MONTHYEARML22262A3142022-10-0404 October 2022 Relief Requests 3IR-18 and 3IR-19, Relief from the Requirements of the ASME Code ML22116A2442022-04-26026 April 2022 Acceptance of Requested Licensing Action Relief Request 3IR-18 and 3IR-19 for End of Third 10-Year ISI Interval for Examinations with Limited Coverage ML20237F3442020-09-21021 September 2020 Authorization of Alternative (Relief Request 3IIR-7) from Certain Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (EPIDs L-2020-LLR-0055, L-2020-LLR-0056, and L-2020-LLR-0057) ML20101L0402020-04-10010 April 2020 Acceptance of Requested Licensing Action Relief Request to Use Code Case OMN-13 with 2012 Edition of the OM Code ML20101H3912020-04-0808 April 2020 Verbal Authorization for Seabrook Relief Request 3IIR-7 SBK-L-20049, Relief Request 3IIR-7, Proposed Alternative to Deter Examinations Beyond the 1 Year Code Allowable2020-04-0505 April 2020 Relief Request 3IIR-7, Proposed Alternative to Deter Examinations Beyond the 1 Year Code Allowable SBK-L-20017, Relief Request SG-1 Proposed Alternative in Accordance with 10 CFR 50.55a(z)(l), Use of Code Case OMN-13 with 2012 Edition of the OM Code2020-03-20020 March 2020 Relief Request SG-1 Proposed Alternative in Accordance with 10 CFR 50.55a(z)(l), Use of Code Case OMN-13 with 2012 Edition of the OM Code ML20076D2812020-03-17017 March 2020 Relief from the Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code ML19340A1282019-12-13013 December 2019 Relief from the Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code ML19249B1012019-09-30030 September 2019 Relief from the Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code; Relief Request RA-19-001 ML18106B1212018-04-25025 April 2018 Proposed Alternative to Use Encoded Phased Array Ultrasonic Examination Techniques L-2017-121, Proposed Alternative for the Use of Encoded Phased Array Ultrasonic Examination Techniques in Lieu of Radiography2017-07-24024 July 2017 Proposed Alternative for the Use of Encoded Phased Array Ultrasonic Examination Techniques in Lieu of Radiography ML17065A1482017-03-27027 March 2017 Relief from the Requirements of the ASME Code ML17080A0382017-03-27027 March 2017 Relief from the Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code SBK-L-17027, Relief Request RA-17-002, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2)2017-02-0606 February 2017 Relief Request RA-17-002, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2) ML16330A1182016-12-15015 December 2016 NextEra Fleet - Safety Evaluation for Proposed Alternative to the American Society of Mechanical Engineers Operation and Maintenance Code by Adoption of Approved Code Case OMN-20, Inservice Test Frequency (CAC Nos. MF8195 Through MF8201) ML14071A4102014-04-10010 April 2014 Request for Relief RA-14-001 from American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI Requirements Regarding the Reactor Vessel Head Flange Seal Leak Detection Piping (TAC No. Mfxxxx) ML12144A2402012-06-0404 June 2012 Second 10-Year Interval Inservice Inspection Program Plan Request for Relief No. 2lR-17 ML12145A1702012-06-0404 June 2012 Second 10-Year Interval Inservice Inspection Program Plan Request for Relief No. 2lR-20 SBK-L-11192, Request for Relief from ASME Code Case N-729-1 Requirements for Examination of Reactor Vessel Head Penetration Welds2011-10-27027 October 2011 Request for Relief from ASME Code Case N-729-1 Requirements for Examination of Reactor Vessel Head Penetration Welds ML1031901392010-11-22022 November 2010 Relief Request for Use of Alternate Depth Sizing Qualification, Third 10-Year Interval ML1023503412010-10-15015 October 2010 Relief Request for System Pressure Test Examinations on Class 1 Component Pressure Boundaries, Third 10-Year Interval ML1013801662010-06-0303 June 2010 Relief Request for Containment Building Spray Pump Bearing Vibration Alert Range Limit, Third 10-Year Interval SBK-L-09038, Supplement to Request for Relief from Inservice Inspection Requirements2009-02-24024 February 2009 Supplement to Request for Relief from Inservice Inspection Requirements SBK-L-08204, CFR 50-55a Request for Alternative Requirements for ASME Class 1 Upper Level Instrumentation Lines on the Pressurizer2008-12-11011 December 2008 CFR 50-55a Request for Alternative Requirements for ASME Class 1 Upper Level Instrumentation Lines on the