ML090720952

From kanterella
Jump to navigation Jump to search
Er 05000440-09-301(DRS), on 1/12/2009 - 1/21/2009, First Energy Corp., Perry Station Initial License Examination Report
ML090720952
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 03/12/2009
From: Hironori Peterson
Operations Branch III
To: Bezilla M
FirstEnergy Nuclear Operating Co
References
IR-09-301
Download: ML090720952 (32)


See also: IR 05000440/2009301

Text

March 12, 2009

Mr. Mark Bezilla

Site Vice President

FirstEnergy Nuclear Operating Company

Perry Nuclear Power Plant

P. O. Box 97, 10 Center Road, A-PY-A290

Perry, OH 44081-0097

SUBJECT: PERRY NUCLEAR POWER PLANT, UNIT 1

NRC INITIAL LICENSE EXAMINATION REPORT 05000440/2009301(DRS);

Dear Mr. Bezilla:

On February 27, 2009, the Nuclear Regulatory Commission (NRC) examiners completed initial

operator licensing examinations at your Perry Nuclear Power Plant. The enclosed report

documents the results of the examination which were discussed on January 16, 2009, with

Mr. A. Mueller Jr. and other members of your staff. An exit meeting was conducted by telephone

on March 4, 2009, between Mr. A. Mueller Jr. of your staff and Mr. Walton, of Operator

Licensing, to review the resolution of the station=s post examination comments and the proposed

final grading of the written examination for the license applicants.

The NRC examiners administered an initial license examination operating test during the week

of January 12, 2009. The written examination was administered by Perry Nuclear Power Plant

training department personnel on January 21, 2009. Eight Senior Reactor Operators and one

Reactor Operator applicant were administered license examinations. The results of the

examinations were finalized on February 27, 2009. All applicants passed all sections of their

respective examinations and seven were issued senior operator licenses and one was issued an

operator license. One senior operator license was withheld until the individual met experience

requirements.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and

its enclosure will be available electronically for public inspection in the NRC Public Document

Room, or from the Publicly Available Records (PARS) component of NRC's document system

(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html

(the Public Electronic Reading Room).

M. Bezilla -2-

We will gladly discuss any questions you have concerning this examination.

Sincerely,

/RA/

Hironori Peterson, Chief

Operations Branch

Division of Reactor Safety

Docket Nos. 50-440

License Nos. NPF-58

Enclosures: 1. Operator Licensing Examination

Report 05000440/2009301(DRS)

w/Attachment: Supplemental Information

2. Simulation Facility Report

3. Post Examination Comments w/NRC Resolution

4. Written Examinations and Answer

Keys (SRO)

cc w/encls 1 & 2: J. Hagan, President and Chief Nuclear Officer - FENOC

J. Lash, Senior Vice President of Operations and

Chief Operating Officer - FENOC

D. Pace, Senior Vice President, Fleet Engineering - FENOC

K. Fili, Vice President, Fleet Oversight - FENOC

P. Harden, Vice President, Nuclear Support

Director, Fleet Regulatory Affairs - FENOC

Manager, Fleet Licensing - FENOC

Manager, Site Regulatory Compliance - FENOC

D. Jenkins, Attorney, FirstEnergy Corp.

Public Utilities Commission of Ohio

C. OClaire, State Liaison Officer, Ohio Emergency Management Agency

R. Owen, Ohio Department of Health

cc w/encls 1, 2, 3, & 4: A. Mueller, Jr. Training Director, Perry Power Plant

M. Bezilla -2-

We will gladly discuss any questions you have concerning this examination.

Sincerely,

/RA/

Hironori Peterson, Chief

Operations Branch

Division of Reactor Safety

Docket Nos. 50-440

License Nos. NPF-58

Enclosures: 1. Operator Licensing Examination

Report 05000440/2009301(DRS)

w/Attachment: Supplemental Information

2. Simulation Facility Report

3. Post Examination Comments w/NRC Resolution

4. Written Examinations and Answer

Keys (SRO)

cc w/encls 1 & 2: J. Hagan, President and Chief Nuclear Officer - FENOC

J. Lash, Senior Vice President of Operations and

Chief Operating Officer - FENOC

D. Pace, Senior Vice President, Fleet Engineering - FENOC

K. Fili, Vice President, Fleet Oversight - FENOC

P. Harden, Vice President, Nuclear Support

Director, Fleet Regulatory Affairs - FENOC

Manager, Fleet Licensing - FENOC

Manager, Site Regulatory Compliance - FENOC

D. Jenkins, Attorney, FirstEnergy Corp.

Public Utilities Commission of Ohio

C. OClaire, State Liaison Officer, Ohio Emergency Management Agency

R. Owen, Ohio Department of Health

cc w/encls 1, 2, 3, & 4: A. Mueller, Jr. Training Director, Perry Power Plant

DISTRIBUTION:

RidsNrrPMPerry

RidsNrrDorlLpI3-2

RidsNrrDirsIrib Resource

Tamara Bloomer

Mark Satorius

Kenneth Obrien

Jared Heck

Carole Ariano

Linda Linn

Cynthia Pederson (hard copy - IRs only)

DRPIII

DRSIII

Patricia Buckley

Tammy Tomczak

ROPreports@nrc.gov

NLS

DOCUMENT NAME: G:\DRS\WORK IN PROGRESS\PER 2009 301 DRS OL.DOC

G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE RIII RIII

NAME KWalton:co HPeterson

DATE 03/06/09 03/12/09

OFFICIAL RECORD COPY

U. S. NUCLEAR REGULATORY COMMISSION

REGION III

Docket Nos: 50-440

License Nos: NPF-58

Report No: 05000440/2009301(DRS)

Licensee: First Energy Corporation

Facility: Perry Nuclear Power Plant, Unit 1

Location: Perry, Ohio

Dates: January 12 - January 21, 2009

Examiners: R. Walton, Senior Operations Engineer

D. Reeser, Operations Engineer

C. Zoia, Operations Engineer

Approved by: Hironori Peterson, Chief

Operations Branch

Division of Reactor Safety

Enclosure 1

SUMMARY OF FINDINGS

ER 05000440/2009301(DRS); 1/12/2009 - 1/21/2009; First Energy Corp., Perry Station Initial

License Examination Report.

The announced initial operator licensing examination was conducted by regional Nuclear

Regulatory Commission examiners in accordance with the guidance of NUREG-1021, AOperator

Licensing Examination Standards for Power Reactors,@ Revision 9.

Examination Summary:

$ Nine of nine applicants passed all sections of their respective examinations. Seven

applicants were issued senior operator licenses and one applicant was issued an

operator license. One senior operator will be issued a license after experience

conditions have been met (Section 4OA5.1).

  • The examiners identified that the licensee used software that incorporated two-phase

fluid flow for modeling feedwater in the Perry simulator. This software has been used in

some but not all BWR simulators. This condition is an unresolved item pending further

review by the NRC (Enclosure 2).

1 Enclosure 1

REPORT DETAILS

4. OTHER ACTIVITIES (OA)

4OA5 Other

.1 Initial Licensing Examinations

a. Examination Scope

The Nuclear Regulatory Commission=s examiners prepared the examination outline and

developed the written examination and operating test. The NRC examiners validated the

proposed examination during the week of December 15, 2008, at the Perry Nuclear

Power Station Training Building with the assistance of members of the licensee training

staff. During the on-site validation week on December 15, 2008, the examiners audited

two license applications for accuracy. The NRC examiners conducted the operating

portion of the initial license examination during the week of January 12, 2009. The NRC

examiners and members of the Perry Nuclear Power Station training department staff

administered the written examination on January 21, 2009. The NRC examiners used

the guidance established in NUREG-1021, AOperator Licensing Examination Standards

for Power Reactors,@ Revision 9, to prepare, validate, revise, administer, and grade the

examination.

b. Findings

Written Examination

During the validation of the written examination several questions were modified or

replaced. Changes made to the written examination were documented on Form

ES-401-9, AWritten Examination Review Worksheet@ which is available electronically in

the NRC Public Document Room or from the Publicly Available Records component of

NRC's document system (ADAMS). The licensee submitted four written examination

post-examination comments for consideration by the NRC examiners when grading the

written examination. The post-examination comments and the NRC resolution for the

post-examination comments are contained in Enclosure 3, APost Examination Comments

and Resolutions.@ The NRC examiners graded the written examination on

February 19, 2009, and conducted a review of each missed question to determine the

accuracy and validity of the examination questions.

Operating Test

During the validation of the operating test, two Job Performance Measures (JPMs) were

modified and changes were made to the dynamic simulator scenarios. The JPMs were

replaced since the JPMs were determined to be too simplistic in nature (inadequate

difficulty level). Changes made to the operating test were documented in a document

titled, AOperating Test Comments,@ which is available electronically in the NRC Public

Document Room or from the Publicly Available Records component of NRC's document

system (ADAMS). The NRC examiners completed operating test grading on

February 19, 2009.

2 Enclosure 1

Examination Results

Eight applicants at the Senior Reactor Operator (SRO) level and one applicant at the

Reactor Operator (RO) level were administered written and operating tests. Two of the

SRO applicants were previously licensed as ROs at Perry Power Station. Nine

applicants passed all portions of their examinations and eight applicants were issued

operating licenses. One applicants license was withheld until experience requirements

had been met.

.2 Examination Security

a. Scope

The NRC examiners reviewed and observed the licensee's implementation of

examination security requirements during the examination validation and administration

to assure compliance with 10 CFR 55.49, AIntegrity of Examinations and Tests.@ The

examiners used the guidelines provided in NUREG 1021, "Operator Licensing

Examination Standards for Power Reactors@ to determine acceptability of the licensee=s

examination security activities.

b. Findings

No Findings

4OA6 Meetings

Debrief

The chief examiner presented the examination team's preliminary observations

and findings on January 16, 2009, to A. Mueller, Jr., and other members of the

Perry Operations and Training Department staff.

Exit Meeting

The chief examiner conducted an exit meeting on March 4, 2009, with Mr. A. Mueller, Jr.,

Perry Station Training Director by telephone. The NRC=s final disposition of the station=s

post-examination comments were disclosed and revised preliminary written examination

results were provided to A. Mueller, Jr., during the telephone discussion. The examiners

asked the licensee whether any of the material used to develop or administer the

examination should be considered proprietary. No proprietary or sensitive information

was identified during the examination or debrief/exit meetings.

