NS Savannah Public Meeting March 11, 2009 1
Post-Shutdown Decommissioning Activities Report
Purpose:
- Discuss the NRC Decommissioning Process 2
- Discuss the NRC Inspection Process
- Discuss the Post Shutdown Decommissioning Activities Report (PSDAR) for the NS Savannah
- Hear public comments
NRC Decommissioning Process
- Permanently cease operations
- Certify permanent cessation of operations 3
- Certify fuel removed from reactor
- Submit PSDAR (within 2 years)
- SAFSTOR and/or plant decommissioning
- Application for license termination (LTP)
- License termination
PSDAR Requirements
- PSDAR describes:
4
- planned decommissioning activities
- decommissioning schedule
- cost estimate for the decommissioning, and
- environmental impacts of decommissioning
PSDAR Review Process
- NRC notices receipt of PSDAR &
requests public comments C
S 5
- NRC schedules PSDAR public meeting
- NRC considers public comments
- Review PSDAR in accordance with Regulatory Guide 1.185
- PSDAR does not require NRC approval
PSDAR Review Criteria
- Decom can be completed as described
- Decom can be completed within 60 years 6
- Decom can be completed for the estimated cost
- Decom activities do not endanger public health and safety or the environment
Decommissioning Activities
- Decom can not be performed within 90 days of PSDAR
- Decom cannot preclude unrestricted release of 7
- Decom cannot preclude unrestricted release of site
- Decom cannot result in significant environmental impacts not previously evaluated
- Decom cannot result in sufficient funds not being available for decommissioning
Conclusion
- NRC received a PSDAR for the Nuclear Ship Savannah on December 11, 2008 C
8
- NRC will consider the public comments in its review of the NS Savannah PSDAR
NRC Contacts
- John Buckley, Project Manager
- John.Buckley@nrc.gov
- 301-415-6607 9
- Margaret Bupp, Acting Branch Chief
- Margaret.Bupp@nrc.gov
- 301-415-3722
- Keith McConnell, Deputy Director
- Keith.McConnell@nrc.gov
- 301-415-7295