Unit 2 - Notification of Conduct of a Triennial Fire Protection Baseline Inspection While Transition to 10 CFR Part 50.48(c) Is in Progress
ML090500164
Person / Time
Site: Nine Mile Point  Constellation icon.png
Issue date: 02/17/2009
From: Rogge J
Engineering Region 1 Branch 3
To: Polson K
Nine Mile Point
References
Download: ML090500164 (7)


Text

February 17, 2009 Mr. Keith J. Polson Vice President Nine Mile Point Nuclear Station, LLC P.O. Box 63 Lycoming, NY 13093-0063

SUBJECT:

NINE MILE POINT NUCLEAR STATION, UNIT 1 AND UNIT 2 - NOTIFICATION OF CONDUCT OF A TRIENNIAL FIRE PROTECTION BASELINE INSPECTION WHILE TRANSITION TO 10 CFR PART 50.48(c) IS IN PROGRESS.

Dear Mr. Polson:

The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)

Region I staff will conduct a triennial fire protection baseline inspection at Nine Mile Point Nuclear Station, Unit 1 and Unit 2 beginning in June 2009. The inspection team will be led by Keith Young from the NRC Region I office. The team will be composed of personnel from NRC, Region I. The inspection will be conducted in accordance with NRC inspection procedure 71111.05TTP, the NRCs baseline fire protection inspection procedure for plants in the process of implementing 10 CFR 50.48(c), NFPA 805. The inspection will focus on the fire protection program infrastructure and the adequacy of compensatory measures implemented. The inspectors will not routinely inspect or evaluate circuit related issues.

The schedule for the inspection is as follows:

Information gathering visit - Week of May 17, 2009 Weeks of onsite inspection - June 1 - 5, 2009, and June 15 - 19, 2009 The purposes of the information gathering visit are to obtain information and documentation needed to support the inspection, to become familiar with the station fire protection programs, fire protection features, and post-fire safe shutdown capabilities and plant layout, and as necessary, obtain plant specific site access training and badging for unescorted access. A list of the types of documents the team may be interested in reviewing and possibly obtaining, are listed in the enclosure. The team leader will contact you with specific document requests prior to the information gathering visit.

During the information gathering visit, the team will also discuss the following inspection support administrative details: office space size and location; specific documents requested to be made available to the team in their office spaces; arrangements for reactor site access, including radiation protection training, security, safety, and fitness for duty requirements; and the availability of knowledgeable plant engineering and licensing organization personnel to serve as points of contact during the inspection.

Mr. Keith J. Polson 2

We request that during the onsite inspection week you ensure that copies of analyses, evaluations, or documentation regarding the implementation and maintenance of the Nine Mile Point Nuclear Station, Unit 1 and Unit 2 fire protection programs, including post-fire safe shutdown capability, be readily accessible to the team for their review. Of specific interest are those documents which establish that your fire protection program satisfies NRC regulatory requirements and conforms to applicable NRC and industry fire protection guidance. Also, personnel should be available at the site during the inspection who are knowledgeable regarding those plant systems required to achieve and maintain safe shutdown conditions from inside and outside the control room, including the electrical aspects of the relevant post-fire safe shutdown analyses, reactor plant fire protection systems and features, and the Nine Mile Point Nuclear Station, Unit 1 and Unit 2 fire protection programs and their implementation.

Your cooperation and support during this inspection will be appreciated. If you have questions concerning this inspection, or the inspection teams information or logistical needs, please contact Keith Young, the team leader in the Region I Office at (610) 337-5293.

Sincerely,

/RA/

John F. Rogge, Chief Engineering Branch 3 Division of Reactor Safety Docket No.

50-220, 50-410 License No.

DPR-63, NPF-69

Enclosure:

List of Reactor Fire Protection Program Supporting Documents

Mr. Keith J. Polson 2

We request that during the onsite inspection week you ensure that copies of analyses, evaluations, or documentation regarding the implementation and maintenance of the Nine Mile Point Nuclear Station, Unit 1 and Unit 2 fire protection programs, including post-fire safe shutdown capability, be readily accessible to the team for their review. Of specific interest are those documents which establish that your fire protection program satisfies NRC regulatory requirements and conforms to applicable NRC and industry fire protection guidance. Also, personnel should be available at the site during the inspection who are knowledgeable regarding those plant systems required to achieve and maintain safe shutdown conditions from inside and outside the control room, including the electrical aspects of the relevant post-fire safe shutdown analyses, reactor plant fire protection systems and features, and the Nine Mile Point Nuclear Station, Unit 1 and Unit 2 fire protection programs and their implementation.

Your cooperation and support during this inspection will be appreciated. If you have questions concerning this inspection, or the inspection teams information or logistical needs, please contact Keith Young, the team leader in the Region I Office at (610) 337-5293.

Sincerely,

/RA/

John F. Rogge, Chief Engineering Branch 3 Division of Reactor Safety Docket No.

50-220, 50-410 License No.