ATTACHMENT: SUPPLEMENTAL INFORMATION

3 Enclosure 1

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

K. Krueger, Plant General Manager

D. Evans, Manager Operations

A. Cayia, Director Performance Improvement

R. Coad, Manager - Regulatory Compliance

A. Mueller, Jr., Manager Training

J. Pelcic, Nuclear Compliance

D. Zielinsky, Training Department

R. Torres, Training Department

J. Kelley, Training Department

D. Richmond, Training Department

NRC

R. Walton, Chief Examiner

ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

UNR (00050/440-2009-301-01), Two-Phase Fluid Flow Modeling for Feedwater

Closed

None

Discussed

None

LIST OF DOCUMENTS REVIEWED

None

LIST OF ACRONYMS USED

ADS Automatic Depressurization System

ADAMS Agency-Wide Document Access and Management System

BWR Boiling Water Reactor

DRS Division of Reactor Safety

NRC Nuclear Regulatory Commission

IR Inspection Report

SPDS Safety Parameters Display System

1 Attachment

SIMULATION FACILITY REPORT

Facility Licensee: Perry Nuclear Power Station

Facility Docket No: 50-440

Operating Tests Administered: 1/12/2009 - 1/16/2009

The following documents observations made by the NRC examination team during the initial

operator license examination. These observations do not constitute audit or inspection

findings and are not, without further verification and review, indicative of non-compliance with

10 CFR 55.45(b). These observations do not affect NRC certification or approval of the

simulation facility other than to provide information which may be used in future evaluations.

No licensee action is required in response to these observations.

During the conduct of the simulator portion of the operating tests, the following items were

observed:

Incorporation of Two-Phase Fluid Flow Modeling for Feedwater

During onsite validation week of the initial license exam at the Perry station, the inspectors noted

that reactor vessel water level appeared to increase with no high pressure injection or operator

intervention after emergency depressurization. With reactor pressure lowering, the reactor

vessel water level swelled about 100 inches. The vessel water level then lowered due to the

ADS valves being opened.

The licensee informed the examiners that previously they had loaded computer software that

changed the high pressure feedwater injection from a single phase fluid flow model to a

two-phase fluid flow model. This resulted in a flashing of high temperature feedwater in

feedwater heaters #6. This condition produced flow into the reactor vessel after the vessel

pressure lowered to the high pressure feedwater heater #6 saturation pressure.

This simulator computer model was taught to the initial license class and requalification classes.

The initial license exam was administered during the week of January 12, 2009, with this

simulator software included.

The examiners determined that this simulator modeling had been included at two other facilities

in the industry. The examiners were uncertain of the pedigree and approval status of this

computer software modeling since it had not yet been approved by the BWR owners group, and

had not been widely accepted by other BWR utilities. This issue was considered an Unresolved

Item (50-440/2009301-01) pending further review by NRC Headquarters Operations staff.

Change in Simulator Modeling between On-Site Validation and Exam Administration

During the week of December 15, 2008, the examiners validated the Perry operating exam with

an operating crew. The operating crew used the Safety Parameters Display System (SPDS)

display screens in the overhead of the simulator to track and trend various parameters important

1 Enclosure 2

to equipment operation and plant monitoring. The SPDS computer received inputs from the

simulator computer. On January 9, 2009, the licensee implemented a change to the SPDS

process computer that was believed to be a graphics change - a change that would not alter

computer modeling.

The following week, on Monday, January 12, 2009, during the administration of the initial license

operating test, the examiners, examinees and licensee simulator operators noted that the SPDS

computer display panel did not accurately display reactor vessel wide range water level.

The following day, after running the first scenario, and seeing that the SPDS computer had

rejected wide range reactor vessel water level input from the simulator computer, the licensees

staff determined that a change to the SPDS computer software had occurred since onsite

validation. Specifically, a change to the SPDS computer included a file that inhibited the SPDS

computer from receiving wide range input from the simulator computer. As a result, the SPDS

displays for wide range level indication were erroneous. The scenarios were continued with this

software change included until the file was removed on Tuesday night, January 13, 2009.

NUREG 1021, ES-301-4, item 8 required that computer modeling not be changed between

onsite validation and exam administration. Since the SPDS computer software was changed

that affected important monitored parameters, the examiners believed there was a potential for

invalidating the Perry Initial operating exam for January 12 and 13, 2009.

The Operator Licensing Branch in Headquarters reviewed this event and determined that the

exam was not invalidated. The erroneous indications on the SPDS panel were clearly identified

by their color, the applicants had access to accurate wide range level indications on the main

control boards and that all other functions worked normally. There was no reason to treat this

any different than any other instrumentation malfunction or to invalidate the affected scenarios.

This event described illustrated the risk of making even simple changes that were not expected

to alter the simulators response.

2 Enclosure 2

POST EXAMINATION COMMENTS AND RESOLUTIONS

RO Question Number 17

A plant startup is in progress per IOI-0001 Cold Startup. The following plant conditions exist:

Reactor Pressure 200 psig

Main Condenser Vacuum 5.0 HgA

Mechanical Vacuum Pumps are being cycled to maintain vacuum

Main Turbine Warming is in progress

Motor Feed Pump is providing Reactor Level Control

TBCC Pumps A and B operating

The following alarm is received on 1H13-P870, TBCC PUMP SUCTION FLOW LOW. The

operator checks TBCC Parameters at 1H13-P870 with the following indications:

TBCC A Pump red and green light off, no discharge pressure indicated.

TBCC B Pump red light on, green light off, no discharge pressure indicated.

TBCC C Pump red light off, green light on, no discharge pressure indicated.

Per ONI-P44 Loss of Turbine Building Closed Cooling, an ____.

