ML083380490

From kanterella
Jump to navigation Jump to search
Entergy Nuclear Presentation Regarding Vermont Yankee - October 14, 2008
ML083380490
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 10/14/2008
From:
Entergy Nuclear Operations
To:
NRC Region 1
Jackson D RGN-I/DRP/PB2/610-337-5306
Shared Package
ML083380467 List:
References
Download: ML083380490 (80)


Text

Vermont Yankee Cooling Tower Update October 14, 2008 ML083380490

Agenda

Introductions

Basic Plant Overview

Cooling Tower Overview

  • Normal Cooling Function
  • Safety Function

Cooling Tower Events

  • Three Events
  • August 2007
  • July 2008
  • September 2008
  • Event Causes and Corrective Actions
  • Event Summary

Long Range Planning

Introductions

Introductions

Ted Sullivan, Entergy Site Vice President

Chris Wamser, Gen. Manager Plant Operations

John Dreyfuss, Director, Nuclear Safety Assurance

Norm Rademacher, Director of Engineering

Basic Plant Operation

River Tower Tower Condenser

Functions of the Cooling Towers

Cooling Tower Functions Normal Cooling Function Safety Function

Cooling Function

Cooling Function Purpose Modes of Operation Design Overview Design Features

Cooling Function - Purpose Cool River Water prior to return to Connecticut River Maintain Environmental Conditions for river NPDES Thermal Discharge Permit

Cooling Water Modes of Operation

Cooling Water Modes Open Closed

Intake Discharge Cooling Towers C

o n

d Open Cycle Towers River

Intake Discharge Cooling Towers C

o n

d Closed Cycle Towers River

Modes of Operation - Summary Cooling Tower operation is dictated by River Conditions

  • Season
  • River Flow
  • River Temperature

Cooling Tower Design

Cooling Tower Design go to page 21

AIR FLOW WATER VAPOR HEAT REJECTED go to page 25

Back to pg. 21

Back to pg. 21

Cooling Tower Design Features

Design Features Two 500 Long Towers

  • Tower 1 (East)
  • Tower 2 (West) 11 Cells per Tower Each Cell has one fan and motor Water distribution system go to page 28

Design Features -

Water Distribution Two Distribution Headers per Tower 90,000 GPM each Multiple Sections, Bell and Spigot Joint Design Pipe Size Varies: 60 to 24 Water Deck / Distribution Valves Fill Material go to page 32

Back to pg. 28

Back to pg. 28

Design Features -

Structural Support Loads:

3/4 Water (primary) 3/4 Fan/motor (secondary)

Saddle Configuration - HOLDS UP PIPE Columns - support water and fans Joints go to page 35

Back to pg. 32

Safety Function

Safety Function Safety Related Cell 2-1 Seismic Qualification Cell 2-2 Alternate Cooling - Loss of Intake Independent from normal Cooling Function

Photo Safety-related Seismic Design

Safety Related Cell CT2-1 Provides Backup Source of Cooling Plant Condenser Discharge to River Safety Equipment Cooled Shutdown Cooling System Backup Electricity Generators Spent Fuel Pool

Independent Safety Piping

Cooling Tower Events

Cooling Tower Events August 2007: Cell 2-4 Failure July 2008: Support Saddle Failures September 2008: Distribution Header Leak

Cell 2-4 Failure August 2007

Cell 2-4 Failure Causes of Event Corrective Actions

Cell 2-4 Failure -

Cause of Event Two support columns failed Failure of B Columns caused Distribution Header to sag

  • Loosened slip joints and caused large leaks Additional water increased weight on remaining support columns Other Support columns overloaded and failed Resulted in a partial collapse go to page 47

C

C B

C B

A S

C B

A

C B

A

C B

A B Column Failure Point

Cell 2-4 Failure - Causal Investigation Root Cause:

Support columns failed due to overload condition Other Causes:

3/4 Inadequate Inspection Methods of Wood Structure 3/4 Inadequate Preventative Maintenance Contributing Cause: Design of Fill Material

Cell 2-4 Failure -

Corrective Actions Rebuilt Cell 2-4 Completed Extent of Condition Inspections and Repairs Fully Revised Inspection Procedures and Acceptance Criteria Established 2008 Cooling Tower Project Plan

Cell 2-4 Failure -

Corrective Actions Phase 1 of Long Range Plan - Completed May 2008 1/3 Replacement - (Bay 4)

New Structural Member Material: Fiberglass Reinforced Plastic (FRP)

New Fill Material Extent of Condition Repairs Used External/Fleet Technical Expertise Long Range Plan go to page 63

2008 Cooling Tower Project (Phase 1)

Fire Wall Typical Cooling Tower Cell Fire Wall Plenum Area Walkway Distribution Header Bay 1 Bay 2 Bay 3 Bay 4 Bay 5 Bay 6 Bay 7 A

B C

S A

B C

S

57

28

July 2008 Event

July 2008 Event Field Observation Leak in Distribution Header (Cell 1-1 East, ~60 gpm)

Broken/Degraded Saddles (4 in tower 1, 2 in tower 2)

Cause of Event Wooden Saddle to FRP Connection Identified by VY Design Engineering prior to placing tower in service Incorrect Technical Assessment by Engineering/Vendor Limited to FRP/Wood Saddles go to page 67

Back to pg. 64

July 2008 Event Corrective Actions Full extent of condition walkdowns Repaired all saddles/connections Revised design documentation

September 2008 Event

Distribution Header Leak -

Initial Actions

Operations Field Observations:

Potential depression in fan deck Leak in distribution header piping

Cooling water to towers promptly secured

Remained at 100% plant power output for ~ 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />

Lowered power to 55% due to river flow

Distribution Header Leak -

Inspections

Walkdowns performed using revised inspection procedures

Leak NOT caused by structural problem

Cause: Packing leak attributed to start/stop of cooling water pumps (not uncommon)

Additional inspections - 8 degraded columns:

  • 1 Level 1 - replace; unrelated to leak
  • 3 Level 2 adjacent to Level 1 - replace
  • 4 Level 2 - address next maintenance window go to page 72

Inspection Acceptance Criteria Level 1: Replace immediately Level 2:

9 If adjacent to Level 1, replace immediately 9 Otherwise, replace next maintenance period Level 3: Inspect/monitor

Distribution Header Leak -

Corrective Actions Leak repaired Replaced support columns

Cooling Tower Event Summary

Cooling Tower Event Summary

Safety function not affected

Maintained compliance with federal/state discharge permit

No impact from power uprate

Revised Inspection procedures/organizational sensitivity effective

Substantial investment in reliability improvements

Long Range Plan

Long Range Plan Phased approach based on maintenance availability 3/4 Phase 1: Bay 4 Complete 3/4 Phase 2: Bay 2 Spring 2009 3/4 Phase 3: Bay 6 Spring 2010 Other inspections/repairs based on revised methods/procedures

Phase 1 Bay 1 Bay 2 Bay 3 Bay 4 Bay 5 Bay 6 Fire Wall Bay 4 C & B Supports Water pipe header / water deck Typical Cooling Tower Cell Bay 7 Fire Wall

Bay 1 Bay 2 Bay 3 Bay 4 Bay 5 Bay 6 Bay 7 Fire wall Bay 2 C & B Supports Water pipe header / water deck Typical Cooling Tower Cell Phase 2 Fire wall

Water pipe header / water deck Typical Cooling Tower Cell Phase 3 Bay 1 Bay 2 Bay 3 Bay 4 Bay 5 Bay 6 Bay 7 Bay 6 C & B Supports Fire wall Fire wall