Pressurizer SBK-L-08174, Request for Relief to Use of an Alternate Depth Sizing Qualification Requirement for Coordinated Implementation of ASME Section XI, Supplements 2 and 10 for Piping Examinations Performed from Inside Surface2008-09-30030 September 2008 Request for Relief to Use of an Alternate Depth Sizing Qualification Requirement for Coordinated Implementation of ASME Section XI, Supplements 2 and 10 for Piping Examinations Performed from Inside Surface SBK-L-08175, Request for Relief from Inservice Inspection Requirements2008-09-30030 September 2008 Request for Relief from Inservice Inspection Requirements ML0422603122004-10-12012 October 2004 Relief, American Society of Mechanical Engineers Boiler and Pressure Vessel Code - Relief for Class 3 Service Water Piping System ML0334400092004-02-0404 February 2004 Relief Inservice Testing Program Relief Request PR-3 ML0310705102003-05-30030 May 2003 Relief, from ASME Code Operations and Maintenance Code Istb 4.3(e)(1) Ten-Year Interval Inservice Test for Containment Spray Pumps CBS-P9A and CBS-P9B (Tac No. MB6676) ML0314100182003-05-0909 May 2003 Inservice Test Program Relief Request PR-3 ML0134603962002-01-28028 January 2002 Inservice Inspection Program Relief Requests 2AR-03, 2AR-04, 2AR-05, and 2IR-14 2022-04-26
[Table view] Category:Letter type:SBK
MONTHYEARSBK-L-24030, 2023 Annual Environmental Operating Report2024-04-12012 April 2024 2023 Annual Environmental Operating Report SBK-L-23053, Radiological Emergency Plan (Ssrep), Revision 802023-06-22022 June 2023 Radiological Emergency Plan (Ssrep), Revision 80 SBK-L-23031, 2022 Annual Radioactive Effluent Release Report2023-04-28028 April 2023 2022 Annual Radioactive Effluent Release Report SBK-L-23044, 2022 Annual Radiological Environmental Operating Report2023-04-28028 April 2023 2022 Annual Radiological Environmental Operating Report SBK-L-23033, 2022 Annual Environmental Operating Report2023-04-11011 April 2023 2022 Annual Environmental Operating Report SBK-L-22093, 75 Day and 150 Day Submittal Letters2022-12-0101 December 2022 75 Day and 150 Day Submittal Letters SBK-L-22113, Radiological Emergency Plan (Ssrep), Revision 792022-11-16016 November 2022 Radiological Emergency Plan (Ssrep), Revision 79 SBK-L-22114, Independent Spent Fuel Storage Installation (Isfsi), Cask Registration2022-11-0909 November 2022 Independent Spent Fuel Storage Installation (Isfsi), Cask Registration SBK-L-22112, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2022-11-0303 November 2022 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration SBK-L-22094, Relief Request 4RA-22-001, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2)2022-10-26026 October 2022 Relief Request 4RA-22-001, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2) SBK-L-22105, Supplement to 2021 Annual Radioactive Effluent Release Report2022-10-24024 October 2022 Supplement to 2021 Annual Radioactive Effluent Release Report SBK-L-22103, 5 to the Physical Security Plan, Training and Qualification Plan and Safeguards Contingency Plan2022-10-12012 October 2022 5 to the Physical Security Plan, Training and Qualification Plan and Safeguards Contingency Plan SBK-L-22102, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2022-10-0606 October 2022 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration SBK-L-22080, Submittal of 10 CFR 72.48 Report of Changes, Tests and Experiments for August 2020 to July 20222022-08-12012 August 2022 Submittal of 10 CFR 72.48 Report of Changes, Tests and Experiments for August 2020 to July 2022 SBK-L-22054, SBK-L-22054 - License Amendment Request 22-01, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2022-06-0909 June 2022 SBK-L-22054 - License Amendment Request 22-01, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections SBK-L-22042, 1 to Updated Final Safety Analysis Report, Cover Letter and Information on Enclosures 1 to 72022-05-0505 May 2022 1 to Updated Final Safety Analysis Report, Cover Letter and Information on Enclosures 1 to 7 SBK-L-22044, 2021 Annual Radioactive Effluent Release Report2022-04-29029 April 2022 2021 Annual Radioactive Effluent Release Report SBK-L-22036, Steam Generator Tube Inspection Report2022-04-25025 April 2022 Steam Generator Tube Inspection Report SBK-L-22040, Radiological Emergency Plan (Ssrep), Revision 7822022-04-20020 April 2022 Radiological Emergency Plan (Ssrep), Revision 782 SBK-L-22024, Response to Request for Additional Information (Raj) Regarding License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements2022-03-0707 March 2022 Response to Request for Additional Information (Raj) Regarding License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements SBK-L-22003, Inservice Inspection Examination Report2022-01-24024 January 2022 Inservice Inspection Examination Report SBK-L-21126, Fourth 10 Year Interval - Inservice Inspection (ISI) Program Plan2022-01-0404 January 2022 Fourth 10 Year Interval - Inservice Inspection (ISI) Program Plan SBK-L-21135, Submittal of Changes to the Seabrook Station Technical Specification Bases2021-12-29029 December 2021 Submittal of Changes to the Seabrook Station Technical Specification Bases SBK-L-21108, Core Operating Limits Report for Cycle 222021-11-0404 November 2021 Core Operating Limits Report for Cycle 22 SBK-L-21106, Transmittal of WCAP-18607-NP, Analysis of Capsule X from the NextEra Energy Seabrook Unit 1 Reactor Vessel Radiation Surveillance Program2021-09-30030 September 2021 Transmittal of WCAP-18607-NP, Analysis of Capsule X from the NextEra Energy Seabrook Unit 1 Reactor Vessel Radiation Surveillance Program SBK-L-21105, Withdrawal of Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink One-Time Allowed Outage Time (AOT) Extension2021-09-27027 September 2021 Withdrawal of Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink One-Time Allowed Outage Time (AOT) Extension SBK-L-21103, Request for Exercise of Enforcement Discretion2021-09-25025 September 2021 Request for Exercise of Enforcement Discretion SBK-L-21104, Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink Onetime Allowed Outage Time (AOT) Extension2021-09-25025 September 2021 Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink Onetime Allowed Outage Time (AOT) Extension SBK-L-21098, Supplement to License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements2021-09-22022 September 2021 Supplement to License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements SBK-L-21083, NextEra Energy Seabrook, LLC - Relief Request 3IR-18 and 3IR-19 for End of Third 10-Year ISI Interval for Examinations with Limited Coverage2021-08-18018 August 2021 NextEra Energy Seabrook, LLC - Relief Request 3IR-18 and 3IR-19 for End of Third 10-Year ISI Interval for Examinations with Limited Coverage SBK-L-21067, License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements2021-07-21021 July 2021 License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements SBK-L-21049, Revision to Updated Final Response to NRC Generic Letter 2004-022021-06-24024 June 2021 Revision to Updated Final Response to NRC Generic Letter 2004-02 SBK-L-21056, Response to Request for Additional Information Regarding Seabrook Steam Generator Tube Inspection Report Review References:2021-05-20020 May 2021 Response to Request for Additional Information Regarding Seabrook Steam Generator Tube Inspection Report Review References: SBK-L-21044, 2020 Annual Radiological Environmental Operating Report2021-04-30030 April 2021 2020 Annual Radiological Environmental Operating Report SBK-L-21045, Submittal of 2020 Annual Radioactive Effluent Release Report2021-04-30030 April 2021 Submittal of 2020 Annual Radioactive Effluent Release Report SBK-L-21042, Response to RIS 2021-01 Preparation and Scheduling of Operator Licensing Examinations2021-04-22022 April 2021 Response to RIS 2021-01 Preparation and Scheduling of Operator Licensing Examinations SBK-L-21033, Response to Request for Additional Information (RAI) Regarding License Amendment Request (LAR) 20-02, Resolve Non-Conservative Heat Flux Hot Channel Factor (Fo(Z)) Requirements2021-03-24024 March 2021 Response to Request for Additional Information (RAI) Regarding License Amendment Request (LAR) 20-02, Resolve Non-Conservative Heat Flux Hot Channel Factor (Fo(Z)) Requirements SBK-L-21023, Radiological Emergency Plan (Ssrep), Revision 772021-03-0404 March 2021 Radiological Emergency Plan (Ssrep), Revision 77 SBK-L-20154, Submittal of Changes to the Seabrook Station Technical Specification Bases2020-12-22022 December 2020 Submittal of Changes to the Seabrook Station Technical Specification Bases SBK-L-20149, Response to Request for Additional Information in