A. immediate scram may not be necessary because the Main Turbine is not in operation

B. immediate scram may not be necessary because reactor pressure control is on the

Bypass Valves

C. immediate scram is required because the Motor Feed Pump is providing level control

D. immediate scram is required because the Mechanical Vacuum Pumps can not be cycled

Answer: A

Reference: ONI-P44, Loss of Turbine Building Closed Cooling, Revision 7, Page 5

1 Enclosure 3

POST EXAMINATION COMMENTS AND RESOLUTIONS

Applicant Comment:

An applicant asserted that the answer key should be changed so that distractor C was the only

correct answer.

The applicant provided the following justification:

1. The question asks what actions are required for a loss of Turbine Building Closed Cooling

(TBCC) per ONI-P44, Loss of Turbine Building Closed Cooling. The stem of the question

contains the status of the TBCC pumps with indication of NO discharge pressure for any of

the 3 TBCC pumps. Lack of discharge pressure is symptomatic of a system leak and a total

loss of TBCC.

2. Plant TBCC pump discharge pressure indicates 16-17 psig when in standby due to the

height of water from the expansion tank. The bottom of surge tank is at elevation 66010

and pump suction is at elevation 6259.250.

3. The procedure directs that for a total loss of TBCC, the reactor be scrammed.

(ONI-P44 immediate action 3.4).

4. Core flow is < 58 mlbm during plant start-up at 200 psig. (No core flow reduction required.)

The applicant provided the following justifications for the distractors:

A. Incorrect answer - Based on a total loss of TBCC an immediate scram is required no

standby TBCC pump is available - no discharge pressure indicated which signifies a leak

in the system.

B. Incorrect answer - Based on a total loss of TBCC an immediate scram is required no

standby TBCC pump is available - no discharge pressure indicated which signifies a leak

in the system. Bypass valve HPUs require shutdown at 150 degrees in sump.

C. Correct answer - Based on a total loss of TBCC an immediate scram is required and the

Feed and Condensate system will be shut down when temperature limits are reached.

D. Incorrect answer - Based on a total loss of TBCC an immediate scram is required

however the Mechanical Vacuum Pumps CAN be cycled. The shutdown limit at 102

degrees F can be exceeded (reference ONI-P44 Attachment 1 limits).

Reference: ONI-P44, Loss of Turbine Building Closed Cooling, pages 5, 8, 10, 11.

2 Enclosure 3

POST EXAMINATION COMMENTS AND RESOLUTIONS

Facility Proposed Resolution:

The facility agreed with the applicant and stated that the answer key should be changed so that

distractor C was the only correct answer. The facility also stated that the question asked what

actions were required for a loss of Turbine Building Closed Cooling (TBCC) per ONI-P44. The

stem of the question contained the status of the TBCC pumps with indication of no discharge

pressure for any of the 3 TBCC pumps. The procedure directed that for a total loss of TBCC the

reactor be scrammed. The facility referred to the applicants comments for details.

Reference: ONI-P44, Loss of Turbine Building Closed Cooling, pages 5, 8, 10, 11.

NRC Resolution:

Upon review of the question, the applicant comment, and the facility proposed resolution, it was

resolved to delete the question from the examination.

The question asked what actions were required for a loss of Turbine Building Closed Cooling

(TBCC) per ONI-P44, Loss of Turbine Building Closed Cooling. The stem of the question

contained the status of the TBCC pumps with indication of no discharge pressure for any of the

3 TBCC pumps. Lack of discharge pressure would be symptomatic of a system leak and a

complete loss of TBCC.

Facility procedure ONI-P44, Loss of Turbine Building Closed Cooling, Step 3.4, required that

for a complete loss of TBCC, the reactor be scrammed. However, a NOTE preceding this step

qualified this step by stating:

The Reactor is shutdown in anticipation of loss of cooling to various loads, e.g.,

Generator Stator. An immediate shutdown may NOT be necessary if the main turbine is

NOT in operation.

Step 4.3.8 of ONI-P44 also required shutdown of TBCC components that reached their

temperature limit. Attachment 1 of ONI-P44, TBCC Served Component Limitations, provided

the temperature limits for the Motor Feedwater Pump and the Mechanical Vacuum Pumps. In

Attachment 1, the temperature limitation of 102°F for the Mechanical Vacuum Pumps had an

asterisk that stated:

This limit for vacuum considerations only and may be exceeded.

However, a NOTE preceding Step 4.3.8 stated:

The Mechanical Vacuum Pumps should NOT be used due to the loss of cooling water to

the seal water coolers.

Based on the above information, the following distractor evaluation was performed:

3 Enclosure 3

POST EXAMINATION COMMENTS AND RESOLUTIONS

Distractor A was considered a correct answer based on the NOTE preceding Step 3.4 of

ONI-P44, because it stated that an immediate scram may NOT be necessary if the main turbine

is not in operation. For the conditions stated in the question stem, the main turbine was not in

operation, and thus the NOTE was applicable. Thus, distractor A, immediate scram may not be

necessary because the Main Turbine is not in operation, was a correct answer.

Distractor B was an incorrect answer based on the following:

- ONI-P44, Step 3.4, required that for a complete loss of TBCC, the reactor be scrammed.

- With the temperature limitation of 150°F provided in Attachment 1 of ONI-P44, for the Steam

Bypass Hydraulic Power Unit (HPU) Reservoir, the Bypass Valves could not be used for any

significant time period before its temperature limit was reached and a scram was required.

Thus, distractor B, immediate scram may not be necessary because reactor pressure control is

on the Bypass Valves, remained an incorrect answer.

Distractor C is a correct answer based on the following:

- ONI-P44, Step 3.4 required that for a complete loss of TBCC the reactor be scrammed.

