MONTHYEARML0829503862008-10-24024 October 2008 Acceptance Review Revised Request to Extend the Inservice Inspection Interval for Reactor Vessel Weld Examinations (Relief Requests ISI-020 and ISI-021)-Calvert Cliffs Nuclear Power Plant, Unit No. 2 Project stage: Acceptance Review ML0833101232008-12-0505 December 2008 Request for Additional Information Proposed Relief Request ISI-020 for Reactor Vessel Weld Examinations - Calvert Cliffs Nuclear Power Plant, Unit No. 2 Project stage: RAI ML0835309802008-12-18018 December 2008 Response to Request for Additional Information: Ccnpp, Unit No. 2 Proposed Relief Request ISI-020 Project stage: Response to RAI ML0835309762008-12-18018 December 2008 Response to Request for Additional Information: Proposed Alternative ISI-020 Reactor Vessel Weld Examination Extension Project stage: Response to RAI ML0902305172009-01-23023 January 2009 Transmittal of Response to Request for Additional Information Calvert Cliffs 2 (Clarification): Proposed Alternative ISI-020 Reactor Vessel Weld Examination Extension Project stage: Response to RAI ML0902305182009-01-23023 January 2009 Response to Request for Additional Information Calvert Cliffs 2 (Clarification): Proposed Alternative ISI-020 Reactor Vessel Weld Examination Extension Project stage: Response to RAI ML0905400622009-02-18018 February 2009 Request to Extend the Inservice Inspection Interval for Reactor Vessel Weld Examinations - Relief Requests (ISI-022 and ISI-023) Project stage: Request ML0907100252009-03-11011 March 2009 Acceptance Review for Calvert Cliffs ISI-022 and ISI-023 (TAC Nos. ME0668 & ME0669) Project stage: Acceptance Review ML0909200772009-04-0808 April 2009 Safety Evaluation for Relief Requests ISI-020 & 021 Reactor Vessel Weld Examination Extension - Calvert Cliffs Nuclear Power Plant, Unit No. 2 (TAC Nos. MD9773 and MD9774) Project stage: Approval ML0930300522009-11-0909 November 2009 Relief Request ISI-022 & ISI-023 to Extend Reactor Vessel and Reactor Vessel Internal Weld Examinations-Calvert Cliffs Nuclear Power Plant, Unit 1 Project stage: Other ML1005396372010-03-0202 March 2010 Correction Letter to Relief Requests ISI-04-020 & ISI-04-022-Calvert Cliffs Nuclear Power Plant, Units 1 & 2 Project stage: Other 2009-11-09
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000336/20240032024-11-0707 November 2024 Integrated Inspection Report 05000336/2024003 and 05000423/2024003 and Apparent Violation and Independent Spent Fuel Storage Installation Inspection Report 07200008/2024001 IR 05000318/20240072024-11-0606 November 2024 Assessment Follow-Up Letter for Calvert Cliffs Nuclear Power Plant, Unit 2 (Report 05000318/2024007) IR 05000317/20240032024-10-22022 October 2024 Integrated Inspection Report 05000317/2024003, 05000318/2024003, and Independent Spent Fuel Storage Installation Report 07200008/2024001 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24283A0012024-10-0909 October 2024 Senior Reactor and Reactor Operator Initial License Examinations IR 05000317/20245012024-10-0707 October 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000317/2024501 and 05000318/2024501 ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification IR 05000317/20240052024-08-29029 August 2024 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2024005 and 05000318/2024005) ML24240A2462024-08-27027 August 2024 Submittal of the Reactor Vessel Material Surveillance Program Capsule Technical Report ML24240A1112024-08-27027 August 2024 Registration of Use of Casks to Store Spent Fuel ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000317/20240022024-08-0606 August 2024 Integrated Inspection Report 05000317/2024002 and 05000318/2024002 IR 05000317/20240102024-07-31031 July 2024 Age-Related Degradation Inspection Report 05000317/2024010 and 05000318/2024010 ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) ML24198A0442024-07-16016 July 2024 Inservice Inspection Report IR 05000317/20244012024-07-0909 July 2024 Security Baseline Inspection Report 05000317/2024401 and 05000318/2024401 ML24177A1832024-06-25025 June 2024 Inservice Inspection Report RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24161A0012024-06-0909 June 2024 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report ML24150A0522024-05-29029 May 2024 Operator Licensing Examination Approval ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24136A1962024-05-15015 May 2024 Independent Spent Fuel Storage Installation - Annual Radiological Environmental Operating Report IR 05000317/20240012024-05-0707 May 2024 Integrated Inspection Report 05000317/2024001 and 05000318/2024001 RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests 05000317/LER-2024-002, Emergency Diesel Generators Automatic Start Due to Loss of a 13kV Bus2024-04-29029 April 2024 Emergency Diesel