Respect to One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-12-0808 December 2020 Response to Request for Additional Information in Respect to One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic SBK-L-20146, One-Time Exemption Request for the Biennial Emergency Preparedness Exercise Requirements of 10 CFR 50, Appendix E. IV.F.2.b and IV.F.2.c2020-12-0303 December 2020 One-Time Exemption Request for the Biennial Emergency Preparedness Exercise Requirements of 10 CFR 50, Appendix E. IV.F.2.b and IV.F.2.c SBK-L-20144, Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-11-23023 November 2020 Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic SBK-L-20143, Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 004-022020-11-19019 November 2020 Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 004-02 SBK-L-20132, Fourth Interval Inservice Testing (IST) Program2020-10-21021 October 2020 Fourth Interval Inservice Testing (IST) Program SBK-L-20127, Generator Tube Inspection Report2020-10-20020 October 2020 Generator Tube Inspection Report SBK-L-20117, Response to Request for Additional Information Regarding Technical Specification 3/4.8.1 for a One-Time Extension of Allowed Outage Time License Amendment Request2020-09-23023 September 2020 Response to Request for Additional Information Regarding Technical Specification 3/4.8.1 for a One-Time Extension of Allowed Outage Time License Amendment Request SBK-L-20103, Inservice Inspection Examination Report2020-07-27027 July 2020 Inservice Inspection Examination Report SBK-L-20092, Response to Request for Additional Information Regarding License Amendment Requests to Adopt TSTF-411 and TSTF-4182020-07-13013 July 2020 Response to Request for Additional Information Regarding License Amendment Requests to Adopt TSTF-411 and TSTF-418 SBK-L-20068, License Amendment Request 20-01, One-Time Change to the Seabrook Technical Specifications A.C. Sources - Operating2020-07-13013 July 2020 License Amendment Request 20-01, One-Time Change to the Seabrook Technical Specifications A.C. Sources - Operating SBK-L-20085, Supplement to Exemption Request for Access Authorization and Fitness for Duty Requirements Due to COVID-19 Pandemic2020-06-16016 June 2020 Supplement to Exemption Request for Access Authorization and Fitness for Duty Requirements Due to COVID-19 Pandemic 2024-04-12
[Table view] |
Text
FPL Energy Seabrook Station FPL Energy P.O. Box 300 Seabrook, NH 03874 Seabrook Station (603) 773-7000 September 30, 2008 Docket No. 50-443 SBK-L-08174 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001 Seabrook Station Request for Use of an Alternate Depth Sizing Qualification Pursuant to 10 CFR 50.55a(a)(3)(i), FPL Energy Seabrook, LLC (FPL Energy Seabrook) requests approval for use of an alternate depth sizing qualification on reactor pressure vessel (RPV) nozzle-to-safe end dissimilar metal (DM) welds and safe end-to-pipe welds from the inside surface.
FPL Energy Seabrook is performing volumetric examinations on RPV nozzle-to-safe end DM welds and safe end-to-pipe welds from the inside surface utilizing the ultrasonic (UT) examination technique during the upcoming end-of-interval ten-year inservice inspection (ISI). FPL Energy Seabrook will implement the NRC approved alternative requirements of Code Cases N-695 and N-696 as described in Attachment 1 of this letter.
Code Cases N-695 and N-696 require that examination procedures and personnel demonstrate a depth sizing error of less than 0.125-inch root mean square (RMS). FPL Energy Seabrook proposes the use of an alternative RMS depth sizing error that is greater than the 0.125-inch RMS error value stated in Code Cases N-695 and N-696.
ASME Code Section XI (Appendix VIII), Code Case N-695 and Code Case N-696 require that the maximum error for flaw depth measurements, when compared to the true flaw depth, must not exceed 0.125-inch RMS error. The nuclear power industry has attempted to qualify personnel and procedures for examinations performed from the inside surface of DM welds (Supplement 10, Code Case N-695) and austenitic similar metal welds (Supplement 2, Code Case N-696) since November 2002. The most recent attempt at achieving the 0.125-inch RMS was in early 2008. This attempt as well as all previous attempts did not achieve the required RMS values for personnel or procedures.
The difficulties are associated with the surface roughness of the field welds. At this time, achieving a 0.125-inch maximum RMS error is impractical. The vendor that FPL Energy Seabrook has chosen achieved a 0.189-inch RMS in their Supplement 10 (Code Case N-A lf F r an FPL Group company
'U. S. Nuclear Regulatory Commission SBK-L-08174 Page 2 695) performance demonstration and a 0.245-inch RMS error in their coordinated implementation of Supplements 2 and 10 (Code Case N-696).
FPL Energy Seabrook requests review and approval of this proposal to support the Seabrook Unit 1 refueling outage in the fall of 2009. Similar alternatives have been submitted for NRC review and approval and are referenced in the attached request.
If you have any questions regarding this submittal, please contact Mr. Michael O'Keefe, Licensing Manager, at (603) 773-7745.
Sincerely, FPL Energy Seabrook, LLC Gene St. Pierre Site Vice President cc: S. J. Collins, NRC Region I Administrator G. E. Miller, NRC Project Manager W. J. Raymond, NRC Resident Inspector to SBK-L-08174 ATTACHMENT 1 10 CFR 50.55a Request Proposed Alternative in Accordance with 10 CFR 50.55a(a)(3)(i)
REQUEST FOR RELIEF TO USE AN ALTERNATIVE DEPTH SIZING QUALIFICATION REQUIREMENT FOR THE COORDINATED IMPLEMENTATION OF ASME SECTION XI, SUPPLEMENTS 2 AND 10 FOR PIPING EXAMINATIONS PERFORMED FROM THE INSIDE SURFACE FOR SEABROOK UNIT 1 ASME Code Components Affected Code class: 1 System: RC Examination Categories: R-A, Risk Informed Inservice Inspection Program TABLE I WELD NUMBERS BY ISI DESIGNATION Item Location Nozzle-to-Safe End Weld Safe End-to-Pipe Weld 1 RPV "A" Outlet Nozzle @2020 RC RPV-SE-301-121-A RC 0001-01 01 2 RPV "B" Inlet Nozzle, @2470 RC RPV-SE-302-121-B RC 0003-01 03 3 RPV "C" Inlet Nozzle, @2930 RC RPV-SE-302-121-C RC 0006-01 03 4 RPV "D" Outlet Nozzle, @338' RC RPV-SE-301-121-D RC 0004-01 01 5 RPV "E" Outlet Nozzle, @22' RC RPV-SE-301-121-E RC 0007-01 01 6 RPV "F" Inlet Nozzle, @67' RC RPV-SE-302-121-F RC 0009-01 03 7 RPV "G" Inlet Nozzle, @1130 RC RPV-SE-302-121-G RC 0012-01 03 8 RPV "H" Outlet Nozzle, @158' RC RPV-SE-301-121-H RC 0010-01 01
=
Applicable Code Edition and Addenda===
FPL Energy Seabrook, LLC (FPL Energy Seabrook) is currently in the 2nd 10-year inservice inspection (ISI) interval. The American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (Code) of record for the current 10-year ISI interval isSection XI, 1995 Edition, including Addenda through 1996 (Reference 1).
Applicable Code Requirement
The examination of Class 1 and 2 piping welds is required to be performed using procedures, personnel and equipment qualified to the criteria of the applicable ASME Code,Section XI, Appendix VIII, Supplements 2 and 10. The applicable supplements to this relief are Supplement 2, "QUALIFICATION REQUIREMENTS FOR WROUGHT AUSTENITIC PIPING WELDS" and Supplement 10, "QUALIFICATION REQUIREMENTS FOR DISSIMILAR METAL PIPING WELDS".
Paragraph 3.2, "Sizing Acceptance Criteria," Subparagraph (b) of Supplement 2, states that the "examination procedures, equipment, and personnel are qualified for depth-sizing if the results of the performance demonstration satisfy the following criteria: the RMS error of the flaw depths estimated by ultrasonics, as compared with the true flaw depths, shall not exceed 0.125-inch."
Paragraph 3.2;' "Sizing Acceptance Criteria," Subparagraph (b) of Supplement 10, states that the "examination procedures, equipment, and personnel are qualified for depth-sizing when the RMS [root mean square] error of the flaw depth measurements, as compared to the true flaw depths, is less than or equal to 0.125-inch (3.2mm)."