- The question stem stated that the Motor Feedwater Pump was providing Reactor Level

Control. With the temperature limitations provided in Attachment 1 of ONI-P44, for the Motor

Feedwater Pump, the Motor Feedwater Pump could not be run for any significant time period

before its temperature limit was reached and a scram was required.

Thus, distractor C, immediate scram is required because the Motor Feed Pump is providing

level control, was a correct answer.

Distractor D is a correct answer based on the following:

- ONI-P44, Step 3.4, required that for a complete loss of TBCC, the reactor be scrammed.

- The NOTE preceding Step 4.3.8 stated that the Mechanical Vacuum Pumps should NOT be

used due to the loss of cooling water to the seal water coolers.

- With the temperature limitations provided in Attachment 1 of ONI-P44, for the Mechanical

Vacuum Pumps, the Mechanical Vacuum Pumps could not be run for any significant time

period before its temperature limit was reached and a scram was required.

Thus, distractor D, immediate scram is required because the Mechanical Vacuum Pumps can

not be cycled, was a correct answer.

Finally, the Examiners Standard, ES-403, part D.1.c stated:

If it is determined that there are two correct answers, both answers will be

accepted as correct. If, however, both answers contain conflicting information,

the question will likely be deleted. For example, if part of one answer states that

operators are required to insert a manual reactor scram, and part of another

answer states that a manual scram is not required, then it is unlikely that both

answers will be accepted as correct, and the question will probably be deleted.

4 Enclosure 3

POST EXAMINATION COMMENTS AND RESOLUTIONS

If three or more answers could be considered correct or there is no correct

answer, the question shall be deleted.

Since there were three correct answers (A, C, and D) identified for the question, and two

combinations of these answers could not logically be true at the same time (A and C or D), it was

resolved to delete the question from the examination.

5 Enclosure 3

POST EXAMINATION COMMENTS AND RESOLUTIONS

SRO Question Number 12

The plant was operating at 100% reactor power when a grid disturbance caused a generator

load rejection. This resulted in a reactor scram. All plant equipment responded as designed.

Per RPS Instrumentation Tech Spec Bases, the primary scram signal analyzed to provide

protection from a generator load rejection event is __(1)__.

As the Unit Supervisor you direct a reactor level band of __(2)__ per EOP-1 RPV Control.

1 2

A. reactor vessel steam dome pressure high 130 to 219

B. reactor vessel steam dome pressure high 178 to 219

C. turbine control valve fast closure, trip oil pressure low 130 to 219

D. turbine control valve fast closure, trip oil pressure low 178 to 219

Answer: A

References: Technical Specification (TS) 3.3.1.1 Bases

Updated Safety Analysis Report (USAR), Revision 12

EOP-1 Guideline, Revision 0

6 Enclosure 3

POST EXAMINATION COMMENTS AND RESOLUTIONS

Applicant Comment:

An applicant asserted that the answer key should be changed so that distractor C should also be

accepted as correct, in addition to distractor D.

The applicant provided the following basis for this reasoning:

1. The questions asks the bases for the generator load rejection scram and the level band the

Unit Supervisor would direct following a grid disturbance that results in a generator load

rejection.

2. Turbine Control Valve - Fast Closure, Trip Oil Pressure Low is the bases for the generator

load rejection.

3. A level band of 130-219 inches is correctly given per the EOP bases for step RLC-4 in

EOP-1, which states the wide RPV water level control band permitted by this step is

sufficient to assure adequate core cooling yet avoid unwarranted demands on an operators

attention.

a. If unnecessarily constrained within narrower limits, an operator may be less effective in

performing concurrent duties.

4. The narrower band of 178-219 inches is suggested per Guideline 2 in EOP-1. Per the EOP

bases guidelines provide supplemental information to the operator.

5.

a. A guideline flag in the flowpath refers to the guideline text.

b. The Guideline text provides supplemental bases information that the operator can call

upon if need to help in decision making and performance of the flowcharts.

6. Since these steps are at the same relative location in the level leg of EOP-1 either band

would be correct to order with the given conditions within the question and might be

amended as plant conditions and Control Room work load changes.

7. The recommendation is that two answers (C and D) are correct because the two level bands

given would be correct if directed.

The applicant provided the following distractor analysis:

A. Incorrect answer - Reactor vessel steam dome pressure high is not the bases for the

trip.

B. Incorrect answer - Reactor vessel steam dome pressure high is not the bases for the

trip.

C. Correct answer - Turbine Control Valve - Fast Closure, Trip Oil Pressure Low and a

Level Band of 130-219 for the wider level band is also correct.

7 Enclosure 3

POST EXAMINATION COMMENTS AND RESOLUTIONS

D. Correct answer - Turbine Control Valve - Fast Closure, Trip Oil Pressure Low and a

Level Band of 178-219 for the narrow level band is still correct.

References: Technical Specification 3.3.1.1 Bases, pages 3.3-11 and 3.3-18

EOP Bases, page 22

EOP-1, RPV Control Bases, pages 25 and 26

Facility Proposed Resolution:

The facility agreed with the applicant and commented that the answer key should be changed so

that distractor C should also be accepted as correct, in addition to distractor D. The facility

stated that the question asked the basis for the generator load rejection scram and the level

band the Unit Supervisor would direct following a grid disturbance that results in a generator

load rejection. Turbine Control Valve Fast Closure Trip Oil Pressure Low is the bases for the

generator load rejection, a level band of 130-219 inches is correctly given per the EOP basis and

the narrower band of 178-219 inches is suggested per Guideline 2. The facility referred to the

applicants comments for details.

