Inspection/Activity Plan 03/01/2009 - 06/30/2010
ML090630438
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 03/04/2009
From:
Reactor Projects Region 2 Branch 6
To:
References
Download: ML090630438 (2)


Text

Inspection / Activity Plan Page 1 of 2 03/04/2009 09:26:28 Report 22 03/01/2009 - 06/30/2010 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Sequoyah PSB1-RP

- RP OCCUPATIONAL INSPECTION WK1 (OUTAGE) 2 1, 2 IP Access Control to Radiologically Significant Areas 7112101 03/30/2009 04/03/2009 1, 2 IP ALARA Planning and Controls 7112102 03/30/2009 04/03/2009 1, 2 IP Radioactive Material Processing and Transportation 7112202 03/30/2009 04/03/2009 1, 2 IP Performance Indicator Verification 71151 03/30/2009 04/03/2009 EB3ISI

- UNIT 1 INSERVICE INSPECTION 2

1 IP Inservice Inspection Activities - PWR 7111108P 04/06/2009 04/10/2009 EB3TI172

- TI-172 RCS DM BUTT WELDS 1

1 IP Reactor Coolant System Dissimiliar Metal Butt Welds 2515/172 04/06/2009 04/10/2009 PSB1-RP

- RP OCCUPATIONAL INSPECTION WK2 (OUTAGE) 2 1, 2 IP Access Control to Radiologically Significant Areas 7112101 04/13/2009 04/17/2009 1, 2 IP ALARA Planning and Controls 7112102 04/13/2009 04/17/2009 1, 2 IP Radioactive Material Processing and Transportation 7112202 04/13/2009 04/17/2009 1, 2 IP Performance Indicator Verification 71151 04/13/2009 04/17/2009 PI&R

- PROBLEM IDENTIFICATION AND RESOLUTION 6

1 IP Identification and Resolution of Problems 71152B 07/13/2009 07/17/2009 1

IP Identification and Resolution of Problems 71152B 07/27/2009 07/31/2009 EB3-HS

- HEAT SINK 1

1, 2 IP Heat Sink Performance 7111107T 08/24/2009 08/28/2009 PSB1EP

- EMERGENCY PREPAREDNESS INSPECTION 1

1, 2 IP Alert and Notification System Testing 7111402 10/19/2009 10/23/2009 1, 2 IP Emergency Response Organization Augmentation Testing 7111403 10/19/2009 10/23/2009 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 10/19/2009 10/23/2009 1, 2 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 10/19/2009 10/23/2009 1, 2 IP Performance Indicator Verification 71151 10/19/2009 10/23/2009 EB3ISI

- UNIT 2 INSERVICE INSPECTION 1

2 IP Inservice Inspection Activities - PWR 7111108P 11/02/2009 11/06/2009 EB3TI172

- TI-172 RCS DM BUTT WELDS 1

2 IP Reactor Coolant System Dissimiliar Metal Butt Welds 2515/172 11/02/2009 11/06/2009 EB3SGISI

- UNIT 2 STEAM GENERATOR ISI 1

2 IP Inservice Inspection Activities - PWR 7111108P 11/09/2009 11/13/2009 OL EXAM

- INITIAL EXAM PREP 3

1 SEQUOYAH/JANUARY 2010 EXAM AT POWER FACILITIES V23287 12/07/2009 12/11/2009 PSB1-RP

- RP GROUND WATER INITIATIVE 1

1, 2 IP Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative 2515/173 12/07/2009 12/11/2009 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Inspection / Activity Plan Page 2 of 2 03/04/2009 09:26:28 Report 22 03/01/2009 - 06/30/2010 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Sequoyah OL EXAM

- INITIAL EXAM - WEEK 1 3

1 SEQUOYAH/JANUARY 2010 EXAM AT POWER FACILITIES V23287 01/18/2010 01/22/2010 OL EXAM

- INITIAL EXAM - WEEK 2 3

1 SEQUOYAH/JANUARY 2010 EXAM AT POWER FACILITIES V23287 01/25/2010 01/29/2010 CDBI

- COMPONENT DESIGN BASES INSPECTION 7

1, 2 IP Component Design Bases Inspection 7111121 03/01/2010 03/05/2010 1, 2 IP Component Design Bases Inspection 7111121 03/15/2010 03/19/2010 1, 2 IP Component Design Bases Inspection 7111121 03/29/2010 04/02/2010 1, 2 IP Component Design Bases Inspection 7111121 04/12/2010 04/16/2010 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure