TAC:MD8800, Steam Generator Tube Integrity (Approved, Closed) |
|
MONTHYEARET 08-0009, Revision to Technical Specification (TS) 5.5.9, Steam Generator (SG) Program for Interim Alternate Repair Criteria2008-02-0808 February 2008 Revision to Technical Specification (TS) 5.5.9, Steam Generator (SG) Program for Interim Alternate Repair Criteria Project stage: Request ML0805002232008-02-13013 February 2008 License Amendment Request to Revise Technical Specification (TS) Sections 5.5.9, Steam Generator (SG) Program and TS 5.6.10, Steam Generator Tube Inspection Report for Interim Alternate Repair Criterion Project stage: Other RS-08-016, Application for Steam Generator Tube Interim Alternate Repair Criteria Technical Specification Amendment2008-02-25025 February 2008 Application for Steam Generator Tube Interim Alternate Repair Criteria Technical Specification Amendment Project stage: Request ML0808502562008-03-21021 March 2008 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specification (TS) Sections 5.5.9, Steam Generator Program and TS 5.6.10, Steam Generator Tube Inspection Report, For.. Project stage: Response to RAI ML0808602482008-03-21021 March 2008 Response to Request for Additional Information Related to License Amendment Request for an Interim Alternate Repair Criterion to Technical Specification 5.5.9, Steam Generator (SG) Program Project stage: Response to RAI RS-08-031, Response to Request for Additional Information Regarding Application for Steam Generator Tube Interim Alternate Repair Criteria Technical Specification2008-03-27027 March 2008 Response to Request for Additional Information Regarding Application for Steam Generator Tube Interim Alternate Repair Criteria Technical Specification Project stage: Response to RAI NRC 2008-0034, License Amendment Request 257, Technical Specifications 5.5.8 and 5.6.8, Steam Generator Program & Steam Generator Tube Inspection Report, Interim Alternate Repair Criteria (Iarc) for Steam Generator Tube Repair2008-05-28028 May 2008 License Amendment Request 257, Technical Specifications 5.5.8 and 5.6.8, Steam Generator Program & Steam Generator Tube Inspection Report, Interim Alternate Repair Criteria (Iarc) for Steam Generator Tube Repair Project stage: Request NRC 2008-0056, Transmittal of Supplement to License Amendment Request 257 to Revise Technical Specifications 5.5.8 and 5.6.8 to Incorporate an Interim Alternate Repair Criterion2008-07-18018 July 2008 Transmittal of Supplement to License Amendment Request 257 to Revise Technical Specifications 5.5.8 and 5.6.8 to Incorporate an Interim Alternate Repair Criterion Project stage: Supplement ML0823409242008-08-20020 August 2008 Request for Hearing and Leave to Intervene, Point Beach Nuclear Plant Project stage: Request ML0825505612008-09-24024 September 2008 Notice of Issuance of Amendment to Renewed Facility Operating License and Final Determination of No Significant Hazard Consideration Project stage: Other ML0825408582008-09-25025 September 2008 Request for Withholding Information from Public Disclosure for Point Beach Nuclear Plant, Unit 1 (Tac No. MD8800) Project stage: Withholding Request Acceptance ML0827605182008-09-29029 September 2008 Notification of Significant Licensing Action Re Amendment Application Dated May 28, 2008 Project stage: Other ML0825408832008-10-0707 October 2008 Issuance of License Amendment, Technical Specification 5.5.8 and 5.6.8 Project stage: Approval 2008-03-27
[Table View] |
|
---|
Category:Legal-Pleading
MONTHYEARML22001A0022022-01-0101 January 2022 Notice of Withdrawal of Mitzi Young on Behalf of NRC Staff ML21257A2402021-09-14014 September 2021 NextEra Energy Point Beach, LLCs Brief in Opposition to Physicians for Social Responsibility Wisconsins Appeal of LBP-21-05 ML21257A4582021-09-14014 September 2021 NRC Staffs Brief in Opposition to Physicians for Social Responsibility Wisconsins Appeal of LBP-21-5 ML21257A4672021-09-14014 September 2021 NRC Staffs Brief in Opposition to Physicians for Social Responsibility Wisconsins Appeal of LBP-21-5 (Corrected) ML21232A6992021-08-20020 August 2021 Notice of Appeal of LBP-21-05 by Petitioner Physicians for Social Responsibility Wisconsin and Brief in Support of Appeal ML21232A7002021-08-20020 August 2021 Notice of Appeal of LBP-21-05 by Petitioner Physicians for Social Responsibility Wisconsin and Brief in Support of Appeal (Refiled) ML21141A0972021-05-21021 May 2021 NextEra Energy Point Beach, Llc'S Answer Opposing the Physicians for Social Responsibility Wisconsin'S Amendment of Contention 2 ML21141A0422021-05-21021 May 2021 NRC Staff'S Answer to Physicians for Social Responsibility Wisconsin'S Motion for Leave to File Amended Proposed Contention 2 ML21116A5782021-04-26026 April 2021 Physicians for