References: Technical Specification 3.3.1.1 Bases, pages 3.3-11 and 3.3-18

EOP Bases, page 22

EOP-1, RPV Control Bases, pages 25 and 26

NRC Resolution:

Upon review of the question, the applicant comment, and the facility proposed resolution, it was

decided to accept the facilitys comment and accept both distractors C and D as correct

answers.

The question asked for the Technical Specification (TS) Bases (from the Reactor Protection

System (RPS) Instrumentation section of the TS) for the generator load rejection event and the

level band the Unit Supervisor would direct following a grid disturbance that resulted in a

generator load rejection and resultant reactor scram.

From page B.3.3-18 of the RPS Instrumentation TS Bases, the Turbine Control Valve Fast

Closure, Trip Oil Pressure Low function is the primary scram signal for the generator load

rejection event.

From EOP-01, RPV Control, Revision A, step RLC-4 stated to Restore and Maintain RPV level

between 130 inches and 219 inches. The EOP Bases document for this step stated:

The wide RPV water level control band permitted by this step is sufficient to assure

adequate core cooling yet avoid unwarranted demands on an operators attention.

If unnecessarily constrained within narrower limits, an operator may be less effective in

performing concurrent duties.

In EOP-01, prior to step RLC-4, there was a guideline flag, which referred to Guideline 2. In

EOP-01, a list of General Guidelines was provided in a text box at the bottom of the flowchart.

General Guideline 2 stated:

8 Enclosure 3

POST EXAMINATION COMMENTS AND RESOLUTIONS

If other EOP actions have a higher priority allow HPCS or RCIC to operate in automatic

between Level 2 and Level 8. Closely monitor system operation. The level band should be

expanded above Level 8 and below Level 2 to allow the system to operate within the level

band. Maintain level above 100 inches to 260 inches. RPV level should be maintained 178

to 219 inches whenever possible and shall be greater than 178 inches whenever shutdown

cooling is in service.

The EOP Bases document associated with the Guideline text stated:

Guidelines provide supplemental information to the operator. A guideline flag in

the flowpath refers to the guideline text. The Guideline text provides

supplemental bases information that the operator can call upon if needed to help

in decision making and performance of the flowcharts.

Based on the above information, the following distractor evaluation was performed:

Distractors A and B were incorrect in that the TS Bases for the generator load rejection event

was turbine control valve fast closure, trip oil pressure low, and not reactor vessel steam dome

pressure high. In addition, from page B.3.3-11 of the RPS Instrumentation TS Bases, no

specific safety analysis took credit for the Reactor Vessel Steam Dome Pressure High function.

Distractor C was a correct answer based on the following:

- The TS Bases for the generator load rejection event was turbine control valve fast closure,

trip oil pressure low, and

- Step RLC-4 of EOP-01, which stated to restore and maintain RPV level between 130 inches

and 219 inches. In addition, the EOP Bases document for this step stated that the wide RPV

water level control band permitted by this step was sufficient to assure adequate core

cooling yet avoid unwarranted demands on an operators attention, and if unnecessarily

constrained within narrower limits, an operator may be less effective in performing

concurrent duties.

Distractor D is a correct answer based on the following:

- The TS Bases for the generator load rejection event is turbine control valve fast closure, trip

oil pressure low, and

- Step RLC-4 of EOP-01, which stated to restore and maintain RPV level between 130 inches

and 219 inches. The level band of 178 to 219 inches was encompassed by the level band of

130 to 219 inches stated in step RLC-4. In addition, the narrower band of 178 to 219 inches

was suggested per Guideline 2 in EOP-01. Per the EOP Bases, the guidelines provided

supplemental information to the operator that the operator could call upon if needed to help

in decision making and performance of the flowcharts.

Therefore, the answer key was modified to accept both distractors C and D as correct answers.

9 Enclosure 3

POST EXAMINATION COMMENTS AND RESOLUTIONS

SRO Question Number 16

A plant startup is in progress with reactor power at 29%.

Number 1 Turbine Bypass Valve fails open.

Full Core Display, RPC MODE light is between GP1-4 Full Out and LO Power Set PT marks.

The __(1)__ and the Unit Supervisor would suspend control rod __(2)__.

(1) (2)

A. Rod Withdrawal Limiter is Inoperable Withdrawal

B. Rod Withdrawal Limiter is Inoperable movement except by scram

C. Rod Pattern Controller is Inoperable Withdrawal

D. Rod Pattern Controller is Inoperable movement except by scram

Answer: B

References: Technical Specification 3.3.2.1

ARI-H13-P680-0005-C9, Revision 11

Applicant Comment:

An applicant asserted that the question should be deleted from the examination since none of

the distractors were correct.

The applicant provided the following justification:

1. The question asks for the operator to make a declaration of Operability in accordance with

Technical Specifications for either the Rod Pattern Controller or the Rod Withdrawal limiter

and then determine the required actions for control rod movement following a failed bypass

valve with reactor power at 29%.

2. PNPP Technical Specifications do not require the Rod Withdrawal Limiter (RWL) to be

Operable until greater than 33.3% RTP and the Rod Pattern Controller (RPC) is only

required to be operable when less than or equal to 19% RTP.

3. The question asks what to do if at 29% RTP. In accordance with TS 3.3.2.1 APPLICABILITY:

According to Table 3.3.2.1-1, there is none since current power is between 19% and 33.3%.

