ML090080123

From kanterella
Jump to navigation Jump to search
Unit 1, Notification of Completion of Transfer of Nuclear Units to Exelon Generation Company, Llc., from Amergen Energy Company, LLC
ML090080123
Person / Time
Site: Oyster Creek, Clinton, Crane
Issue date: 01/08/2009
From: Cowan P
Exelon Generation Co
To:
Office of Nuclear Reactor Regulation
References
RA-09-005, RS-09-004, TMI-09-004
Download: ML090080123 (2)


Text

Exelon RS-09-004 RA-09-005 TMI-09-004 January 8, 2009 Director of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission 11555 Rockville Pike Rockville, MD 20852 Clinton Power Station, Unit 1 Facility Operating License No. NPF-62 NRC Docket No. 50-461 Oyster Creek Nuclear Generating Station Facility Operating License No. DPR-16 NRC Docket Nos. 50-219 & 72-15 Three Mile Island Nuclear Station, Unit 1 Facility Operating License No. DPR-50 NRC Docket No. 50-289

Subject:

Notification of Completion of Transfer of Nuclear Units to Exelon Generation Company, LLC

Reference:

NRC letters, Christopher Gratton (USNRC) to Charles G. Pardee (Exelon/AmerGen) "Order Approving Transfer of the Operating License and Conforming Amendment," dated December 23, 2008 (Three letters, one each involving Clinton Power Station, Oyster Creek Nuclear Generating Station, and Three Mile Island Nuclear Station, Unit 1)

In accordance with the Orders issued in the referenced letters, we are informing the Director of the Office of Nuclear Reactor Regulation of the completion of the transfer of the above nuclear units from AmerGen Energy Company, LLC to Exelon Generation Company, LLC. The closing of the transfer of the nuclear units occurred today, January 8,2009.

U. S. Nuclear Regulatory Commission January 8, 2009 Page 2 There are no regulatory commitments contained in this letter.

If you have any questions about this letter, please contact David Helker at (610) 765-5525.

Respectfully, Pamela Cowan Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC cc:

NRC Document Control Desk Regional Administrator - NRC Region I Regional Administrator - NRC Region III C. Gratton - NRC Project Manager, NRR - (Exelon/AmerGen Fleet)

NRC Senior Resident Inspector - Clinton Power Station, Unit 1 NRC Senior Resident Inspector - Oyster Creek Nuclear Generating Station NRC Senior Resident Inspector - Three Mile Island Nuclear Station, Unit 1 NRC Project Manager, NRR - Clinton Power Station, Unit 1 NRC Project Manager, NRR - Oyster Creek Nuclear Generating Station NRC Project Manager, NRR - Three Mile Island Nuclear Station, Unit 1 Illinois Emergency Management Agency - Division of Nuclear Safety Director, Bureau of Radiation Protection - Pennsylvania Department of Environmental Resources Director, Bureau of Nuclear Engineering, New Jersey Department of Environmental Protection Chairman, Board of County Commissioners of Dauphin County, PA Chairman, Board of Supervisors of Londonderry Township, PA Mayor of Lacey Township, Forked River, NJ R. R. Janati, Commonwealth of Pennsylvania TMI File No. 08040