Code Case N-695, "Qualification Requirements for Dissimilar Metal Piping Welds,Section XI, Division 1," provides alternative requirements to Appendix VIII, Supplement 10. Paragraph 3.3(c) of Code Case N-695 states, "Examination procedures, equipment, and personnel are qualified for depth-sizing when the RMS error of the flaw depth measurements, as compared to the true flaw depths, do not exceed 0.125-in. (3 mm)." Code Case N-695 is unconditionally approved for use through Regulatory Guide 1.147, "In-service Inspection Code Case Acceptability, ASME Section XI, Division 1," Revision 15.
Code Case N-696, "Qualification Requirements for Appendix VIII Piping Examinations Conducted From the Inside Surface," provides alternative requirements to Appendix VIII, Supplements 2, 3 and 10 when performed from the inside surface. Paragraph 3.3(d) of Code Case N-696 states, "Supplement 2 or Supplement 3 examination procedures, equipment and personnel are qualified for depth-sizing when the RMS error of the flaw depth measurements, as compared to the true flaw depths, do not exceed 0.125-in. (3 mm) RMS, when combined with a successful Supplement 10 qualification."
=
Reason for Request===
FPL Energy Seabrook is performing volumetric examination of RPV nozzle-to-safe end dissimilar metal (DM) welds and the adjacent safe end-to-pipe welds from the inside surface during the upcoming ten-year RPV IS1.
FPL Energy Seabrook will implement the NRC-approved alternative requirements of Code Cases N-695 and N-696 for the qualification of procedures and personnel for examinations performed during the upcoming ten- year RPV ISI.
Code Cases N-695 and N-696 require that qualified procedures and personnel shall demonstrate a flaw depth sizing error less than or equal to 0.125 RMS. To date, no personnel or procedure has achieved less than or equal to the ASME Code required 0.125 inch RMS error. This has been verified in the EPRI letter dated June 30, 2008 (Reference 2).
The inability of the examination procedures to achieve the required RMS value is primarily due to a combination of factors such as surface condition, scan access, base materials and the effect of the dendritic structure of the welds themselves. The combination of all of these factors has proven too difficult for the procedures and personnel to achieve an RMS value that meets the current Code requirements or Code Case N-695 and N-696.
Proposed Alternative and Basis for Use FPL Energy Seabrook proposes using an alternative depth-sizing RMS error value greater than the 0.125-inch RMS error value stated in Code Cases N-695 and N-696. Pursuant to 10 CFR 50.55a(a)(3)(i), relief is requested to use an alternative that will provide an acceptable level of quality and safety.
As an alternative to the ASME Code-required RMS error for procedure and personnel depth sizing, FPL Energy Seabrook will add the difference between the ASME Code required RMS value of 0.125-inch RMS and the actual RMS value achieved by FPL Energy Seabrook's inspection vendor to the flaw depth as determined during flaw sizing. The inspection vendor chosen has achieved an RMS of 0.189" for Supplement 10 welds and an RMS of 0.367" for Supplement 2.
Applying the difference between the required RMS error and the achieved RMS error to the actual flaw size, will ensure a conservative flaw bounding approach and provide an acceptable level of quality and safety.
Precedents Similar relief requests have been granted to the following plants:
NRC to Southern Nuclear Operating Company Inc. letter, "Joseph M. Farley Nuclear Plant Unit 1, and Vogtle Electric Generating Plant, Units 1 and 2 - Evaluation of Relief Request ISI-GEN-ALT-06-02," (TAC Nos. MD 2482, MD2483 and MD2484), dated September 29, 2006 (ML062770359).
NRC to Exelon Generating Company, LLC letter, "Braidwood Station, Units 1 and 2 -
Relief Request (12R-49) Regarding In-service Inspection Program Alternative Method (TAC Nos. MD5996 and MD5997)," dated November 8, 2007 (ML072760048).
Duration of Proposed Alternative The alternative requirements of this request will be applied for the duration of up to and including the last outage of the current 2nd 10-year ISI interval.
References
- 1. ASME Code,Section XI, 1995 Edition, including Addenda through 1996.
- 2. EPRI Letter Dated 6/30/08, "Summary of WESDYNE International, LLC Supplements 2 & 10 depth sizing results obtained from the inside surface."