UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
SAM NUNN ATLANTA FEDERAL CENTER
61 FORSYTH STREET, SW, SUITE 23T85
ATLANTA, GEORGIA 30303-8931
March 5, 2009
Mr. Greg Kilpatrick, Training Manager
Harris Energy & Environmental Center
Progress Energy Carolinas, Inc.
Shearon Harris Nuclear Power Plant
P. O. Box 327, State Road 1127
New Hill, NC 27562-0165
SUBJECT:
SHEARON HARRIS NUCLEAR PLANT - OPERATOR LICENSING
WRITTEN EXAMINATION APPROVAL 05000400/2009301
Dear Mr. Kilpatrick:
The purpose of this letter is to confirm the final arrangements for the upcoming operator
licensing written examination at the Shearon Harris Nuclear Plant.
The U.S. Nuclear Regulatory Commission (NRC) has completed its review of the operator
license applications submitted in connection with this examination and separately provided a list
of approved applicants to you. The NRC staff will administer the operating tests to these
individuals, as applicable, during the weeks of March 9, 2009, and March 16, 2009. Note that
any examination waivers and application denials have been addressed in separate
correspondence.
The NRC has approved the subject written examination and hereby authorizes you to
administer the written examination in accordance with Revision 9, Supplement 1, of NUREG-
1021, Operator Licensing Examination Standards for Power Reactors, during the week of
March 16, 2009.
This examination has undergone extensive review by my staff and representatives responsible
for operator training at your facility. Based on this review I have concluded that the examination
meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By
administering this examination, you also agree that it meets NUREG-1021 guidelines, and is
appropriate for measuring the qualifications of licensed operators at your facility. If you
determine that this examination is not appropriate for licensing operators at your facility, do not
administer the examination and contact me at (404) 562-4550.
G. Kilpatrick
2
Please contact your Chief Examiner, Mr. Frank Ehrhardt, at (404) 562-4611 if you have any
questions or identify any errors or changes in license level (RO or SRO) or type of examination
(partial or complete written examination and/or operating test) specified for each applicant on
the list of approved applicants.
Sincerely,
/ RA /
Malcolm T. Widmann, Chief
Operations Branch
Division of Reactor Safety
Docket Nos.: 50-400
License Nos.: NPF-63
G PUBLICLY AVAILABLE
G NON-PUBLICLY AVAILABLE
G SENSITIVE
G NON-SENSITIVE
ADAMS: G Yes
ACCESSION NUMBER:_________________________
G SUNSI REVIEW COMPLETE
OFFICE
RII:DRS
RII:DRS
SIGNATURE
/ RA /
/ RA /
NAME
FEHRHARDT:btm
MWIDMANN
DATE
3/ /2009
3/ /2009
3/ /2009
E-MAIL COPY?
NO
NO
OFFICIAL-RECORD-COPY DOCUMENT-NAME:--O:\\HARRIS-EXAMINATIONS\\INITIAL-EXAM-
2009301\\CORRESPONDENCE\\HAR MARCH 2009-301 APPROVAL LETTER [BTM].DOC