MONTHYEARML24250A1062024-09-0606 September 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24234A2772024-08-21021 August 2024 NRR E-mail Capture - Final RAI - Constellation Energy, LLC - Fleet Request - Proposed Alternative Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds (L-2024-LLR-0031) ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24156A0082024-05-31031 May 2024 NRR E-mail Capture - Constellation Energy, LLC - Fleet Request - Acceptance of Proposed Alternative Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds (L-2024-LLR-0031 ML24131A0612024-05-10010 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24222A4092024-05-0303 May 2024 NRR E-mail Capture - Request for Additional Information Regarding Reactor Water Cleanup (RWCU) Pump Rooms - L-2023-LLA-0118 ML24122B5072024-05-0101 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-591, Revision 0 ML24064A1222024-02-0606 February 2024 Biennial Problem and Identification Inspection Request for Information ML23363A0302023-12-29029 December 2023 NRR E-mail Capture - Preliminary RAIs for Clinton Partial Site Release ML23338A0402023-12-0404 December 2023 NRR E-mail Capture - Ready for Clean TS Pages and Updated Review Hours for Clinton Power Station, Unit 1, Request for License Amendment to Revise Technical Specifications Section 3.8.3 ML23328A0132023-11-22022 November 2023 Supplement - Security Rule Exemption Request – ISFSI Docket No. Reference (L-2023-LLE-0028) ML23304A0162023-10-30030 October 2023 NRR E-mail Capture - Final RCI - Constellation Energy Generation, LLC - LaSalle 1 & 2 - Exemption from Security Rule (L-2023-LLE-0028) ML23268A0022023-09-22022 September 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-264-A, Revision 0 ML23264A1512023-09-21021 September 2023 Notification of Upcoming Biennial Problem Identification and Resolution Inspection LaSalle and RFI ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC – Fleet Request – License Amendment Request to Adopt TSTF-580, Revision 1 ML23261A0032023-09-15015 September 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton Amendment Request to Revise Timing of Reactor Water Cleanup Isolation Valves ML23237B3972023-08-24024 August 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Alternative Request to Use Updated BWRVIP Guidelines ML23230B1682023-08-18018 August 2023 NRR E-mail Capture - Clinton Power Station, Unit 1, Preliminary Requests for Additional Information (Rais) Related to the Amendment Request to Revise Diesel Generator Starting Air Technical Specifications ML23219A2142023-08-0404 August 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton Request for Partial Site Release ML23194A1102023-07-13013 July 2023 NRR E-mail Capture - Non-acceptance of Clinton Request for Partial Site Release ML23163A2292023-06-12012 June 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-580, Revision 1 ML23153A1562023-06-0202 June 2023 NRR E-mail Capture - RAI LaSalle pressure-temperature Limits Report (PTLR) Amendment Request ML23151A6602023-05-31031 May 2023 NRR E-mail Capture - LaSalle County Station, Units 1 and 2 - Acceptance of I4R-14 ML23150A2482023-05-25025 May 2023 NRR E-mail Capture - RAI Re LaSalle Downcomer Analysis Amendment Request ML23095A1892023-04-0505 April 2023 NRR E-mail Capture - LaSalle County Station, Units 1 and 2 - Audit Plan PTLR Amendment Request ML23087A0122023-03-28028 March 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton License Amendment Request to Revise Technical Specifications 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air (L-2023-LLA-0034) ML23074A0372023-03-14014 March 2023 NRR E-mail Capture - (External_Sender) Implementation of Exigent Amendment ML23044A0452023-02-13013 February 2023 NRR E-mail Capture - LaSalle County Station, Units 1 and 2 - Acceptance of Requested Licensing Action License Amendment Request to Revise Lower Downcomer Braces Analysis ML23046A1132023-02-13013 February 2023 Transmittal Email, Paul Bessette to Gibson, 2/13/23, Filing of Formal Opposition to PG&E Exemption Request ML23033A0332023-02-0101 February 2023 NRR E-mail Capture - NRC Acceptance Review of Clinton License Amendment Request to Adopt TSTF-332 (L-2023-LLA-0007) ML23052A2042023-01-10010 January 2023 E-mail from Paul Bessette Dated 01/10/2023 Regarding Diablo Canyon ML22357A0382022-12-23023 December 2022 NRR E-mail Capture - LaSalle County Station, Units 1 and 2 - Acceptance of Requested Licensing Action License Amendment Request to Relocate the Pressure and Temperature Limit Curves ML22354A2622022-12-20020 December 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Request to Use Certain Provisions of the 2019 Edition of the ASME BPV Code, Section XI ML22301A0902022-10-28028 October 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-301, Revision 2 ML22256A0112022-09-12012 September 2022 NRR E-mail Capture - Request for Additional Information LaSalle County Station, Units 1 and 2 and Quad Cities Nuclear Power Station, Units 1 and 2 License Amendments Related to Fuel Storage ML22200A0782022-07-19019 July 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request to Use Honeywell Mururoa V4F1 R Supplied Air Suits ML22173A0382022-06-21021 June 2022 NRR E-mail Capture - Request for Additional Information (RAI) Regarding Clinton License Amendment Request for Secondary Containment Design Basis (L-2022-LLA-0055) ML22165A1902022-06-14014 June 2022 NRR E-mail Capture - NRC Acceptance Review of Clinton Request to Adopt TSTF-230 (L-2022-LLA-0076) ML22165A1912022-06-14014 June 2022 NRR E-mail Capture - NRC Acceptance Review of Clinton Request to Adopt TSTF-269 (L-2022-LLA-0077) ML23089A0182022-05-24024 May 2022 NRR E-mail Capture - Clinton Power Station Acceptance Review Results - Submittal of Preliminary Decommissioning Cost Estimate and Spent Fuel Management Plan ML22138A4112022-05-18018 May 2022 NRR E-mail Capture - Lasalle 1 and 2 - (RAI) License Amendment Request Regarding New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies, with Changes to TS Sections 4.3.1 and 5.6.5 (EPID-L-2021-LLA-0124) ML22126A0392022-05-0606 May 2022 NRR E-mail Capture - Lasalle 1 and 2 Draft (RAI) License Amendment Request Regarding New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies, with Proposed Changes to TS Sections 4.3.1 and 5.6.5 ML22116A0422022-04-26026 April 2022 NRR E-mail Capture - NRC Acceptance Review of Clinton License Amendment Request to Revise Secondary Containment Design Basis ML22066A7622022-03-0707 March 2022 NRR E-mail Capture - Verbal Authorization - EPID-L-2022-LLR-0028, LaSalle Unit 1 Request for Alternative Examination for Repairs of Flow Control Valves 1B33-F060A and 1B33-F060B ML22062B0232022-03-0303 March 2022 NRR E-mail Capture - EPID-L-2022-LLR-0028, LaSalle Unit 1, Request for Additional Information (Rai), LaSalle Unit 1, Relief Request I4R-13 Relief from Code Examinations for 1B33-F060A and 1B33-F060B Repairs ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22157A3872022-01-28028 January 2022 Post Exam Submittal Letter Clinton 22 ML22020A0692022-01-14014 January 2022 NRR E-mail Capture - (External_Sender) IEMA Response: State Consultation - LaSalle 1 and 2: License Amendment Request Re; Revision of Technical Specifications to Incorporate GNF CRDA Methodology ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles 2024-09-06
[Table view] |
Text
From: Stephen Sands Sent: Wednesday, December 03, 2008 12:18 PM To: 'Alison.MacKellar@exeloncorp.com'
Subject:
Relief Request CR-26 Acceptance Review Importance: High
- Alison, This e-mail is to inform Exelon that the NRC has formally accepted the Relief Request CR-26, Inservice Inspection Program Relief Regarding Examination Coverage for Second 10-Year Inservice Inspection Interval, dated October 1, 2008, for review. CVIB found the submittals dated October 1, 2008 and the supplemental information dated November 18, 2008, acceptable to review under LIC-109. However, this acceptance does not necessarily mean the NRC staff will not need additional information, once we get involved with the review.
Stephen Sands Division of Operating Reactors Clinton & LaSalle Project Manager Licensing Project Branch 3-2 Phone: 301-415-3154 E-mail: Stephen.Sands@nrc.gov E-mail Properties Mail Envelope Properties ()
Subject:
Relief Request CR-26 Acceptance Review Sent Date: 12/03/2008 12:09:22 PM Received Date: 12/03/2008 12:18:00 PM From: Stephen Sands Created By: Stephen.Sands@nrc.gov Recipients:
Alison.MacKellar@exeloncorp.com ('Alison.MacKellar@exeloncorp.com')
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 8194 12/03/2008 Options Expiration Date:
Priority: olImportanceHigh ReplyRequested: False Return Notification: False Sensitivity: olNormal Recipients received: