Inspection/Activity Plan, 09/02-2008 - 12/31/2009, Report 22
ML082460993
Person / Time
Site: Watts Bar  Tennessee Valley Authority icon.png
Issue date: 09/02/2008
From:
Reactor Projects Region 2 Branch 6
To:
References
Download: ML082460993 (2)


Text

Watts Bar Inspection / Activity Plan 09/02/2008 - 12/31/2009 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 09/02/2008 08:16:14 Report 22 1

TI-176

- EDG TECH SPEC SURV ENDURANCE MARGIN TEST Generic Safety Inspection Emergency Diesel Generator Tech Spec Surveillance Requirements Re: Endurance & Margin Testing 09/02/2008 12/31/2008 1

2515/176 IP 3

TI-171

- B.5.B PHASE 2&3 Generic Safety Inspection Verification of Site Specific Implementation Of B.5.b Phase 2 & 3 Mitigating Strategies 09/29/2008 10/03/2008 1

2515/171 IP 1

PSB1-EP

- EP INSP Baseline Inspections Emergency Response Organization, Drill/Exercise Performance Indicator, Program Review 10/20/2008 10/24/2008 1

2515/175 IP EP Baseline Inspection Alert and Notification System Testing 10/20/2008 10/24/2008 1

7111402 IP EP Baseline Inspection Emergency Response Organization Augmentation Testing 10/20/2008 10/24/2008 1

7111403 IP EP Baseline Inspection Emergency Action Level and Emergency Plan Changes 10/20/2008 10/24/2008 1

7111404 IP EP Baseline Inspection Correction of Emergency Preparedness Weaknesses and Deficiencies 10/20/2008 10/24/2008 1

7111405 IP Baseline Inspections Drill/Exercise Performance 10/20/2008 10/24/2008 1

71151-EP01 IP Baseline Inspections ERO Drill Participation 10/20/2008 10/24/2008 1

71151-EP02 IP Baseline Inspections Alert & Notification System 10/20/2008 10/24/2008 1

71151-EP03 IP 2

OL RQ

- REQUAL INSPECTION Baseline Inspections Licensed Operator Requalification Program 12/08/2008 12/12/2008 1

7111111B IP 5

EB1-MODS - MODIFICATIONS-10CFR50.59 Baseline Inspections Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 01/19/2009 01/30/2009 1

7111117 IP 3

OL EXAM

- INITIAL EXAM PREP Not Applicable WATTS BAR/MARCH 2009 EXAM AT POWER FACILITIES 02/09/2009 02/13/2009 1

V23316 3

OL EXAM

- INITIAL EXAM - WEEK 1 Not Applicable WATTS BAR/MARCH 2009 EXAM AT POWER FACILITIES 03/09/2009 03/13/2009 1

V23316 3

OL EXAM

- INITIAL EXAM - WEEK 2 Not Applicable WATTS BAR/MARCH 2009 EXAM AT POWER FACILITIES 03/23/2009 03/27/2009 1

V23316 6

PI&R

- PROBLEM IDENTIFICATION AND RESOLUTION Baseline Inspections Identification and Resolution of Problems 06/08/2009 06/12/2009 1

71152B IP Baseline Inspections Identification and Resolution of Problems 06/22/2009 06/26/2009 1

71152B IP 1

EB3-HS

- HEAT SINK Baseline Inspections Heat Sink Performance 08/03/2009 08/07/2009 1

7111107B IP 1

PSB1-RP

- RP PUBLIC PREINSPECTION VISIT Baseline Inspections Access Control to Radiologically Significant Areas 08/03/2009 08/07/2009 1

7112101 IP 3

PSB1-RP

- RADIATION PROTECTION PUBLIC INSPECTION Baseline Inspections Radiation Monitoring Instrumentation and Protective Equipment 08/31/2009 09/04/2009 1

7112103 IP Baseline Inspections Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 08/31/2009 09/04/2009 1

7112201 IP Baseline Inspections Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 08/31/2009 09/04/2009 1

7112203 IP Baseline Inspections RETS/ODCM Radiological Effluent 08/31/2009 09/04/2009 1

71151-PR01 IP This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Watts Bar Inspection / Activity Plan 09/02/2008 - 12/31/2009 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 09/02/2008 08:16:14 Report 22 1

EB3ISI

- INSERVICE INSPECTION Baseline Inspections Inservice Inspection Activities - PWR 09/28/2009 10/02/2009 1

7111108P IP 1

EB3TI172

- TI-172 RCS DM BUTT WELDS Generic Safety Inspection Reactor Coolant System Dissimiliar Metal Butt Welds 09/28/2009 10/02/2009 1

2515/172 IP 4

OL EXAM

- INITIAL EXAM PREP Not Applicable WATTS BAR/SEPTEMBER 2009 EXAM AT POWER FACILITIES 09/28/2009 10/02/2009 1

V23317 1

PSB1-RP

- RP ACCESS CONTROLS INSPECTION (OUTAGE)

Baseline Inspections Access Control to Radiologically Significant Areas 09/28/2009 10/02/2009 1

7112101 IP 4

OL EXAM

- INITIAL EXAM - WEEK 1 Not Applicable WATTS BAR/SEPTEMBER 2009 EXAM AT POWER FACILITIES 10/19/2009 10/23/2009 1

V23317 3

OL EXAM

- INITIAL EXAM - WEEK 2 Not Applicable WATTS BAR/SEPTEMBER 2009 EXAM AT POWER FACILITIES 10/26/2009 10/30/2009 1

V23317 3

PSB1EP

- EMERGENCY PREPAREDNESS EXERCISE Baseline Inspections Emergency Response Organization, Drill/Exercise Performance Indicator, Program Review 11/02/2009 11/06/2009 1

2515/175 IP EP Baseline Inspection Exercise Evaluation 11/02/2009 11/06/2009 1

7111401 IP EP Baseline Inspection Emergency Action Level and Emergency Plan Changes 11/02/2009 11/06/2009 1

7111404 IP Baseline Inspections Drill/Exercise Performance 11/02/2009 11/06/2009 1

71151-EP01 IP Baseline Inspections ERO Drill Participation 11/02/2009 11/06/2009 1

71151-EP02 IP Baseline Inspections Alert & Notification System 11/02/2009 11/06/2009 1

71151-EP03 IP This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.