Since there is no applicability there is no operability requirement and no required action until

10 Enclosure 3

POST EXAMINATION COMMENTS AND RESOLUTIONS

RTP is either greater than 33.3% or less than 19% RTP. This condition would be addressed

by a Potential LCO and administratively tracked.

4. Therefore, Answer A (i.e. Rod Withdrawal Limiter is Inoperable and the Unit Supervisor

would suspend control rod withdrawal) is incorrect.

The applicant provided the following distractor analysis:

A. Incorrect answer - RWL is NOT required to be operable therefore no required action.

B. Incorrect answer - RWL is NOT required to be operable therefore no required action.

C. Incorrect answer - RPC is NOT required to be operable therefore no required action.

D. Incorrect answer - RPC is NOT required to be operable therefore no required action.

References: Technical Specification 3.3.2.1, Control Rod Block Instrumentation and

Table 3.3.2.1-1

Facility Proposed Resolution:

The facility agreed with the applicant and commented that the question should be deleted from

the examination since none of the distractors were correct. The facility stated that the question

asked for the operator to make a declaration of Operability for either the Rod Pattern Controller

or the Rod Withdrawal Limiter and determine the required actions for control rod movement

following a failed bypass valve with reactor power at 29%. The facility commented that the Perry

Nuclear Power Plant Technical Specifications do not require the Rod Withdrawal Limiter to be

Operable until greater than 33.3% reactor thermal power (RTP) and required the Rod Pattern

Controller only operable at less than or equal to 19% RTP. The facility referred to the applicants

comments for details.

References: Technical Specifications 3.3.2.1, page 3.3-15 and Table 3.3.2.1-1

NRC Resolution:

Upon review of the question, the applicant comment, and the facility proposed resolution, it was

decided to it was decided to delete the question from the examination.

The question asked for the Unit Supervisor to make a declaration of operability for either the Rod

Pattern Controller or the Rod Withdrawal Limiter, and to determine the required actions for

control rod movement following a failed open #1 turbine bypass valve with reactor power at 29%

and a plant startup in progress.

Technical Specification (TS) 3.3.2.1, Control Rod Block Instrumentation, defined the TS

operability requirements for both the Rod Withdrawal Limiter (RWL) and the Rod Pattern

Controller (RPC). The Applicability of the Control Rod Block Instrumentation is according to

Table 3.3.2.1-1 of the TS. In Table 3.3.2.1-1 of the TS, the Applicable Modes or Other

11 Enclosure 3

POST EXAMINATION COMMENTS AND RESOLUTIONS

Specified Conditions, was given as:

- For the RWL, either Reactor Thermal Power (RTP) greater than 66.7% or between

greater than 33.3% and less than or equal to 66.7%.

- For the RPC, RTP less than or equal to 19.0%, except during the reactor shutdown

process if the coupling of each withdrawn control rod has been confirmed.

Based on the above information, the Technical Specifications did not require either the Rod

Withdrawal Limiter to be operable until greater than 33.3% RTP, and the Rod Pattern Controller

was only required to be operable when less than or equal to 19% RTP. Since the question

asked for actions required with the plant at 29% reactor power, the TS did not apply, and there

was no operability requirement and no required action for this plant condition. Thus, there were

no correct answers, and it was decided to delete the question from the examination.

12 Enclosure 3

POST EXAMINATION COMMENTS AND RESOLUTIONS

SRO Question Number 25

Alert JA1 was declared.

Emergency Coordinator duties remain with the Shift Manager.

When the Shift Manager is ready to terminate from event, the Shift Manager is responsible to

terminate the event ____.

Reference Provided: EPI-A1 Attachments 1 & 2

A. after consulting with the NRC, State and local counties

B. after consulting with the State and local counties

C. after consulting with the NRC

D. without consultation

Answer: D

References: EPI-A1, page 11

EPI-A2, pages 13 and 17

Applicant Comment:

An applicant asserted that the question should be deleted from the examination since none of

the distractors were correct.

The applicant provided the following justification:

The question asks for the required consultations when terminating from an Alert but does not

specify a specific instruction. There are two references listed which include conflicting and in

one case, vague guidance on correct execution.

a. In accordance with EPI-A-2, Emergency Action Levels, Section 5.3.1.6 and on Event

Termination Actions Checklist, item # A.4 - For events classified as an Alert or above,

the NRC, State of Ohio, and local counties have been consulted regarding event

termination.

b. In accordance with EPI-A-1, Emergency Actions Based on Event Classification,

Section 5.5.1.11 - Consult with NRC, State of Ohio, and local county officials regarding

the decision to terminate the emergency. The intent of this action is to involve the NRC,

State and local counties in event decision making; however, this action is not intended to

13 Enclosure 3

POST EXAMINATION COMMENTS AND RESOLUTIONS

delay or hinder the Perry Plants ability to terminate from an Unusual Event or Alert that

no longer meets the criteria for any event at the time of declaration.

1) The last line of the step may given the correct circumstances contradict the first

line in the step.

2) This issue has been identified and a Condition Report is to be written to resolve

the differences between the above two procedures

The applicant provided the following distractor analysis:

A. Correct answer - IAW EPI A2 page 14 and 17, PNPP is to consult with the NRC, State

and local county officials regarding event termination, Answer A lists all three per the

EPI.

