UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II SAM NUNN ATLANTA FEDERAL CENTER 61 FORSYTH STREET, SW, SUITE 23T85 ATLANTA, GEORGIA 30303-8931 December 4, 2008 Mr. Christopher L. Burton Vice President Carolina Power & Light Company Shearon Harris Nuclear Plant P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165

SUBJECT:

REQUALIFICATION PROGRAM INSPECTION - SHEARON HARRIS NUCLEAR PLANT

Dear Mr. Burton:

In a telephone conversation on November 24, 2008, Mr. Edwin Lea, NRC Senior Operations Engineer, and Ken Bailey, Supervisor of Operator Continuing Training, made arrangements for the NRC to inspect the licensed operator requalification program at the Shearon Harris Nuclear Plant. The inspection is planned for the week of January 12, 2009, which coincides with your regularly scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program. It is our understanding that your simulator is committed to ANSI/ANS-3.5-1998, AAmerican National Standard for Nuclear Power Plant Simulators for use in Operator Training and Examination.@

In accordance with 10 CFR 55.59(c), the NRC has requested that you submit the material as specified in the Enclosure, in order to support the NRC's inspection program needs. Mr. Bailey has been advised of this request and provided with the name and address of the NRC lead inspector assigned to this inspection.

This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number Part 55 (3150-0018), which expires on June 30, 2009.

The public reporting burden for this collection of information is estimated to average four hours per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail at SLF@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0101), Office of Management and Budget, Washington, DC 20503.

XG SUNSI REVIEW COMPLETE OFFICE RII:DRS RII:DRS RII:DRP SIGNATURE

/RA/

/RA/

/RA/

NAME ELea MWidmann RMusser DATE 12/4/2008 12/4/2008 12/4/2008 12/ /2008 12/ /2008 12/ /2008 12/ /2008 E-MAIL COPY?

YES NO YES NO YES NO YES NO YES NO YES NO YES NO

CP&L 3

cc w/encl:

Brian C. McCabe Manager Nuclear Regulatory Affairs Progress Energy Electronic Mail Distribution Paul Fulford Manager Performance Evaluation and Regulatory Affairs PEB5 Carolina Power & Light Company Electronic Mail Distribution R. J. Duncan, II Vice President Nuclear Operations Carolina Power & Light Company Electronic Mail Distribution Mr. G. Kilpatrick Training Manager Harris Progress Energy Carolinas, Inc.

Electronic Mail Distribution Kimberly Harshaw Manager Support Services Progress Energy Carolinas, Inc.

Electronic Mail Distribution David H. Corlett Supervisor Licensing/Regulatory Programs Carolina Power & Light Company Electronic Mail Distribution (cc: w/encl - See Page 4)

David T. Conley Associate General Counsel Legal Dept.

Progress Energy Service Company, LLC Electronic Mail Distribution John H. O'Neill, Jr.

Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washington, DC 20037-1128 Beverly O. Hall Chief, Radiation Protection Section Department of Environmental Health N.C. Department of Environmental Commerce & Natural Resources Electronic Mail Distribution Public Service Commission State of South Carolina P.O. Box 11649 Columbia, SC 29211 Chairman North Carolina Utilities Commission Electronic Mail Distribution Robert P. Gruber Executive Director Public Staff - NCUC 4326 Mail Service Center Raleigh, NC 27699-4326 Herb Council Chair Board of County Commissioners of Wake County P.O. Box 550 Raleigh, NC 27602

CP&L 4

cc: w/encl Tommy Emerson Chair Board of County Commissioners of Chatham County 186 Emerson Road Siler City, NC 27344 Progress Energy Carolina, Inc.

ATTN: Mr. G. Kilpatrick Training Manager Harris Energy & Env. Center Shearon Harris Nuclear Power Plant P.O. Box 327, State Road 1127 New Hill, NC 27562-0165 Kelvin Henderson Plant General Manager Carolina Power and Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution Senior Resident Inspector Carolina Power and Light Company Shearon Harris Nuclear Power Plant U.S. NRC 5421 Shearon Harris Rd New Hill, NC 27562-9998

CP&L 5

Letter to Christopher L. Burton from Malcolm T. Widmann dated December 4, 2008

SUBJECT:

REQUALIFICATION PROGRAM INSPECTION - SHEARON HARRIS NUCLEAR PLANT Distribution w/encl:

RIDSNRRDIRS PUBLIC M. Vaaler, NRR (PM - Harris)

Enclosure Materials Request List The items listed below are being requested per telephone conversation on November 24, 2008, to support the upcoming IP-71111.11 inspection in January 2009 at the Shearon Harris Nuclear Plant. Items in paragraph "A" are to be sent prior to the inspection. They must be received in our office by January 5, 2009. Please have the items listed in paragraph "B" ready for our review upon arrival on January 12, 2009.

A.

In-office inspection material:

1.

Exam results since last requal inspection, copies of exam that had pass/failure rates significantly outside the average.

2.

A copy of the last biennial requal written examination (RO/SRO exams) and all biennial re-takes.

3.

List of personnel scheduled for requal testing the week of 01/12/09.

4.

Copies of simulator scenarios for this exam (when available).

5.

Program evaluation for the previous 2 years training cycle.

6.

A list of all personnel that reactivated their licenses since the last requal inspection.

7.

Simulator:

List of all open simulator discrepancies (SSR=s).

Copy of the Simulator Management and Configuration Procedures.

List of all closed simulator SSR=s for last 12 months.

List of Simulator Performance tests.

B.

On-site inspection material:

1.

Condition Reports and LERs resulting from human performance errors since the last requal inspection.

2.

All training feedback forms since the last requal inspection.

3.

All remedial training packages since the last requal inspection.

4.

Security badge and HP printouts for all (selected) personnel that reactivated their licenses since the last requal inspection.

5.

Copies of the reference list for all administrative procedures which direct the training process, including development of training and test materials, remedial training, modifications, plant and industry experience.

Enclosure 2

6.

Records for maintenance of active licenses - time on shift 56/60 hrs/qtr since the last requal inspection.

7.

All Medical Exam Records with a copy of the individual=s license attached.

8.

Simulator JPMs and in-plant JPMs that have been administered for this requal exam.

9.

Copy of an Organizational Chart for the training department including the simulator group.

10.

Complete list of all licensed individuals complete with license restrictions.

11.

Security procedures for the simulator.