March Exam 05000400/2009301 Approval Letter Dated 3-5-2009
ML090641142
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 03/05/2009
From: Widmann M
Division of Reactor Safety II
To: Kilpatrick G
Progress Energy Carolinas
References
50-400/09-301
Download: ML090641142 (2)


See also: IR 05000400/2009301

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

SAM NUNN ATLANTA FEDERAL CENTER

61 FORSYTH STREET, SW, SUITE 23T85

ATLANTA, GEORGIA 30303-8931

March 5, 2009

Mr. Greg Kilpatrick, Training Manager

Harris Energy & Environmental Center

Progress Energy Carolinas, Inc.

Shearon Harris Nuclear Power Plant

P. O. Box 327, State Road 1127

New Hill, NC 27562-0165

SUBJECT: SHEARON HARRIS NUCLEAR PLANT - OPERATOR LICENSING

WRITTEN EXAMINATION APPROVAL 05000400/2009301

Dear Mr. Kilpatrick:

The purpose of this letter is to confirm the final arrangements for the upcoming operator

licensing written examination at the Shearon Harris Nuclear Plant.

The U.S. Nuclear Regulatory Commission (NRC) has completed its review of the operator

license applications submitted in connection with this examination and separately provided a list

of approved applicants to you. The NRC staff will administer the operating tests to these

individuals, as applicable, during the weeks of March 9, 2009, and March 16, 2009. Note that

any examination waivers and application denials have been addressed in separate

correspondence.

The NRC has approved the subject written examination and hereby authorizes you to

administer the written examination in accordance with Revision 9, Supplement 1, of NUREG-

1021, Operator Licensing Examination Standards for Power Reactors, during the week of

March 16, 2009.

This examination has undergone extensive review by my staff and representatives responsible

for operator training at your facility. Based on this review I have concluded that the examination

meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By

administering this examination, you also agree that it meets NUREG-1021 guidelines, and is

appropriate for measuring the qualifications of licensed operators at your facility. If you

determine that this examination is not appropriate for licensing operators at your facility, do not

administer the examination and contact me at (404) 562-4550.

G. Kilpatrick 2

Please contact your Chief Examiner, Mr. Frank Ehrhardt, at (404) 562-4611 if you have any

questions or identify any errors or changes in license level (RO or SRO) or type of examination

(partial or complete written examination and/or operating test) specified for each applicant on

the list of approved applicants.

Sincerely,

/ RA /

Malcolm T. Widmann, Chief

Operations Branch

Division of Reactor Safety

Docket Nos.: 50-400

License Nos.: NPF-63

G PUBLICLY AVAILABLE G NON-PUBLICLY AVAILABLE G SENSITIVE G NON-SENSITIVE

ADAMS: G Yes ACCESSION NUMBER:_________________________ G SUNSI REVIEW COMPLETE

OFFICE RII:DRS RII:DRS

SIGNATURE / RA / / RA /

NAME FEHRHARDT:btm MWIDMANN

DATE 3/ /2009 3/ /2009 3/ /2009

E-MAIL COPY? NO NO

OFFICIAL-RECORD-COPY DOCUMENT-NAME:--O:\HARRIS-EXAMINATIONS\INITIAL-EXAM-

2009301\CORRESPONDENCE\HAR MARCH 2009-301 APPROVAL LETTER [BTM].DOC