B. Correct answer - IAW EPI A2 page 14 and 17, PNPP is to consult with the NRC, State

and local county officials regarding event termination, Answer B just lists the State and

local county officials however it does not say only, even though the NRC is also to be

consulted, Answer B is not wrong, Answer B is a subset of Answer A.

C. Correct answer - IAW EPI A2 page 14 and 17, PNPP is to consult with the NRC, State

and local county officials regarding event termination, Answer C just lists the NRC

however it does not say only, even though the State and local county officials are also to

be consulted, Answer C is not wrong, Answer C is a subset of Answer A.

D. Correct answer - EPI A1 page 11 (this is a different reference than for Answers A, B, C),

PNPP is to consult with the NRC, State and local county officials regarding event

termination however during an Unusual Event or an Alert this action is not intended to

delay or hinder PNPPs ability to terminate from an Unusual Event or an Alert. Therefore

given the correct circumstances consultation is not required.

References: EPI A1 page 11

EPI A2 pages 14 and 17

Facility Proposed Resolution:

The facility agreed with the applicant and commented that the question should be deleted from

the examination since none of the distractors were correct. The facility stated that the question

asked for the required consultations when terminating from an Alert in accordance with

EPI-A-0001, Emergency Actions Based on Event Classification, Section 5.5.1.11, Answers A, B,

C are correct. In accordance with EPI-A-0002, Emergency Action Levels, Section 5.3.6,

Answer D is correct. The facility referred to the applicants comments for details.

References: EPI A1 page 11

EPI A2 pages 14 and 17

14 Enclosure 3

POST EXAMINATION COMMENTS AND RESOLUTIONS

NRC Resolution:

Upon review of the question, the applicant comment, and the facility proposed resolution, it was

decided to it was decided to delete the question from the examination.

The question asked for the required consultations when terminating from an Alert condition in

accordance with the emergency plan procedures.

In accordance with EPI-A2, step 5.3.1.6, it stated:

For events classified as an Alert or above, the NRC, State of Ohio, and local counties

have been consulted regarding event termination.

In accordance with EPI-A2, Attachment 2, Section A, Event Termination Actions, step 6, it

stated:

[ALERT OR ABOVE ONLY] NRC, State of Ohio, and local counties consulted regarding

the decision to terminate the emergency.

In accordance with EPI-A1, step 5.5.1.11, it stated:

Consult with NRC, State of Ohio, and local county officials regarding the decision to

terminate the emergency. The intent of this action is to involve the NRC, State and local

counties in event decision making; however, this action is not intended to delay or hinder

the Perry Plants ability to terminate from an Unusual Event or Alert that no longer meets

the criteria for any event at the time of declaration.

Based on the above information, the following distractor evaluation was performed:

Distractor A was a correct answer based on EPI-A2, step 5.3.1.6, EPI-A1, step 5.5.1.11, and

EPI-A2, Attachment 2, Section A, Event Termination Actions, step 6, which stated that for

events classified as an Alert or above, the NRC, State of Ohio, and local counties have been

consulted regarding event termination.

Distractor B was a correct answer based on EPI-A1, step 5.5.1.11; EPI-A2, step 5.3.1.6; and

EPI-A2, Attachment 2, Section A, Event Termination Actions, step 6, which stated that for

events classified as an Alert or above, the NRC, State of Ohio, and local counties have been

consulted regarding event termination. Since distractor B required consulting with the State and

local counties, and did not specifically state that these were the ONLY organizations to be

consulted, this distractor was also a correct answer.

Distractor C was a correct answer based on EPI-A1, step 5.5.1.11; EPI-A2, step 5.3.1.6; and

EPI-A2, Attachment 2, Section A, Event Termination Actions, step 6, which stated that for

events classified as an Alert or above, the NRC, State of Ohio, and local counties have been

consulted regarding event termination. Since distractor C required consulting with the NRC, and

did not specifically state that this was the ONLY organization to be consulted, this distractor was

also a correct answer.

15 Enclosure 3

POST EXAMINATION COMMENTS AND RESOLUTIONS

Distractor D was an incorrect answer based on EPI-A1, step 5.5.1.11; EPI-A2, step 5.3.1.6; and

EPI-A2, Attachment 2, Section A, Event Termination Actions, step 6, which stated that for

events classified as an Alert or above, the NRC, State of Ohio, and local counties have been

consulted regarding event termination. Per EPI-A1, the intent is to involve the NRC, state, and

local counties in the decision making process. EPI-A1, step 5.5.1.11, goes on to state that this

action is not intended to delay or hinder the plants ability to terminate from an Unusual Event or

an Alert that no longer meets the criteria for any event at the time of declaration. As stated in

Section 5.3 of EPI-1A, an event that no longer meets the criteria for any event at time of

declaration, need not even be classified.

The applicant asserted that, given the correct circumstances, consultation with any organizations

was not required. However, applicants are instructed prior to the test per NUREG 1021,

Appendix E not to make assumptions regarding conditions that were not specified in the

question unless they occurred as a consequence of other conditions that were stated in the

question. Nothing in the stem of the question supported an assumption that the event no longer

met the EAL criteria at the time of the declaration. Therefore, the applicants assertion is invalid

and distractor D remained an incorrect answer.

Since three of the four distractors were correct answers, it was determined to delete the question

from the examination.

16 Enclosure 3

POST EXAMINATION COMMENTS AND RESOLUTIONS

Post Examination Comments and Resolutions

WRITTEN EXAMINATIONS AND ANSWER KEYS (RO/SRO)

RO/SRO Initial Examination ADAMS Accession # ML090650492

1 Enclosure 4