Generators Automatic Start Due to Loss of a 13kV Bus 05000318/LER-2024-001, Manual Reactor Trip Due to 22 Steam Generator Feed Pump Trip2024-04-24024 April 2024 Manual Reactor Trip Due to 22 Steam Generator Feed Pump Trip ML24101A1942024-04-22022 April 2024 Closeout Letter for GL 2004-02 ML24114A0182024-04-18018 April 2024 Electronic Reporting of Occupational Exposure Reporting 05000318/LER-2023-004-01, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-04-12012 April 2024 Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000317/20240402024-04-11011 April 2024 95001 Supplemental Inspection Report 05000317/2024040 and Follow-Up Assessment Letter RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24082A0082024-03-22022 March 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 ML24078A1152024-03-18018 March 2024 10 CFR 50.46 Annual Report ML24059A0632024-03-15015 March 2024 Authorization and Safety Evaluation for Alternative Request ISI-05-021 (EPID L-2023-LLR-0006) - Non-Proprietary IR 05000317/20230062024-02-28028 February 2024 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2, (Reports 05000317/2023006 and 05000318/2023006 ML24052A0072024-02-14014 February 2024 Core Operating Limits Report for Unit 1, Cycle 27, Revision 0 ML24040A0962024-02-0909 February 2024 Notification of Readiness for NRC 95001 Inspection ML24040A1492024-02-0909 February 2024 Response to NRC Request for Additional Information Regarding Final Response to Generic Letter 2004-02 IR 05000317/20230042024-02-0101 February 2024 Integrated Inspection Report 05000317/2023004 and 05000318/2023004 ML24029A0102024-01-29029 January 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000317/2024010 and 05000318/2024010 ML24003A8872024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0033 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24011A0732024-01-11011 January 2024 Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping 05000318/LER-2023-003, Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip2024-01-0808 January 2024 Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip ML24005A0222024-01-0505 January 2024 Revised Steam Generator Tube Inspection Reports ML23304A0642024-01-0202 January 2024 Issuance of Amendment No. 349 to Modify the Long-Term Coupon Surveillance Program RS-23-125, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) ML23331A2992023-11-27027 November 2023 Submittal of Condition Prohibited by Technical Specifications Due to Failure to Sample Diesel Generator Fuel Oil Storage Tank IR 05000317/20230102023-11-20020 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000317/2023010 and 05000318/2023010 2024-09-06
[Table view] |
Text
Calvert Cliffs Nucl ear Power Plant 1650 Calvert Cliffs Parkway O ..,
tella io Nuclear Genera ion Group gy Lusby, Maryland 20657 January 23, 2009 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION: Document Contro l Desk
SUBJECT:
Calvert Cliffs Nuclear Power Plant Unit No.2; Docket No. 50-318 Response to Request for Additiona l Information Calvert Cliffs 2 (Clarification):
Proposed Alternative ISI-020 Reactor Vessel Weld Examination Extension (TAC No. MD9773)
REFERENCES:
(a) Letter from Mr. M. D. Flaherty (CCNPP) to Document Control Desk (NRC), dated October 1, 2008, Revised Request to Extend the Inservice Inspection Interval for Reactor Vessel Weld Examinations - Relief Requests (ISI-020 and ISI-021)
(b) Letter from Mr. D. V. Pickett (NRC) to Mr. J. A. Spina (CCNPP), dated December 5, 2008, Request for Additional Information Re: Proposed Relief Request ISI-020 for Reactor Vessel Weld Examination s - Calvert Cliffs Nuclear Power Plant, Unit No. 2 (TAC No. MD9773)
(c) Letter from Mr. M. D. Flaherty (CCNPP) to Document Control Desk (NRC), dated December 18, 2008, Response to Request for Additional Information Calvert Cliffs 2: Proposed Alternative ISI-020 Reactor Vessel Weld Examination Extension (TAC No. MD9773)
In Reference (a), we provided Relief Request ISI-020, requesting an alternative from the Code requirements pursuant to 10 CFR 50.55a(a)(3)(i). In Reference (b), the Nuclear Regulatory Commission staff requested additional information necessary to complete their review of ISI-020. Our response was provided in Reference (c). The NRC has requested clarification of our response to Question 1 (contained in Reference c). This information is provided in Attachment (1).
Should you have questions regarding this matter, please contact Mr. Jay S. Gaines at (410) 495-5219.
Very truly yours,
.f--~' U ~ ! ~
.i\u.-
) <;..)l ~
Mark D. Flaherty Manager-Engineering Services MDF/ALS/bjd
Attachment:
( 1) RAI Clarification -- Proposed Alternative ISI-020
Document Control Desk January 23, 2009 Page 2 cc: D. V. Pickett, NRC S. Gray, DNR S. 1. Collins, NRC Safety Program Manager, State of Maryland Resident Inspector, NRC