Brunswick Inspection / Activity Plan 09/01/2008 - 12/31/2009 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 09/02/2008 16:37:20 Report 22 3
TI-171
- B.5.B PHASE 2&3 Generic Safety Inspectio Verification of Site Specific Implementation Of B.5.b Phase 2 & 3 Mitigating Strategies 09/15/2008 09/19/2008 1, 2 2515/171 IP 3
OL EXAM
- INITIAL EXAM PREP Not Applicable BRUNSWICK/DECEMBER 2008 EXAM AT POWER FACILITIES 10/06/2008 10/10/2008 1
V23291 8
EB2-TFP
- TRIENNIAL FIRE PROTECTION Baseline Inspections Fire Protection-NFPA 805 Transition Period [Triennial]
11/03/2008 11/07/2008 1, 2 7111105P IP Baseline Inspections Fire Protection-NFPA 805 Transition Period [Triennial]
11/17/2008 11/21/2008 1, 2 7111105P IP 2
- ISFSI PAD FORM & REBAR & CONCRETE Other Routine On-Site Fabrication Of Components And Construction On An ISFSI 11/03/2008 11/07/2008 1, 2 60853 IP 3
OL EXAM
- INITIAL EXAM Not Applicable BRUNSWICK/DECEMBER 2008 EXAM AT POWER FACILITIES 11/03/2008 11/07/2008 1
V23291 3
- REQUAL INSPECTION Baseline Inspections Licensed Operator Requalification Program 11/17/2008 11/21/2008 1, 2 7111111B IP 3
PSB1-EP
- EMERGENCY PREPAREDNESS EXERCISE Baseline Inspections Emergency Response Organization, Drill/Exercise Performance Indicator, Program Review 11/17/2008 11/21/2008 1, 2 2515/175 IP EP Baseline Inspection Exercise Evaluation 11/17/2008 11/21/2008 1, 2 7111401 IP EP Baseline Inspection Emergency Action Level and Emergency Plan Changes 11/17/2008 11/21/2008 1, 2 7111404 IP Baseline Inspections Drill/Exercise Performance 11/17/2008 11/21/2008 1, 2 71151-EP01 IP Baseline Inspections ERO Drill Participation 11/17/2008 11/21/2008 1, 2 71151-EP02 IP Baseline Inspections Alert & Notification System 11/17/2008 11/21/2008 1, 2 71151-EP03 IP 1
PSB1-RP
- RP OCCUPATIONAL PRE INSPECTION VISIT Other Routine Operation of an Independent Spent Fuel Storage Installation at Operating Plants 02/02/2009 02/04/2009 1, 2 60855.1 IP Baseline Inspections Access Control to Radiologically Significant Areas 02/02/2009 02/04/2009 1, 2 7112101 IP 1
EB3ISI
- UNIT 2 INSERVICE INSPECTION Baseline Inspections Inservice Inspection Activities - BWR 03/09/2009 03/13/2009 2
7111108G IP 3
PSB1-RP
- RP OCCUPATIONAL BASELINE WEEK1 Baseline Inspections Access Control to Radiologically Significant Areas 03/09/2009 03/13/2009 1, 2 7112101 IP Baseline Inspections ALARA - Required 03/09/2009 03/13/2009 1, 2 7112102-7112102R IP Baseline Inspections Radioactive Material Processing and Transportation 03/09/2009 03/13/2009 1, 2 7112202 IP Baseline Inspections Occupational Exposure Control Effectiveness 03/09/2009 03/13/2009 1, 2 71151-OR01 IP Baseline Inspections RETS/ODCM Radiological Effluent 03/09/2009 03/13/2009 1, 2 71151-PR01 IP 2
PSB1-RP
- RADIATION PROTECTION OCCUPATIONAL WK2 Baseline Inspections Access Control to Radiologically Significant Areas 03/23/2009 03/27/2009 1, 2 7112101 IP Baseline Inspections ALARA Planning and Controls 03/23/2009 03/27/2009 1, 2 7112102 IP Baseline Inspections Radioactive Material Processing and Transportation 03/23/2009 03/27/2009 1, 2 7112202 IP This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Brunswick Inspection / Activity Plan 09/01/2008 - 12/31/2009 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 09/02/2008 16:37:20 Report 22 2
PSB1-RP
- RADIATION PROTECTION OCCUPATIONAL WK2 Baseline Inspections Occupational Exposure Control Effectiveness 03/23/2009 03/27/2009 1, 2 71151-OR01 IP Baseline Inspections RETS/ODCM Radiological Effluent 03/23/2009 03/27/2009 1, 2 71151-PR01 IP 5
- PROBLEM IDENTIFICATION AND RESOLUTION Baseline Inspections Identification and Resolution of Problems 04/20/2009 04/24/2009 1, 2 71152B IP Baseline Inspections Identification and Resolution of Problems 05/04/2009 05/08/2009 1, 2 71152B IP 1
EB3-HS
- HEAT SINK Baseline Inspections Heat Sink Performance 07/06/2009 07/10/2009 1, 2 7111107B IP 3
OL EXAM
- INITIAL EXAM PREP Not Applicable BRUNSWICK/NOVEMBER 2009 EXAM AT POWER FACILITIES 10/26/2009 10/30/2009 1
V23322 3
OL EXAM
- INITIAL EXAM - WEEK 1 Not Applicable BRUNSWICK/NOVEMBER 2009 EXAM AT POWER FACILITIES 11/16/2009 11/20/2009 1
V23322 1
PSB1EP
- EMERGENCY PREPAREDNESS INSPECTION EP Baseline Inspection Alert and Notification System Testing 11/16/2009 11/20/2009 1, 2 7111402 IP EP Baseline Inspection Emergency Response Organization Augmentation Testing 11/16/2009 11/20/2009 1, 2 7111403 IP EP Baseline Inspection Emergency Action Level and Emergency Plan Changes 11/16/2009 11/20/2009 1, 2 7111404 IP EP Baseline Inspection Correction of Emergency Preparedness Weaknesses and Deficiencies 11/16/2009 11/20/2009 1, 2 7111405 IP Baseline Inspections Drill/Exercise Performance 11/16/2009 11/20/2009 1, 2 71151-EP01 IP Baseline Inspections ERO Drill Participation 11/16/2009 11/20/2009 1, 2 71151-EP02 IP Baseline Inspections Alert & Notification System 11/16/2009 11/20/2009 1, 2 71151-EP03 IP 3
OL EXAM
- INITIAL EXAM - WEEK 2 Not Applicable BRUNSWICK/NOVEMBER 2009 EXAM AT POWER FACILITIES 11/30/2009 12/04/2009 1
V23322 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.