DPR-63, NPF-69

Enclosure:

List of Reactor Fire Protection Program Supporting Documents SUNSI Review Complete: JFR (Reviewers Initials) ADAMS ACC# ML090500164 DOCUMENT NAME: G:\\DRS\\Engineering Branch 3\\Young\\NMP-U1&U2 FP 90 Day Letter-2008.doc After declaring this document An Official Agency Record it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRS RI/DRS NAME KAYoung/DS/KAY JFRogge/JFR DATE 02/17/2009 02/17/2009 OFFICIAL RECORD COPY

Mr. Keith J. Polson 3

cc w/encl:

M. Wallace, Vice - Chairman, Constellation Energy H. Barron, President, CEO & Chief Nuclear Officer, Constellation Energy Nuclear Group C. Fleming, Esquire, Senior Counsel, Nuclear Generation, Constellation Energy Group, LLC M. Wetterhahn, Esquire, Winston & Strawn T. Syrell, Director, Licensing, Nine Mile Point Nuclear Station J. Spath, Program Director, New York State Energy Research and Development Authority F. Murray, New York State Energy Research and Development Authority P. Eddy, New York State Department of Public Service C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law Supervisor, Town of Scriba P. Church, Oswego County Administator T. Judson, Central NY Citizens Awareness Network D. Katz, Citizens Awareness Network J. Evans, LIPA G. Detter, Manager, Corp Nuclear Safety and Security, Constellation Energy C. Adrienne Rhodes, Chairman and Executive Director, State Consumer Protection Board

Mr. Keith J. Polson 4

Distribution w/encl:

(via E-mail)

S. Collins, RA M. Dapas, DRA D. Roberts, DRS E. Cobey, DRS D. Lew, DRP J. Clifford, DRP S. Campbell, RI OEDO R. Nelson, NRR M. Kowal, NRR R. Guzman, NRR D. V. Pickett, NRR G. Dentel, DRP N. Perry, DRP J. Hawkins, DRP E. Knutson, SRI D. Dempsey, RI K. Kolek, DRP, OA J. Rogge, DRS K. Young, DRS Region I Docket Room (with concurrences)

ENCLOSURE Reactor Fire Protection Program Supporting Documentation

[Note: This is a broad list of the documents the NRC inspection team may be interested in reviewing, and possibly obtaining, during the information gathering site visit.]

1. The current version of the Fire Protection Program and Fire Hazards Analysis.
2. Current versions of the fire protection program implementing procedures (e.g.,

administrative controls, surveillance testing, and fire brigade.)

3. Fire brigade training program and pre-fire plans.
4. Post-fire safe shutdown systems and separation analysis.
5. Post-fire alternative shutdown analysis.
6. Piping and instrumentation (flow) diagrams showing the systems and components used to achieve and maintain hot standby and cold shutdown for fires outside the control room and those components used for those areas requiring alternative shutdown capability.
7. Plant layout and equipment drawings which identify the physical plant locations of hot standby and cold shutdown equipment.
8. Plant layout drawings which identify plant fire area delineation, areas protected by automatic fire suppression and detection, and the locations of fire protection equipment.
9. Plant layout drawings which identify the location of the post-fire emergency lighting units.
10. Plant operating procedures which would be used for shutdown from the control room with a postulated fire occurring in any plant area outside the control room, and procedures which would be used to implement alternative shutdown capability in the event of a fire in either the control or cable spreading room.
11. Maintenance and surveillance testing procedures for alternative shutdown capability and fire barriers, detectors, pumps and suppression systems. (Last completed copy.)
12. Maintenance procedures which routinely verify fuse breaker coordination in accordance with the post-fire safe shutdown coordination analysis.
13. A list of fire protection and post-fire safe shutdown related design change packages (including their associated 10 CFR 50.59 evaluations) and Generic Letter 86-10 evaluations.
14. The reactor plants IPEEE, results of any post-IPEEE reviews, and listings of actions taken/plant modifications conducted in response to IPEEE information.

2 Enclosure

15. Copies of AC and DC electrical system one line diagrams. (From offsite power grid connections down to the 120 volt level.)
16. Organization charts of site personnel down to the level of fire protection staff personnel.
17. A listing of the SERs which form the licensing basis for the reactor plants post-fire safe shutdown configuration.
18. A list of applicable codes and standards related to the design of plant fire protection features and evaluations of code deviations.
19. Procedures/instructions that govern the implementation of plant modifications, temporary modifications, maintenance, and special operations, and their impact on fire protection.
20. The three most recent fire protection QA audits and/or fire protection self-assessments.
21. Recent QA surveillances of fire protection activities.
22. A listing of open fire protection and fire safe shutdown related condition reports.
23. A listing of fire protection and fire safe shutdown condition reports closed in the past three years.
24. Fire protection system health reports (last 2).
25. Lesson plans and related training information for licensed and non-licensed operators for post-fire safe shutdown (including alternative shutdown).