Social Responsibility, Wisconsin, Reply in Support of Petition for Leave to Intervene in Point Beach Plant Subsequent License Renewal Proceeding, and Requesting an Adjudicatory Hearing ML21109A3872021-04-19019 April 2021 NRC Staff'S Answer Opposing Physicians for Social Responsibility Wisconsin'S Petition to Intervene ML21109A1342021-04-19019 April 2021 Notices of Appearance for David R. Lewis, Anne R. Leidich, and Steve Hamrick on Behalf of NextEra Energy Point Beach, LLC ML21109A1332021-04-19019 April 2021 NextEra Energy Point Beach, Llc'S Answer Opposing the Physicians for Social Responsibility Wisconsin'S Petition for Leave to Intervene and Request for Hearing ML12118A4682012-04-27027 April 2012 Answer of Florida Power & Light Company, NextEra Energy Seabrook, LLC, NextEra Energy Point Beach, LLC, and NextEra Energy Duane Arnold, LLC Opposing the Requests for Hearing of Pilgrim Watch and Beyond Nuclear on EA-12-050 with Regard to . ML0828000552008-10-0404 October 2008 Petitioners' Opposition to FPL Energy Point Beach, Llc'S Motion to Strike Saporit'S Reply and for Sanctions ML0827605172008-09-29029 September 2008 Submittal of Notification of Significant Licensing Action in the Matter of Point Beach Unit 1 ML0827605182008-09-29029 September 2008 Notification of Significant Licensing Action Re Amendment Application Dated May 28, 2008 ML0825901362008-09-15015 September 2008 Notice of Appearance of Lloyd B. Subin as Counsel for the U.S. Nuclear Regulatory Commission in the Matter of Point Beach Unit 1, License Amendment ML0825904462008-09-15015 September 2008 NRC Staff'S Answer to Saporito Energy Consultants' Petition to Intervene and Request for Hearing ML0825607692008-09-12012 September 2008 Notice of Appearance of Marcia J. Simon as Counsel for the U.S. Nuclear Regulatory Commission in the Matter of Point Beach, Unit 1 License Amendment ML0825507402008-09-11011 September 2008 Answer of FPL Energy Point Beach, LLC to Request for Hearing and Petition for Leave to Intervene of Saporito Energy Consultants, and Notice of Appearance for Antonio Fernandez, FPL Energy Point Beach, LLC 2022-01-01
[Table view] |
Text
OFFICE OF NUCLEAR REACTOR REGULATION NOTIFICATION OF SIGNIFICANT LICENSING ACTION LICENSEE: FPL Energy Point Beach, LLC Point Beach Nuclear Plant Unit 1 Docket No. 50-266
SUBJECT:
PROPOSED ISSUANCE OF A FINAL NO SIGNIFICANT HAZARDS CONSIDERATION DETERMINATION AND LICENSE AMENDMENT FOR WHICH A HEARING HAS BEEN REQUESTED (TAC NO. MD8800)
This is to inform the Commission that a final no significant hazards consideration determination and license amendment will be issued on or about October 5, 2008, to FPL Energy Point Beach, LLC. This action is being taken in response to the licensee=s amendment application dated May 28, 2008 (Agencywide Document Access and Management System (ADAMS) Accession No. ML081560178), and July 18, 2008 (ADAMS Accession No. ML082040226), and will modify Renewed Facility Operating License No. DPR-24 for Point Beach Nuclear Plant Unit 1 by a one cycle revision to the Point Beach Nuclear Plant (PBNP) Unit 1 technical specifications (TS). Specifically, TS 5.5.8, "Steam Generator (SG) Program," and TS 5.6.8, "Steam Generator Tube Inspection Report," will be revised to incorporate an interim alternate repair criterion into the provisions for SG tube repair for use during the Unit 1 2008 fall refueling outage and the subsequent operating cycle.
The Office of the Secretary received via E-Filing a petition to intervene and request for hearing submitted by Saporito Energy Consultants, dated August 20, 2008. The request was submitted in response to a notice issued by the U.S. Nuclear Regulatory Commission staff that provided an opportunity for a hearing on the license amendment for the PBNP Unit 1. The notice was published in the Federal Register at 73 FR 45479 thru 45481 (August 5, 2008). The request can be found in ADAMS under Accession No. ML082340924 and on the Electronic Hearing Docket. If granted, a hearing will not be completed prior to the issuance of the amendment.
Pursuant to the delegation by the Commission dated December 29, 1972, published in the Federal Register, 37 FR 28,710 (1972), and the Commissions regulations, see 10 C.F.R. §§ 2.104, 2.300, 2.303, 2.309, 2.311, 2.318, and 2.321, notice was given that an Atomic Safety and Licensing Board (Board) was established to preside over the proceeding. Answers in response to the petition to intervene and request for hearing were timely filed, by the Applicant and the Staff on or before September 22, 2008.
Saporito Energy Consultants replied within 7 days and the Board will usually have 45 days thereafter to issue a decision.
The State of Wisconsin will be notified.
CONTACT: Jack Cushing, DORL/NRR 301-415-1424