Summary of Telephone Conf Call Held on Sept. 26, 2008 Between NRC and Firstenergy Nuclear Operating Company Concerning the RAI Pertaining to the Refurbishment Activities at the Bvps. Units 1&2 LRA
ML083500325
Person / Time
Site: Beaver Valley
Issue date: 01/21/2009
From: Kent Howard
License Renewal Projects Branch 2
To:
FirstEnergy Nuclear Operating Co
Sayoc, Manny, NRR/DLR/RLRB 415-1924
References
Download: ML083500325 (6)


Text

January 21, 2009 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY:

Beaver Valley Power Station, Units 1 and 2

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON SEPTEMBER 26, 2008, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY CONCERNING A REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of FirstEnergy Nuclear Operating Company held a telephone conference call on September 26, 2008, to discuss follow-up questions for the B.2.6-2 Request for Additional Information concerning the Beaver Valley Power Station, Units 1 and 2, license renewal application. Enclosure 1 is a list of the conference call participants. Enclosure 2 is a summary of the telephone conference discussions.

If you have any questions concerning the NRC staffs summary of this telephone conference, please contact Mr. Kent Howard at 301-415-2989 or by e-mail at Kent.Howard@nrc.gov.

Sincerely

\\RA\\

Kent Howard, Sr., Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412

Enclosures:

As stated cc w/encls.: See next page

ML083500325 OFFICE:

LA:DLR PM:DLR:RPB2 PM:DLR:RPB2 BC: DLR:RPB2 NAME:

SFigueroa ESayoc KHoward DWrona DATE:

01/14/09 01/15/09 01/15/09 01/21/09

ENCLOSURE 1 LIST OF PARTICIPANTS FOR THE TELEPHONE CONFERENCE CALL FOR BEAVER VALLEY POWER STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION September 26, 2008 PARTICIPANTS AFFILIATIONS Kent Howard U.S. Nuclear Regulatory Commission (NRC)

John Fair NRC On Yee NRC Jim Davis NRC Robert Sun NRC Cliff Custer FirstEnergy Nuclear Operating Company (FENOC)

John Thomas FENOC Larry Hinkle FENOC Jim Hester FENOC

ENCLOSURE 2

SUMMARY

OF TELEPHONE CONFERENCE CALL FOR BEAVER VALLEY POWER STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION September 26, 2008 In this telephone conference call, the U.S. Nuclear Regulatory Commission (the NRC or staff) and representatives from FirstEnergy Nuclear Operating Company (FENOC) discussed issues related to the request for additional information (RAI) B.2.6-2, concerning leaks related to bolting. These leak issues are monitored and corrected using the FENOC Corrective Action Program. As indicated in the RAI response, the applicant relies upon this program to determine inspection frequency and required response in order to address leaks. However the staff determined that this program has no specific requirement, checks, or limiting processes which would ensure that the inspection frequency does not decrease to less than the recommended biweekly frequency in the generic aging lessons learned (GALL) Report. In the telephone conference, the staff indicated that the applicant did not provide sufficient information to address all issues in the RAI, that the program is not consistent with the associated elements in the GALL Report, and that the applicant should have identified the program as an exception to the GALL Report. The applicant agreed to supplement the RAI response with an expansion of technical basis on how the program in conjunction with other FENOC programs, actually call for inspection frequencies that at least meet the inspection requirements recommended in the GALL Report.

Letter to FirstEnergy Nuclear Operating Company from K. Howard, dated January 21, 2009

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON SEPTEMBER 26, 2008, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY CONCERNING THE REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSbwb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter KHoward ESayoc NMorgan MModes, RI PCataldo, RI DWerkheiser, RI

Beaver Valley Power Station, Units 1 and 2 cc:

Joseph J. Hagan President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-19 76 South Main Street Akron, OH 44308 James H. Lash Senior Vice President of Operations and Chief Operating Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Danny L. Pace Senior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Jeannie M. Rinckel Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Paul A. Harden Vice President, Nuclear Support FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 David W. Jenkins, Attorney FirstEnergy Corporation Mail Stop A-GO-15 76 South Main Street Akron, OH 44308 Manager, Fleet Licensing FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH 44308 Director, Fleet Regulatory Affairs FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH 44308 Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-A P.O. Box 4, Route 168 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077 Cliff Custer FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077

Beaver Valley Power Station, Units 1 and 2 cc:

Steve Dort FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Mike Banko FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077