO)
Director, Division of Inspection and Regional Support, NRR (RIDSNRRDIRS)
Director, Division of Operating Reactor Licensing, NRR/DORL (RIDSNRRDORL)
Project Directorate I-1 (PD1/2), NRR (RIDSNRRDORlLpl 1-2)
Asst. General Counsel Materials Litigation and Enforcement,OGC (RIDSOGCMAILCENTER RESOURCE)
S. Collins, RA M. Dapas, DRA D. Lew, DRP J. Clifford, DRP D. Roberts, DRS E. Cobey, DRS D. Jackson, DRP J. Lilliendahl, DRP A. Rao, DRP G. Newman, DRP D. Screnci, PAO N. Sheehan, PAO N. McNamara, SLO D. Tiffts, SLO M. Marshfield, DRP, SRI T. Setzer, DRP, Actg RI A. Rancourt, DRP, OA S. Campbell, RI, OEDO J. Lubinski, NRR M. Kowal, NRR J. Kim, PM, NRR J. Boska, PM, NRR J. Thompson, NRR G. Matakas, ORA DRS Div Secretary, RI DRP Div Secretary, RI R. Barkley, ORA RI Receptionist PMNS ROPreportsResource@nrc.gov Region I Docket Rm D. Bearde, DRP